Service Agreement No. 125
Attachment 5
Additional Operating Requirements for the Transmission Owner's
Transmission System and Affected Systems Needed to Support
the Interconnection Customer's Needs
The Transmission Owner shall also provide requirements that must be met by the Interconnection Customer prior to initiating parallel operation with the Transmission Owner's Transmission System.
It is acknowledged that the Small Generating Facility, Interconnection Facilities, and metering equipment are existing and in service at the time of signing of this agreement and that there are no further requirements to continue parallel operation of the Small Generating Facility with the Transmission Owner's Transmission System.
Effective Date: 10/12/2010 - Docket #: ER10-2561-000 - Page 1