NYISO Tariffs --> Open Access Transmission Tariff (OATT) --> 40 Attachment HH - Standard Interconnection Procedures --> 40.25 OATT Att HH Appendices to Attachment HH --> 40.25.2 OATT Att HH Appendix 2 CRIS-Only Request

40.25.2APPENDIX 2 TO ATTACHMENT HH

CRIS-ONLY REQUEST

  1. The undersigned Interconnection Customer who submits this request is proposing to develop or own a proposed or an existing Facility requesting Capacity Resource Interconnection Service (“CRIS”).

 

  1. Legal Name of the Interconnection Customer (or, if an individual, individual’s name) (must be a single individual or entity):

 

Name of Interconnection Customer :                      

Contact Person:                              

Title                                                    

Address:                           

Email:                                            

 

Telephone:                                   

 

  1. Type of CRIS-Only Request:

____ CRIS or increased CRIS for an existing facility

____ CRIS or increased CRIS for a facility that is not existing but has ERIS

____ Different location CRIS Transfer (skip to question 13)

____ External CRIS Rights Request (skip to question 14)

 

  1. Queue Position/PTID No./TO or NYSIR queue no. (if applicable): _________________ 

 

  1. Project/facility name:

 

  1. Is this Project mutually exclusive with another project proposed by the Interconnection Customer or its Affiliate in the current ongoing Expedited Deliverability Study, Class Year Study, or Cluster Study?

      ____Yes                     ____No

    If yes:

Indicate the Queue Position/PTID No./TO or NYSIR queue no. (if applicable): _________

Is the Interconnection Customer submitting the Project as a Contingent Project in accordance with Section 40.5.4.1? ____Yes                     ____No

 

  1. Address or location or the proposed new Facility site (to the extent known) or, in the case of an existing Facility, the name and specific location of that existing facility:                                                                                                                                                                                                                                                                                                                                                                                                                                               

 

  1. MW nameplate rating: ________ at _______ ° F (if temperature sensitive)

MW of requested CRIS at the POI: ________

 

 

  1. If a Cluster Study Transmission Project, which of the following forms of CRIS does the Interconnection Customer intend to request:

 

____ Unforced Capacity Deliverability Rights

____ External-to-Rest of State Deliverability Rights

  1. General description of the proposed Project (e.g.: describe type/size/number/general configuration of the proposed generator units, transmission, transformers, feeders, lines leading to the proposed point of interconnection(s), breakers, etc.):

               

 

                

 

                

 

  1. Attach a conceptual breaker one-line diagram of the plant and station facilities.  For staged projects, please indicate future generation, transmission circuits, etc.

 

The conceptual breaker one-line diagram is a representation of electrical components that are connecting into the NYSTS or Distribution System as applicable. This conceptual breaker one-line diagram should include, at a minimum:

Acronyms used in the conceptual breaker one-line diagram should follow ANSI Standard Device Numbers & Common Acronyms.

  1. A workable Project power flow, short circuit, transient stability modeling data and supporting documentation (as set forth in Attachment A) must be provided with this CRIS-Only Request form.
  2. Proposed Initial Backfeed Date (Month/Year):                                                                                                      

Proposed Synchronization Date (Month/Year):                                                 

Proposed Commercial Operation Date (Month/Year):                                                 

  1. If requesting a CRIS transfer, indicate the following:

 

 

  1. If requesting External CRIS, indicate the following:

 

  1. Detailed generating facility data specified in Attachment A must be submitted with this CRIS-Only Request form.

 

  1. $5,000 non-refundable Application Fee must be submitted with this CRIS-Only Request form in accordance with Section 40.5.5.1.3 of Attachment HH.

 

  1. A $50,000 Study Deposit must be submitted with this CRIS-Only Request form pursuant to Section 40.5.5.1.4 of Attachment HH.

 

  1. By submitting this CRIS-Only Request:

 

Interconnection Customer represents and warrants that the information and materials it provides with this CRIS-Only Request are accurate and complete as of the time of this submission.

 

Interconnection Customer acknowledges that it will be required to execute a Cluster Study Agreement with the NYISO, Connecting Transmission Owner, and any identified Affected Transmission Owner(s) or Affected System Owner(s) following the validation of this CRIS-Only Request.

 

Interconnection Customer acknowledges and agrees that it shall pay the study costs incurred under the requirements of the NYISO’s Standard Interconnection Procedures in Attachment HH to the NYISO OATT and ISO Procedures in connection with this CRIS-Only Request, including any study costs that are incurred prior to the full execution of the Cluster Study Agreement for this CRIS-Only Request.

 

[This CRIS-Only Request to be signed by an officer of the Interconnection Customer or a person authorized to sign for the Interconnection Customer]

 

Signature: 

Name (type or print): 

Title: 

Company: 

Date: 

ATTACHMENT A


DETAILED GENERATING FACILITY DATA


(Not Applicable for CRIS Transfer and External CRIS Rights Requests)

(Additional data maybe required at subsequent stages of the Cluster Study Process)

 

  1.                                                                                                                                                                                                                                                                                                                        Describe the composition of assets (including MW level) within the Generating Facility, including load reduction assets (e.g., 50 MW wind facility, 20 MW Energy Storage Resource and a load reduction resource with a maximum of 1 MW of load reduction):             

___________________________________________________________________________

  1.                                                                                                                                                                                                                                                                                                                        Maximum Injection Capability of entire Generating Facility over 1 hour:

              ___________________________________________________________________________

  1.                                                                                                                                                                                                                                                                                                                        If the facility includes a Resource with Energy Duration Limitations, indicate the maximum injection capability for the entire Generating Facility over the selected duration (e.g., 100 MW over 4 hours):              
  2.                                                                                                                                                                                                                                                                                                                        Provide the following information for each unit within the Generating Facility:

Resource/Fuel type:

___ Solar

___ Wind

___ Hydro ___Hydro Type (e.g. Run-of-River):         

___ Diesel 

___ Natural Gas 

___ Fuel Oil

___ Other (state type)

Generator Nameplate Rating:  _______MW (Typical)

MVA _________°F ___________Voltage (kV)__________

Maximum Reactive Power at Rated Power Leading (MVAR): ___

Minimum Reactive Power at Rated Power Lagging (MVAR): ___

Customer-Site Load: _______________MW

Existing load? Yes ___ No___

If existing load with metered load data, provide coincident Summer peak load: ________________________________________________________________________

If new load or existing load without metered load data, provide estimated coincident Summer peak load, together with supporting documentation for such estimated value: _______________________________________________________________________

Typical Reactive Load: ___________________________MVAR

Generator manufacturer, model name & number: ___________________________

Inverter manufacturer, model name, number, and version: ___________________________

 

Nameplate Output Power Rating in MW:* (Summer) (Winter)

Nameplate Output Power Rating in MVA: (Summer)                           (Winter)              

* The Nameplate Output Power Rating is at the inverter terminal for IBRs

 

If solar, total number of solar panels in solar farm to be interconnected pursuant to this CRIS-Only Request:                 

Inverter manufacturer, model name, number, and version: ­­

 

If wind, total number of generators in wind farm to be interconnected pursuant to this CRIS-Only Request:                 

Generator Height: Single phaseThree Phase

Wind Model Type: ___Type 1 ___ Type 2 ___ Type 3 ___ Type 4

 

If an Energy Storage Resource or a Resource with Energy Duration Limitations:

Inverter manufacturer, model name, number, and version:   

Energy storage capability (MWh):  

Minimum Duration for full discharge (i.e., injection) (Hours):                                                  

Minimum Duration for full charge (i.e., withdrawal) (Hours):               ________________                             

Maximum withdrawal from the system (i.e., when charging) (MW):               __________                             

Maximum sustained hour injection in MW hours (calculated at the Minimum Duration for full discharge):                                          

Primary frequency response operating range for electric storage resource:                                         

Minimum State of Charge:   (%)

Maximum State of Charge:                  (%)

 

  1. Attach modeling data files:*

* PSSE files must be in .raw or .sav and .dyr format. ASPEN files must be in .olr format.

 

ADDITIONAL INFORMATION REQUESTED FOR CLUSTER STUDY TRANSMISSION PROJECTS

 

Description of proposed project:

  1. General description of the equipment configuration and kV level:

_______________________________________________________________

_______________________________________________________________

  1. Transmission technology and manufacturer (e.g., HVDC VSC):

 

_______________________________________________________________

_______________________________________________________________

 

 

 

Effective Date: 5/2/2024 - Docket #: ER24-1915-000 - Page 1