NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
FERC rendition of the electronically filed tariff records in Docket No. ER20--000
Filing Data:
CID: C000038
Filing Title: SGIA NMPC LaChute Hydro SA 2511 Company Filing Identifier: 1561
Type of Filing Code: 10
Associated Filing Identifier: [if applicable]
Tariff Title: NYISO Agreements
Tariff ID: 58
Payment Confirmation: N
Suspension Motion:
Tariff Record Data:
Record Content Description: Agreement No. 2511
Tariff Record Title: NMPC LaChute Hydro Small Generator Interconnection Agreement Record Version Number: 0.0.0
Option Code: A
Tariff Record ID: 263
Tariff Record Collation Value:8088800
Tariff Record Parent Identifier: 2
Proposed Date: 2019-12-19
Priority Order:500
Record Change Type: New
Record Content Type: 2
Associated Filing Identifier: [Source - if applicable]
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Service Agreement No. 2511
STANDARD SMALL GENERATOR INTERCONNECTION AGREEMENT
BETWEEN NIAGARA MOHAWK POWER CORPORATION D/B/A NATIONAL
GRID AND LaCHUTE HYDRO COMPANY, LLC
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
TABLE OF CONTENTS
Article 1Scope and Limitations of Agreement
1.1Applicability
1.2Purpose
1.3Scope of Interconnection Service
1.4Limitations
1.5Responsibilities of the Parties
1.6Parallel Operation Obligations
1.7Metering
1.8Reactive Power and Primary Frequency Response
1.9Capitalized Terms
Article 2.Inspection, Testing, Authorization, and Right of Access
2.1Equipment Testing and Inspection
2.2Authorization Required Prior to Parallel Operation
2.3Right of Access
Article 3Effective Date, Term, Termination, and Disconnection
3.1Effective Date
3.2Term of Agreement
3.3Termination
3.4Temporary Disconnection
3.4.1Emergency Conditions
3.4.2Routine Maintenance, Construction, and Repair
3.4.4Adverse Operating Effects
3.4.5Modification of the Small Generating Facility
3.4.6Reconnection
Article 4.Cost Responsibility for Interconnection Facilities and Distribution Upgrades
4.1Interconnection Facilities
4.2Distribution Upgrades
Article 5.Cost Responsibility for System Upgrade Facilities and System Deliverability
Upgrades
5.1Applicability
5.2System Upgrades
5.3Special Provisions for Affected Systems
Article 6.Billing, Payment, Milestones, and Financial Security
6.1Billing and Payment Procedures and Final Accounting
6.2Milestones
6.3Financial Security Arrangements
Article 7.Assignment, Liability, Indemnity, Force Majeure, Consequential Damages,
and Default
7.1Assignment
7.2Limitation of Liability
7.3Indemnity
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
7.4Consequential Damages
7.5Force Majeure
7.6Breach and Default
Article 8.Insurance
Article 9.Confidentiality
Article 10.Disputes
Article 11.Taxes
Article 12.Miscellaneous
12.1Governing Law, Regulatory Authority, and Rules
12.2Amendment
12.3No Third-Party Beneficiaries
12.4Waiver
12.5Entire Agreement
12.6Multiple Counterparts
12.7No Partnership
12.8Severability
12.9Security Arrangements
12.10Environmental Releases
12.11Subcontractors
12.12Reservation of Rights
Article 13.Notices
13.1General
13.2Billing and Payment
13.3Alternative Forms of Notice
13.4Designated Operating Representative
13.5Changes to the Notice Information
Article 14.Signatures
Attachment 1 - Glossary of Terms
Attachment 2 - Detailed Scope of Work, Including Description and Costs of the Small
Generating Facility, Interconnection Facilities, and Metering Equipment
Attachment 3 - One-line Diagram Depicting the Small Generating Facility, Interconnection
Facilities, Metering Equipment, and Upgrades
Attachment 4 - Milestones
Attachment 5 - Additional Operating Requirements for the New York State Transmission
System, the Distribution System and Affected Systems Needed to Support the Interconnection Customer’s Needs
Attachment 6 - Connecting Transmission Owner’s Description of its Upgrades and Best Estimate
of Upgrade Costs
Attachment 7 - Insurance Coverage
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
This Small Generator Interconnection Agreement (“Agreement” or “SGIA”) is made and entered into this 19th day of December, 2019, by and between Niagara Mohawk Power Corporation
d/b/a National Grid, a corporation organized and existing under the laws of the State of New
York (“Connecting Transmission Owner”), and LaChute Hydro Company, LLC, a Limited
liability company organized and existing under the laws of the State of Delaware
(“Interconnection Customer”) each hereinafter sometimes referred to individually as “Party” or referred to together as the “Parties.”
In consideration of the mutual covenants set forth herein, the Parties agree as follows:
Article 1: Scope and Limitations of Agreement
1.1Applicability
This Agreement hereby incorporates by reference the terms of the ISO OATT as they
apply to interconnection services provided by the Connecting Transmission Owner and taken by the Interconnection Customer. To the extent a conflict exists between the terms and conditions of this Agreement and the ISO OATT, the provisions of this Agreement shall prevail.
1.2Purpose
This Agreement governs the terms and conditions under which the Interconnection
Customer’s Small Generating Facility will interconnect with, and operate in parallel with, the New York State Transmission System or the Distribution System.
1.3Scope of Interconnection Service
1.3.1 The New York Independent System Operator, Inc., a not-for-profit corporation
organized and existing under the laws of the laws of the State of New York
(“NYISO”) will provide Energy Resource Interconnection Service and Capacity
Resource Interconnection Service to Interconnection Customer at the Point of
Interconnection in accordance with Section F of Attachment 2.
1.3.2 This Agreement does not constitute an agreement to purchase or deliver the
Interconnection Customer’s power. The purchase or delivery of power and other
services that the Interconnection Customer may require will be covered under
separate agreements, if any, or applicable provisions of NYISO’s or Connecting
Transmission Owner’s tariffs. The Interconnection Customer will be responsible
for separately making all necessary arrangements (including scheduling) for
delivery of electricity in accordance with the applicable provisions of the ISO
OATT and Connecting Transmission Owner’s tariff. The execution of this
Agreement does not constitute a request for, or agreement to; provide Energy, any
Ancillary Services or Installed Capacity under the NYISO Services Tariff or any
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Connecting Transmission Owner’s tariff. If Interconnection Customer wishes to supply or purchase Energy, Installed Capacity or Ancillary Services, then
Interconnection Customer will make application to do so in accordance with the NYISO Services Tariff or Connecting Transmission Owner’s tariff.
1.4Limitations
Nothing in this Agreement is intended to affect any other agreement between the Connecting Transmission Owner and the Interconnection Customer, except as otherwise expressly provided herein.
1.5Responsibilities of the Parties
1.5.1 The Parties shall perform all obligations of this Agreement in accordance with all
Applicable Laws and Regulations, Operating Requirements, and Good Utility
Practice.
1.5.2 The Interconnection Customer shall construct, interconnect, operate and maintain
its Small Generating Facility and construct, operate, and maintain its
Interconnection Facilities in accordance with the applicable manufacturer’s
recommended maintenance schedule, and in accordance with this Agreement, and
with Good Utility Practice.
1.5.3 The Connecting Transmission Owner shall construct, operate, and maintain its
Interconnection Facilities and Upgrades covered by this Agreement in accordance with this Agreement, and with Good Utility Practice.
1.5.4 The Interconnection Customer agrees to construct its facilities or systems in
accordance with applicable specifications that meet or exceed those provided by
the National Electrical Safety Code, the American National Standards Institute,
IEEE, Underwriter’s Laboratory, and Operating Requirements in effect at the time
of construction and other applicable national and state codes and standards. The
Interconnection Customer agrees to design, install, maintain, and operate its Small
Generating Facility so as to reasonably minimize the likelihood of a disturbance
adversely affecting or impairing the system or equipment of the Connecting
Transmission Owner or Affected Systems.
1.5.5 The Connecting Transmission Owner and Interconnection Customer shall operate,
maintain, repair, and inspect, and shall be fully responsible for the facilities that it
now or subsequently may own unless otherwise specified in the Attachments to
this Agreement. Each Party shall be responsible for the safe installation,
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
maintenance, repair and condition of its respective lines and appurtenances on its
respective sides of the point of change of ownership. The Connecting
Transmission Owner and the Interconnection Customer, as appropriate, shall
provide Interconnection Facilities that adequately protect the Connecting
Transmission Owner’s electric system, personnel, and other persons from damage
and injury. The allocation of responsibility for the design, installation, operation,
maintenance and ownership of Interconnection Facilities shall be delineated in the
Attachments to this Agreement.
1.5.6 The Connecting Transmission Owner shall cooperate with the NYISO to
coordinate with all Affected Systems to support the interconnection.
1.5.7 The Interconnection Customer shall ensure “frequency ride through” capability
and “voltage ride through” capability of its Small Generating Facility. The
Interconnection Customer shall enable these capabilities such that its Small
Generating Facility shall not disconnect automatically or instantaneously from the
system or equipment of the Connecting Transmission Owner and any Affected
Systems for a defined under-frequency or over-frequency condition, or an under-
voltage or over-voltage condition, as tested pursuant to section 2.1 of this
Agreement. The defined conditions shall be in accordance with Good Utility
Practice and consistent with any standards and guidelines that are applied to other
generating facilities in the Balancing Authority Area on a comparable basis. The
Small Generating Facility’s protective equipment settings shall comply with the
Transmission Owner’s automatic load-shed program. The Transmission Owner
shall review the protective equipment settings to confirm compliance with the
automatic load-shed program. The term “ride through” as used herein shall mean
the ability of a Small Generating Facility to stay connected to and synchronized
with the system or equipment of the Transmission Owner and any Affected
Systems during system disturbances within a range of conditions, in accordance
with Good Utility Practice and consistent with any standards and guidelines that
are applied to other generating facilities in the Balancing Authority on a
comparable basis. The term “frequency ride through” as used herein shall mean
the ability of a Small Generating Facility to stay connected to and synchronized
with the system or equipment of the Transmission Owner and any Affected
Systems during system disturbances within a range of under-frequency and over-
frequency conditions, in accordance with Good Utility Practice and consistent
with any standards and guidelines that are applied to other generating facilities in
the Balancing Authority Area on a comparable basis. The term “voltage ride
through” as used herein shall mean the ability of a Small Generating Facility to
stay connected to and synchronized with the system or equipment of the
Transmission Owner and any Affected Systems during system disturbances
within a range of under-voltage and over-voltage conditions, in accordance with
Good Utility Practice and consistent with any standards and guidelines that are
applied to other generating facilities in the Balancing Authority Area on a
comparable basis.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
1.6Parallel Operation Obligations
Once the Small Generating Facility has been authorized to commence parallel operation, the Interconnection Customer shall abide by all rules and procedures pertaining to the parallel operation of the Small Generating Facility in the applicable control area, including, but not
limited to: (1) the rules and procedures concerning the operation of generation set forth in the NYISO tariffs or ISO Procedures or the Connecting Transmission Owner’s tariff; (2) any
requirements consistent with Good Utility Practice or that are necessary to ensure the safe and reliable operation of the Transmission System or Distribution System; and (3) the Operating Requirements set forth in Attachment 5 of this Agreement.
1.7Metering
The Interconnection Customer shall be responsible for the Connecting Transmission
Owner’s reasonable and necessary cost for the purchase, installation, operation, maintenance,
testing, repair, and replacement of metering and data acquisition equipment specified in
Attachments 2 and 3 of this Agreement. The Interconnection Customer’s metering (and data
acquisition, as required) equipment shall conform to applicable industry rules and Operating
Requirements.
1.8 Reactive Power and Primary Frequency Response
1.8.1 Power Factor Design Criteria
1.8.1.1 Synchronous Generation. The Interconnection Customer shall design its
Small Generating Facility to maintain a composite power delivery at continuous
rated power output at the Point of Interconnection at a power factor within the
range of 0.95 leading to 0.95 lagging, unless the NYISO or the Transmission
Owner in whose Transmission District the Small Generating Facility
interconnects has established different requirements that apply to all similarly
situated generators in the New York Control Area or Transmission District (as
applicable) on a comparable basis, in accordance with Good Utility Practice.
1.8.1.2 Non-Synchronous Generation. The Interconnection Customer shall design
its Small Generating Facility to maintain a composite power delivery at
continuous rated power output at the high-side of the generator substation at a
power factor within the range of 0.95 leading to 0.95 lagging, unless the NYISO
or the Transmission Owner in whose Transmission District the Small Generating
Facility interconnects has established a different power factor range that applies to
all similarly situated non-synchronous generators in the control area or
Transmission District (as applicable) on a comparable basis, in accordance with
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Good Utility Practice. This power factor range standard shall by dynamic and can
be met using, for example, power electronics designed to supply this level of
reactive capability (taking into account any limitations due to voltage level, real
power output, etc.) or fixed and switched capacitors, or a combination of the two.
This requirement shall only apply to newly interconnecting non-synchronous
generators that have not yet executed a Facilities Study Agreement as of
September 21, 2016.
1.8.2 The Parties understand that the Interconnection Customer shall be paid by the
NYISO for reactive power, or voltage support service, that the Interconnection
Customer provides from the Small Generating Facility in accordance with Rate
Schedule 2 of the NYISO Services Tariff.
1.9Capitalized Terms
Capitalized terms used herein shall have the meanings specified in the Glossary of Terms in Attachment 1 or the body of this Agreement. Capitalized terms used herein that are not so defined shall have the meanings specified in Appendix 1 of Attachment Z, Section 25.1.2 of Attachment S, or Section 30.1 of Attachment X of the ISO OATT.
Article 2: Inspection, Testing, Authorization, and Right of Access
2.1 Equipment Testing and Inspection
2.1.1 The Interconnection Customer shall test and inspect its Small Generating Facility
and Interconnection Facilities prior to interconnection. The Interconnection
Customer shall notify the NYISO and the Connecting Transmission Owner of
such activities no fewer than five Business Days (or as may be agreed to by the
Parties) prior to such testing and inspection. Testing and inspection shall occur on
a Business Day. The Connecting Transmission Owner may, at its own expense,
send qualified personnel to the Small Generating Facility site to inspect the
interconnection and observe the testing. The Interconnection Customer shall
provide the NYISO and Connecting Transmission Owner a written test report
when such testing and inspection is completed. The Small Generating Facility
may not commence parallel operations if the NYISO, in consultation with the
Connecting Transmission Owner, finds that the Small Generating Facility has not
been installed as agreed upon or may not be operated in a safe and reliable
manner.
2.1.2 The Connecting Transmission Owner shall, and the NYISO may, provide the
Interconnection Customer written acknowledgment that it has received the
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Interconnection Customer’s written test report. Such written acknowledgment
shall not be deemed to be or construed as any representation, assurance,
guarantee, or warranty by the NYISO or Connecting Transmission Owner of the
safety, durability, suitability, or reliability of the Small Generating Facility or any
associated control, protective, and safety devices owned or controlled by the
Interconnection Customer or the quality of power produced by the Small
Generating Facility.
2.2 Authorization Required Prior to Parallel Operation
2.2.1 The Connecting Transmission Owner, in consultation with the NYISO, shall use
Reasonable Efforts to list applicable parallel Operating Requirements in
Attachment 5 of this Agreement. Additionally, the Connecting Transmission
Owner, in consultation with the NYISO, shall notify the Interconnection
Customer of any changes to these requirements as soon as they are known. The
NYISO and Connecting Transmission Owner shall make Reasonable Efforts to
cooperate with the Interconnection Customer in meeting requirements necessary
for the Interconnection Customer to commence parallel operations by the in-
service date.
2.2.2 The Interconnection Customer shall not operate its Small Generating Facility in
parallel with the New York State Transmission System or the Distribution System
without prior written authorization of the NYISO. The Parties understand that the
NYISO, in consultation with the Connecting Transmission Owner, will provide
such authorization once the NYISO receives notification that the Interconnection
Customer has complied with all applicable parallel Operating Requirements.
Such authorization shall not be unreasonably withheld, conditioned, or delayed.
2.3Right of Access
2.3.1 Upon reasonable notice, the NYISO and/or Connecting Transmission Owner may
send a qualified person to the premises of the Interconnection Customer at or
immediately before the time the Small Generating Facility first produces energy
to inspect the interconnection, and observe the commissioning of the Small
Generating Facility (including any required testing), startup, and operation for a
period of up to three Business Days after initial start-up of the unit. In addition,
the Interconnection Customer shall notify the NYISO and Connecting
Transmission Owner at least five Business Days prior to conducting any on-site
verification testing of the Small Generating Facility.
2.3.2 Following the initial inspection process described above, at reasonable hours, and
upon reasonable notice, or at any time without notice in the event of an
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
emergency or hazardous condition, the NYISO and Connecting Transmission
Owner each shall have access to the Interconnection Customer’s premises for any reasonable purpose in connection with the performance of the obligations
imposed on them by this Agreement or if necessary to meet their legal obligation to provide service to their customers.
2.3.3 Each Party shall be responsible for its own costs associated with following this
article.
Article 3: Effective Date, Term, Termination, and Disconnection
3.1Effective Date
This Agreement shall become effective upon execution by the Parties subject to
acceptance by FERC (if applicable), or if filed unexecuted, upon the date specified by the FERC. The Connecting Transmission Owner shall promptly file, or cause to be filed, this Agreement with FERC upon execution, if required. If the Agreement is disputed and the Interconnection Customer requests that it be filed with FERC in an unexecuted form, the Connecting
Transmission Owner shall file, or cause to be filed, this Agreement and the Connecting
Transmission Owner shall identify the disputed language.
3.2Term of Agreement
This Agreement shall become effective on the Effective Date and shall remain in effect
for a period of twenty (20) years from the Effective Date or such other longer period as the
Interconnection Customer may request and shall be automatically renewed for each successive
one-year period thereafter, unless terminated earlier in accordance with article 3.3 of this
Agreement.
3.3Termination
No termination shall become effective until the Parties have complied with all Applicable
Laws and Regulations applicable to such termination, including the filing with FERC of a notice
of termination of this Agreement (if required), which notice has been accepted for filing by
FERC.
3.3.1 The Interconnection Customer may terminate this Agreement at any time by
giving the Connecting Transmission Owner 20 Business Days written notice.
The Connecting Transmission Owner may terminate this Agreement after the
Small Generating Facility is Retired.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
3.3.2 Either Party may terminate this Agreement after Default pursuant to article 7.6.
3.3.3 Upon termination of this Agreement, the Small Generating Facility will be
disconnected from the New York State Transmission System or the Distribution System, as applicable. All costs required to effectuate such disconnection shall be borne by the terminating Party, unless such termination resulted from the nonterminating Party’s Default of this Agreement or such non-terminating Party otherwise is responsible for these costs under this Agreement.
3.3.4 The termination of this Agreement shall not relieve either Party of its liabilities
and obligations, owed or continuing at the time of the termination. The
Interconnection Customer shall pay all amounts in excess of any deposit or other
security without interest within 30 calendar days after receipt of the invoice for
such amounts. If the deposit or other security exceeds the invoice, the Connecting
Transmission Owner shall refund such excess within 30 calendar days of the
invoice without interest. If the Interconnection Customer disputes an amount to be
paid the Interconnection Customer shall pay the disputed amount to the
Connecting Transmission Owner or into an interest-bearing escrow account,
pending resolution of the dispute in accordance with Article 10 of this Agreement.
To the extent the dispute is resolved in the Interconnection Customer’s favor, that
portion of the disputed amount will be returned to the Interconnection Customer
with interest at rates applicable to refunds under the Commission’s regulations.
To the extent the dispute is resolved in the Connecting Transmission Owner’s
favor, that portion of any escrowed funds and interest will be released to the
Connecting Transmission Owner.
3.3.5 The limitations of liability, indemnification and confidentiality provisions of this
Agreement shall survive termination or expiration of this Agreement.
3.4Temporary Disconnection
Temporary disconnection shall continue only for so long as reasonably necessary under Good Utility Practice.
3.4.1 Emergency Conditions
“Emergency Condition” shall mean a condition or situation: (1) that in the judgment of
the Party making the claim is imminently likely to endanger life or property; or (2) that, in the
case of the NYISO or Connecting Transmission Owner, is imminently likely (as determined in a
non-discriminatory manner) to cause a material adverse effect on the security of, or damage to
the New York State Transmission System or Distribution System, the Connecting Transmission
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Owner’s Interconnection Facilities or the electric systems of others to which the New York State
Transmission System or Distribution System is directly connected; or (3) that, in the case of the
Interconnection Customer, is imminently likely (as determined in a non-discriminatory manner)
to cause a material adverse effect on the security of, or damage to, the Small Generating Facility
or the Interconnection Customer’s Interconnection Facilities. Under Emergency Conditions, the
NYISO or Connecting Transmission Owner may immediately suspend interconnection service
and temporarily disconnect the Small Generating Facility. The Connecting Transmission Owner
shall notify the Interconnection Customer promptly when it becomes aware of an Emergency
Condition that may reasonably be expected to affect the Interconnection Customer’s operation of the Small Generating Facility. The Interconnection Customer shall notify the NYISO and
Connecting Transmission Owner promptly when it becomes aware of an Emergency Condition
that may reasonably be expected to affect the New York State Transmission System or
Distribution System or any Affected Systems. To the extent information is known, the
notification shall describe the Emergency Condition, the extent of the damage or deficiency, the expected effect on the operation of each Party’s facilities and operations, its anticipated duration, and the necessary corrective action.
3.4.2 Routine Maintenance, Construction, and Repair
The NYISO or Connecting Transmission Owner may interrupt interconnection service or curtail the output of the Small Generating Facility and temporarily disconnect the Small
Generating Facility from the New York State Transmission System or Distribution System when necessary for routine maintenance, construction, and repairs on the New York State
Transmission System or Distribution System. The NYISO or the Connecting Transmission
Owner shall provide the Interconnection Customer with five Business Days’ notice prior to such interruption. The Connecting Transmission Owner shall use Reasonable Efforts to coordinate
such reduction or temporary disconnection with the Interconnection Customer. The Parties
understand that any actions the NYISO is authorized to take under this article 3.4.2 are
conditioned upon the NYISO’s use of Reasonable Efforts to coordinate such reduction or
temporary disconnection with the Interconnection Customer.
3.4.3 Forced Outages
During any forced outage, the NYISO or Connecting Transmission Owner may suspend
interconnection service to the Interconnection Customer to effect immediate repairs on the New
York State Transmission System or the Distribution System. The Connecting Transmission
Owner shall use Reasonable Efforts to provide the Interconnection Customer with prior notice. If
prior notice is not given, the Connecting Transmission Owner shall, upon request, provide the
Interconnection Customer written documentation after the fact explaining the circumstances of
the disconnection. The Parties understand that any suspension or disconnection the NYISO is
authorized to make under this article 3.4.3 is conditioned upon: (i) the NYISO’s use of
Reasonable Efforts to provide the Interconnection Customer with prior notice; and (ii) if prior
notice is not given, the NYISO’s provision to the Interconnection Customer, upon request, of
written documentation after the fact explaining the circumstances of the disconnection.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
3.4.4 Adverse Operating Effects
The NYISO or Connecting Transmission Owner shall notify the Interconnection
Customer as soon as practicable if, based on Good Utility Practice, operation of the Small
Generating Facility may cause disruption or deterioration of service to other customers served from the same electric system, or if operating the Small Generating Facility could cause damage to the New York State Transmission System, the Distribution System or Affected Systems, or if disconnection is otherwise required under Applicable Reliability Standards or the ISO OATT. Supporting documentation used to reach the decision to disconnect shall be provided to the
Interconnection Customer upon request. If, after notice, the Interconnection Customer fails to remedy the adverse operating effect within a reasonable time, the NYISO or Connecting
Transmission Owner may disconnect the Small Generating Facility. The NYISO or Connecting Transmission Owner shall provide the Interconnection Customer with five Business Day notice of such disconnection, unless the provisions of article 3.4.1 apply.
3.4.5 Modification of the Small Generating Facility
The Interconnection Customer must receive written authorization from the NYISO and
Connecting Transmission Owner before making any change to the Small Generating Facility that
may have a material impact on the safety or reliability of the New York State Transmission
System or the Distribution System. Such authorization shall not be unreasonably withheld.
Modifications shall be done in accordance with Good Utility Practice. If the Interconnection
Customer makes such modification without the prior written authorization of the NYISO and
Connecting Transmission Owner, the Connecting Transmission Owner shall have the right to
temporarily disconnect the Small Generating Facility. If disconnected, the Small Generating
Facility will not be reconnected until the unauthorized modifications are authorized or removed.
3.4.6 Reconnection
The Parties shall cooperate with each other to restore the Small Generating Facility,
Interconnection Facilities, and the New York State Transmission System and Distribution
System to their normal operating state as soon as reasonably practicable following a temporary disconnection.
Article 4: Cost Responsibility for Interconnection Facilities and Distribution Upgrades
4.1Interconnection Facilities
4.1.1 The Interconnection Customer shall pay for the cost of the Interconnection
Facilities itemized in Attachment 2 of this Agreement. The Connecting
Transmission Owner shall provide a best estimate cost, including overheads, for
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
the purchase and construction of its Interconnection Facilities and provide a
detailed itemization of such costs. Costs associated with Interconnection Facilities may be shared with other entities that may benefit from such facilities by
agreement of the Interconnection Customer, such other entities, and the
Connecting Transmission Owner.
4.1.2 The Interconnection Customer shall be responsible for its share of all reasonable
expenses, including overheads, associated with (1) owning, operating,
maintaining, repairing, and replacing its own Interconnection Facilities, and (2)
operating, maintaining, repairing, and replacing the Connecting Transmission
Owner’s Interconnection Facilities, as set forth in Attachment 2 to this
Agreement.
4.2Distribution Upgrades
The Connecting Transmission Owner shall design, procure, construct, install, and own
the Distribution Upgrades described in Attachment 6 of this Agreement. If the Connecting
Transmission Owner and the Interconnection Customer agree, the Interconnection Customer may
construct Distribution Upgrades that are located on land owned by the Interconnection Customer.
The actual cost of the Distribution Upgrades, including overheads, shall be directly assigned to
the Interconnection Customer. The Interconnection Customer shall be responsible for its share of
all reasonable expenses, including overheads, associated with owning, operating, maintaining,
repairing, and replacing the Distribution Upgrades, as set forth in Attachment 6 to this
Agreement.
Article 5: Cost Responsibility for System Upgrade Facilities and System Deliverability Upgrades
5.1Applicability
No portion of this article 5 shall apply unless the interconnection of the Small Generating Facility requires System Upgrade Facilities or System Deliverability Upgrades.
5.2System Upgrades
The Connecting Transmission Owner shall procure, construct, install, and own the
System Upgrade Facilities and System Deliverability Upgrades described in Attachment 6 of this
Agreement. To the extent that design work is necessary in addition to that already
accomplished in the Class Year Interconnection Facilities Study for the Interconnection
Customer, the Connecting Transmission Owner shall perform or cause to be performed such
work. If the Parties agree, the Interconnection Customer may construct System Upgrade
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Facilities and System Deliverability Upgrades that are located on land owned by the Interconnection Customer.
5.2.1 As described in Section 32.3.5.3 of the SGIP in Attachment Z of the ISO OATT,
the responsibility of the Interconnection Customer for the cost of the System
Upgrade Facilities and System Deliverability Upgrades described in Attachment 6
of this Agreement shall be determined in accordance with Attachment S of the
ISO OATT, as required by Section 32.3.5.3.2 of Attachment Z. The
Interconnection Customer shall be responsible for all System Upgrade Facility
costs as required by Section 32.3.5.3.2 of Attachment Z or its share of any System
Upgrade Facilities and System Deliverability Upgrades costs resulting from the
final Attachment S process, as applicable, and Attachment 6 to this Agreement
shall be revised accordingly.
5.2.2 Pending the outcome of the Attachment S cost allocation process, if applicable,
the Interconnection Customer may elect to proceed with the interconnection of its
Small Generating Facility in accordance with Section 32.3.5.3 of the SGIP.
5.3 Special Provisions for Affected Systems
For the repayment of amounts advanced to the Affected System Operator for System Upgrade Facilities or System Deliverability Upgrades, the Interconnection Customer and Affected System Operator shall enter into an agreement that provides for such repayment, but only if responsibility for the cost of such System Upgrade Facilities is not to be allocated in accordance with Attachment S of the ISO OATT. The agreement shall specify the terms governing payments to be made by the Interconnection Customer to the Affected System Operator as well as the repayment by the Affected System Operator.
Article 6Billing, Payment, Milestones, and Financial Security
6.1 Billing and Payment Procedures and Final Accounting
6.1.1 The Connecting Transmission Owner shall bill the Interconnection Customer for
the design, engineering, construction, and procurement costs of Interconnection
Facilities and Upgrades contemplated by this Agreement on a monthly basis, or as
otherwise agreed by the Parties. The Interconnection Customer shall pay all
invoice amounts within 30 calendar days after receipt of the invoice.
6.1.2 Within three months of completing the construction and installation of the
Connecting Transmission Owner’s Interconnection Facilities and/or Upgrades
described in the Attachments to this Agreement, the Connecting Transmission
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Owner shall provide the Interconnection Customer with a final accounting report
of any difference between (1) the Interconnection Customer’s cost responsibility
for the actual cost of such facilities or Upgrades, and (2) the Interconnection
Customer’s previous aggregate payments to the Connecting Transmission Owner
for such facilities or Upgrades. If the Interconnection Customer’s cost
responsibility exceeds its previous aggregate payments, the Connecting
Transmission Owner shall invoice the Interconnection Customer for the amount
due and the Interconnection Customer shall make payment to the Connecting
Transmission Owner within 30 calendar days. If the Interconnection Customer’s
previous aggregate payments exceed its cost responsibility under this Agreement,
the Connecting Transmission Owner shall refund to the Interconnection Customer
an amount equal to the difference within 30 calendar days of the final accounting
report.
6.1.3 If the Interconnection Customer disputes an amount to be paid, the
Interconnection Customer shall pay the disputed amount to the Connecting
Transmission Owner or into an interest bearing escrow account, pending
resolution of the dispute in accordance with Article 10 of this Agreement. To the extent the dispute is resolved in the Interconnection Customer’s favor, that portion of the disputed amount will be credited or returned to the Interconnection
Customer with interest at rates applicable to refunds under the Commission’s
regulations. To the extent the dispute is resolved in the Connecting Transmission Owner’s favor, that portion of any escrowed funds and interest will be released to the Connecting Transmission Owner.
6.2Milestones
Subject to the provisions of the SGIP, the Parties shall agree on milestones for which
each Party is responsible and list them in Attachment 4 of this Agreement. A Party’s obligations
under this provision may be extended by agreement. If a Party anticipates that it will be unable to
meet a milestone for any reason other than a Force Majeure event, it shall immediately notify the
other Party of the reason(s) for not meeting the milestone and: (1) propose the earliest reasonable
alternate date by which it can attain this and future milestones, and (2) requesting appropriate
amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not
unreasonably withhold agreement to such an amendment unless: (1) it will suffer significant
uncompensated economic or operational harm from the delay, (2) attainment of the same
milestone has previously been delayed, or (3) it has reason to believe that the delay in meeting
the milestone is intentional or unwarranted notwithstanding the circumstances explained by the
Party proposing the amendment.
6.3Financial Security Arrangements
At least 20 Business Days prior to the commencement of the design, procurement,
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
installation, or construction of a discrete portion of the Connecting Transmission Owner’s
Interconnection Facilities and Upgrades, the Interconnection Customer shall provide the
Connecting Transmission Owner, at the Interconnection Customer’s option, a guarantee, a surety
bond, letter of credit or other form of security that is reasonably acceptable to the Connecting
Transmission Owner and is consistent with the Uniform Commercial Code of the jurisdiction
where the Point of Interconnection is located. Such security for payment shall be in an amount
sufficient to cover the costs for constructing, designing, procuring, and installing the applicable
portion of the Connecting Transmission Owner’s Interconnection Facilities and Upgrades and
shall be reduced on a dollar-for-dollar basis for payments made to the Connecting Transmission
Owner under this Agreement during its term. The Connecting Transmission Owner may draw
on any such security to the extent that the Interconnection Customer fails to make any payments
due under this Agreement. In addition:
6.3.1 The guarantee must be made by an entity that meets the creditworthiness
requirements of the Connecting Transmission Owner, and contain terms and conditions that guarantee payment of any amount that may be due from the Interconnection Customer, up to an agreed-to maximum amount.
6.3.2 The letter of credit or surety bond must be issued by a financial institution or
insurer reasonably acceptable to the Connecting Transmission Owner and must
specify a reasonable expiration date.
6.3.3 Notwithstanding the above, Security posted for System Upgrade Facilities for a
Small Generating Facility required to enter the Class Year process, or cash or
Security provided for System Deliverability Upgrades, shall meet the
requirements for Security contained in Attachment S to the ISO OATT.
Article 7Assignment, Liability, Indemnity, Force Majeure, Consequential Damages, and
Default
7.1Assignment
This Agreement, and each and every term and condition hereof, shall be binding upon and inure to the benefit of the Parties hereto and their respective successors and assigns. This Agreement may be assigned by either Party upon 15 Business Days prior written notice and opportunity to object by the other Party; provided that:
7.1.1 A Party may assign this Agreement without the consent of the other Parties to any
affiliate of the assigning Party with an equal or greater credit rating and with the
legal authority and operational ability to satisfy the obligations of the assigning
Party under this Agreement, provided that the Interconnection Customer promptly
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
notifies the NYISO and the Connecting Transmission Owner of any such
assignment. A Party may assign this Agreement without the consent of the other Party in connection with the sale, merger, restructuring, or transfer of a substantial portion of all of its assets, including the Interconnection Facilities it owns, so long as the assignee in such a transaction directly assumes all rights, duties and
obligation arising under this Agreement.
7.1.2 The Interconnection Customer shall have the right to assign this Agreement,
without the consent of the NYISO or Connecting Transmission Owner, for
collateral security purposes to aid in providing financing for the Small Generating
Facility.
7.1.3 Any attempted assignment that violates this article is void and ineffective.
Assignment shall not relieve a Party of its obligations, nor shall a Party’s
obligations be enlarged, in whole or in part, by reason thereof. An assignee is
responsible for meeting the same financial, credit, and insurance obligations as
the Interconnection Customer. Where required, consent to assignment will not be
unreasonably withheld, conditioned or delayed.
7.2Limitation of Liability
Each Party’s liability to the other Party for any loss, cost, claim, injury, liability, or
expense, including reasonable attorney’s fees, relating to or arising from any act or omission in its performance of this Agreement, shall be limited to the amount of direct damage actually incurred. In no event shall either Party be liable to the other Party for any indirect, special, consequential, or punitive damages.
7.3Indemnity
7.3.1 This provision protects each Party from liability incurred to third parties as a
result of carrying out the provisions of this Agreement. Liability under this
provision is exempt from the general limitations on liability found in article 7.2.
7.3.2 Each Party (the “Indemnifying Party”) shall at all times indemnify, defend, and
hold harmless the other Party (the “ Indemnified Party”) from, any and all
damages, losses, claims, including claims and actions relating to injury to or death
of any person or damage to property, the alleged violation of any Environmental
Law, or the release or threatened release of any Hazardous Substance, demand,
suits, recoveries, costs and expenses, court costs, attorney fees, and all other
obligations by or to third parties (any and all of these a “Loss”), arising out of or
resulting from: (i) the Indemnified Party’s performance under this Agreement on
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
behalf of the Indemnifying Party, except in cases where the Indemnifying Party can demonstrate that the Loss of the Indemnified Party was caused by the gross negligence or intentional wrongdoing by the Indemnified Party, or (ii) the
violation by the Indemnifying Party of any Environmental Law or the release by the Indemnifying Party of a Hazardous Substance.
7.3.3 If a Party is entitled to indemnification under this article as a result of a claim by a
third party, and the Indemnifying Party fails, after notice and reasonable
opportunity to proceed under this article, to assume the defense of such claim,
such Indemnified Party may at the expense of the Indemnifying Party contest,
settle or consent to the entry of any judgment with respect to, or pay in full, such
claim.
7.3.4 If the Indemnifying Party is obligated to indemnify and hold the Indemnified
Party harmless under this article, the amount owing to the Indemnified Party shall be the amount of such Indemnified Party’s actual loss, net of any insurance or
other recovery.
7.3.5 Promptly after receipt by the Indemnified Party of any claim or notice of the
commencement of any action or administrative or legal proceeding or
investigation as to which the indemnity provided for in this article may apply, the
Indemnified Party shall notify the Indemnifying Party of such fact. Any failure of
or delay in such notification shall not affect a Party’s indemnification obligation
unless such failure or delay is materially prejudicial to the Indemnifying Party.
7.4Consequential Damages
Other than as expressly provided for in this Agreement, neither Party shall be liable under any provision of this Agreement for any losses, damages, costs or expenses for any special,
indirect, incidental, consequential, or punitive damages, including but not limited to loss of profit or revenue, loss of the use of equipment, cost of capital, cost of temporary equipment or services, whether based in whole or in part in contract, in tort, including negligence, strict liability, or any other theory of liability; provided, however, that damages for which a Party may be liable to the
other Party under another agreement will not be considered to be special, indirect, incidental, or
consequential damages hereunder.
7.5Force Majeure
7.5.1 As used in this article, a “Force Majeure Event” shall mean “any act of God, labor
disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood,
explosion, breakage or accident to machinery or equipment, any order, regulation
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
or restriction imposed by governmental, military or lawfully established civilian
authorities, or any other cause beyond a Party’s control. A Force Majeure Event
does not include an act of negligence or intentional wrongdoing.” For the
purposes of this article, this definition of Force Majeure shall supersede the
definitions of Force Majeure set out in Section 32.10.1 of the ISO OATT.
7.5.2 If a Force Majeure Event prevents a Party from fulfilling any obligations under
this Agreement, the Party affected by the Force Majeure Event (“Affected Party”)
shall promptly notify the other Party, either in writing or via the telephone, of the
existence of the Force Majeure event. The notification must specify in reasonable
detail the circumstances of the Force Majeure Event, its expected duration, and
the steps that the Affected Party is taking to mitigate the effects of the event on its
performance. The Affected Party shall keep the other Party informed on a
continuing basis of developments relating to the Force Majeure Event until the event ends. The Affected Party will be entitled to suspend or modify its
performance of obligations under this Agreement (other than the obligation to make payments) only to the extent that the effect of the Force Majeure Event cannot be mitigated by the use of Reasonable Efforts. The Affected Party will use Reasonable Efforts to resume its performance as soon as possible.
7.6Breach and Default
7.6.1 No Breach of this Agreement shall exist where such failure to discharge an
obligation (other than the payment of money) is the result of a Force Majeure
Event or the result of an act or omission of the other Party. Upon a Breach, the
non-breaching Party shall give written notice of such Breach to the Breaching
Party. Except as provided in article 7.6.2, the Breaching Party shall have 60
calendar days from receipt of the Breach notice within which to cure such Breach;
provided however, if such Breach is not capable of cure within 60 calendar days,
the Breaching Party shall commence such cure within 20 calendar days after
notice and continuously and diligently complete such cure within six months from
receipt of the Breach notice; and, if cured within such time, the Breach specified
in such notice shall cease to exist.
7.6.2 If a Breach is not cured as provided in this article, or if a Breach is not capable of
being cured within the period provided for herein, a Default shall exist and the
non-defaulting Party shall thereafter have the right to terminate this Agreement, in
accordance with article 3.3 hereof, by written notice to the defaulting Party at any
time until cure occurs, and be relieved of any further obligation hereunder and,
whether or not that Party terminate this Agreement, to recover from the defaulting
Party all amounts due hereunder, plus all other damages and remedies to which
they are entitled at law or in equity. The provisions of this article shall survive
termination of this Agreement.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
7.6.3 In cases where the Interconnection Customer has elected to proceed under Section
32.3.5.3 of the SGIP, if the Interconnection Request is withdrawn or deemed withdrawn pursuant to the SGIP during the term of this Agreement, this Agreement shall terminate.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Article 8:Insurance
8.1 The Interconnection Customer shall, at its own expense, maintain in force general
liability insurance without any exclusion for liabilities related to the interconnection
undertaken pursuant to this Agreement. The amount of such insurance shall be sufficient
to insure against all reasonably foreseeable direct liabilities given the size and nature of
the generating equipment being interconnected, the interconnection itself, and the
characteristics of the system to which the interconnection is made. Such insurance
coverage is specified in Attachment 7 to this Agreement. The Interconnection Customer
shall obtain additional insurance only if necessary as a function of owning and operating
a generating facility. Such insurance shall be obtained from an insurance provider
authorized to do business in New York State where the interconnection is located.
Certification that such insurance is in effect shall be provided upon request of the
Connecting Transmission Owner, except that the Interconnection Customer shall show
proof of insurance to the Connecting Transmission Owner no later than ten Business
Days prior to the anticipated commercial operation date. An Interconnection Customer of
sufficient creditworthiness may propose to self-insure for such liabilities, and such a
proposal shall not be unreasonably rejected.
8.2 The Connecting Transmission Owner agree to maintain general liability insurance or self-
insurance consistent with the existing commercial practice. Such insurance or self-
insurance shall not exclude the liabilities undertaken pursuant to this Agreement.
8.3 The Parties further agree to notify one another whenever an accident or incident occurs
resulting in any injuries or damages that are included within the scope of coverage of such insurance, whether or not such coverage is sought.
Article 9: Confidentiality
9.1 Confidential Information shall mean any confidential and/or proprietary information
provided by one Party to the other Party that is clearly marked or otherwise designated
“Confidential.” For purposes of this Agreement all design, operating specifications, and
metering data provided by the Interconnection Customer shall be deemed Confidential
Information regardless of whether it is clearly marked or otherwise designated as such.
Confidential Information shall include, without limitation, information designated as such
by the NYISO Code of Conduct contained in Attachment F to the ISO OATT.
9.2 Confidential Information does not include information previously in the public domain,
required to be publicly submitted or divulged by Governmental Authorities (after notice
to the other Party and after exhausting any opportunity to oppose such publication or
release), or necessary to be divulged in an action to enforce this Agreement. Each Party
receiving Confidential Information shall hold such information in confidence and shall
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
not disclose it to any third party nor to the public without the prior written authorization from the Party providing that information, except to fulfill obligations under this
Agreement, or to fulfill legal or regulatory requirements.
9.2.1 Each Party shall employ at least the same standard of care to protect Confidential
Information obtained from the other Party as it employs to protect its own
Confidential Information.
9.2.2 Each Party is entitled to equitable relief, by injunction or otherwise, to enforce its
rights under this provision to prevent the release of Confidential Information
without bond or proof of damages, and may seek other remedies available at law
or in equity for breach of this provision.
9.3 Notwithstanding anything in this article to the contrary, and pursuant to 18 CFR §
lb.20, if FERC, during the course of an investigation or otherwise, requests
information from the other Party that is otherwise required to be maintained in
confidence pursuant to this Agreement, the Party shall provide the requested
information to FERC, within the time provided for in the request for information.
In providing the information to FERC, the Party may, consistent with 18 CFR §
388.112, request that the information be treated as confidential and non-public by
FERC and that the information be withheld from public disclosure. Each Party is
prohibited from notifying the other Party to this Agreement prior to the release of
the Confidential Information to FERC. The Party shall notify the other Party to
this Agreement when it is notified by FERC that a request to release Confidential
Information has been received by FERC, at which time either of the Parties may
respond before such information would be made public, pursuant to 18 CFR §
388.112. Requests from a state regulatory body conducting a confidential
investigation shall be treated in a similar manner if consistent with the applicable
state rules and regulations.
9.4 Consistent with the provisions of this article 9, the Parties to this Agreement will
cooperate in good faith to provide each other, Affected Systems, Affected System Operators, and state and federal regulators the information necessary to carry out the terms of the SGIP and this Agreement.
Article 10: Disputes
10.1 The Connecting Transmission Owner and Interconnection Customer agree to attempt to
resolve all disputes arising out of the interconnection process according to the provisions of this article.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
10.2In the event of a dispute, the Parties will first attempt to promptly resolve it on an
informal basis. If the Parties cannot promptly resolve the dispute on an informal basis, then either Party shall provide the other Party with a written Notice of Dispute. Such notice shall describe in detail the nature of the dispute.
10.3 If the dispute has not been resolved within two Business Days after receipt of the notice,
either Party may contact FERC’s Dispute Resolution Service (“DRS”) for assistance in resolving the dispute.
10.4 The DRS will assist the Parties in either resolving their dispute or in selecting an
appropriate dispute resolution venue (e.g., mediation, settlement judge, early neutral
evaluation, or technical expert) to assist the Parties in resolving their dispute. The result of this dispute resolution process will be binding only if the Parties agree in advance. DRS can be reached at 1-877-337-2237 or via the internet at
http://www.ferc.gov/legal/adr.asp.
10.5Each Party agrees to conduct all negotiations in good faith and will be responsible for
one-half of any costs paid to neutral third-parties.
10.6 If either Party elects to seek assistance from the DRS, or if the attempted dispute
resolution fails, then either Party may exercise whatever rights and remedies it may have in equity or law consistent with the terms of this Agreement.
Article 11: Taxes
11.1 The Parties agree to follow all applicable tax laws and regulations, consistent with
FERC policy and Internal Revenue Service requirements.
11.2 Each Party shall cooperate with the other Parties to maintain the other Party’s tax status.
Nothing in this Agreement is intended to adversely affect the tax status of either Party
including the status of any Connecting Transmission Owner with respect to the issuance of bonds including, but not limited to, Local Furnishing Bonds. Notwithstanding any
other provisions of this Agreement, LIPA, NYPA and Consolidated Edison Company of New York, Inc. shall not be required to comply with any provisions of this Agreement
that would result in the loss of tax-exempt status of any of their Tax-Exempt Bonds or
impair their ability to issue future tax-exempt obligations. For purposes of this provision, Tax-Exempt Bonds shall include the obligations of the Long Island Power Authority,
NYPA and Consolidated Edison Company of New York, Inc., the interest on which is not included in gross income under the Internal Revenue Code.
11.3 LIPA and NYPA do not waive their exemptions, pursuant to Section 201(f) of the FPA,
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
from Commission jurisdiction with respect to the Commission’s exercise of the FPA’s general ratemaking authority.
11.4 Any payments due to the Connecting Transmission Owner under this Agreement shall be
adjusted to include any tax liability incurred by the Connecting Transmission Owner with respect to the interconnection request which is the subject of this Agreement. Such
adjustments shall be made in accordance with the provisions of Article 5.17 of the LGIA in Attachment X of the ISO OATT. Except where otherwise noted, all costs, deposits,
financial obligations and the like specified in this Agreement shall be assumed not to
reflect the impact of applicable taxes.
Article 12: Miscellaneous
12.1 Governing Law, Regulatory Authority, and Rules
The validity, interpretation and enforcement of this Agreement and each of its provisions shall be governed by the laws of the state of New York, without regard to its conflicts of law principles. This Agreement is subject to all Applicable Laws and Regulations. Each Party
expressly reserves the right to seek changes in, appeal, or otherwise contest any laws, orders, or regulations of a Governmental Authority.
12.2Amendment
The Parties may amend this Agreement by a written instrument duly executed by the Parties, or under article 12.12 of this Agreement.
12.3 No Third-Party Beneficiaries
This Agreement is not intended to and does not create rights, remedies, or benefits of any character whatsoever in favor of any persons, corporations, associations, or entities other than the Parties, and the obligations herein assumed are solely for the use and benefit of the Parties, their successors in interest and where permitted, their assigns. Notwithstanding the foregoing, any
subcontractor of the Connecting Transmission Owner assisting that Party with the
Interconnection Request covered by this Agreement shall be entitled to the benefits of
indemnification provided for under Article 7.3 of this Agreement and the limitation of liability
provided for in Article 7.2 of this Agreement.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
12.4Waiver
12.4.1 The failure of a Party to this Agreement to insist, on any occasion, upon strict
performance of any provision of this Agreement will not be considered a waiver of any obligation, right, or duty of, or imposed upon, such Party.
12.4.2 Any waiver at any time by a Party of its rights with respect to this Agreement
shall not be deemed a continuing waiver or a waiver with respect to any other
failure to comply with any other obligation, right, duty of this Agreement.
Termination or default of this Agreement for any reason by Interconnection
Customer shall not constitute a waiver of the Interconnection Customer’s legal
rights to obtain an interconnection from the NYISO. Any waiver of this
Agreement shall, if requested, be provided in writing.
12.5Entire Agreement
This Agreement, including all Attachments, constitutes the entire agreement between the Parties with reference to the subject matter hereof, and supersedes all prior and contemporaneous understandings or agreements, oral or written, between the Parties with respect to the subject matter of this Agreement. There are no other agreements, representations, warranties, or
covenants which constitute any part of the consideration for, or any condition to, either Party’s compliance with its obligations under this Agreement.
12.6 Multiple Counterparts
This Agreement may be executed in two or more counterparts, each of which is deemed an original but all constitute one and the same instrument.
12.7No Partnership
This Agreement shall not be interpreted or construed to create an association, joint
venture, agency relationship, or partnership between the Parties or to impose any partnership
obligation or partnership liability upon either Party. Neither Party shall have any right, power or authority to enter into any agreement or undertaking for, or act on behalf of, or to act as or be an agent or representative of, or to otherwise bind, the other Party.
12.8Severability
If any provision or portion of this Agreement shall for any reason be held or adjudged to
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
be invalid or illegal or unenforceable by any court of competent jurisdiction or other
Governmental Authority, (1) such portion or provision shall be deemed separate and
independent, (2) the Parties shall negotiate in good faith to restore insofar as practicable the
benefits to each Party that were affected by such ruling, and (3) the remainder of this Agreement shall remain in full force and effect.
12.9 Security Arrangements
Infrastructure security of electric system equipment and operations and control hardware and software is essential to ensure day-to-day reliability and operational security. FERC expects the NYISO, the Connecting Transmission Owner, Market Participants, and Interconnection
Customers interconnected to electric systems to comply with the recommendations offered by the President’s Critical Infrastructure Protection Board and, eventually, best practice
recommendations from the electric reliability authority. All public utilities are expected to meet basic standards for system infrastructure and operational security, including physical,
operational, and cyber-security practices.
12.10 Environmental Releases
Each Party shall notify the other Party, first orally and then in writing, of the release of
any hazardous substances, any asbestos or lead abatement activities, or any type of remediation
activities related to the Small Generating Facility or the Interconnection Facilities, each of which
may reasonably be expected to affect the other Party. The notifying Party shall: (1) provide the
notice as soon as practicable, provided such Party makes a good faith effort to provide the notice
no later than 24 hours after such Party becomes aware of the occurrence, and (2) promptly
furnish to the other Party copies of any publicly available reports filed with any governmental authorities addressing such events.
12.11 Subcontractors
Nothing in this Agreement shall prevent a Party from utilizing the services of any
subcontractor as it deems appropriate to perform its obligations under this Agreement; provided, however, that each Party shall require its subcontractors to comply with all applicable terms and conditions of this Agreement in providing such services and each Party shall remain primarily liable to the other Party for the performance of such subcontractor.
12.11.1 The creation of any subcontract relationship shall not relieve the hiring
Party of any of its obligations under this Agreement. The hiring Party shall
be fully responsible to the other Party to the extent provided for in
Sections 32.7.2 and 32.7.3 above for the acts or omissions of any
subcontractor the hiring Party hires as if no subcontract had been made;
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
provided, however, that in no event shall the Connecting Transmission
Owner be liable for the actions or inactions of the Interconnection
Customer or its subcontractors with respect to obligations of the
Interconnection Customer under this Agreement. Any applicable
obligation imposed by this Agreement upon the hiring Party shall be
equally binding upon, and shall be construed as having application to, any
subcontractor of such Party.
12.11.2The obligations under this article will not be limited in any way by any
limitation of subcontractor’s insurance.
12.12 Reservation of Rights
Nothing in this Agreement shall alter the right of the Connecting Transmission Owner to make unilateral filings with FERC to modify this Agreement with respect to any rates, terms and conditions, charges, classifications of service, rule or regulation under Section 205 or any other applicable provision of the Federal Power Act and FERC’s rules and regulations thereunder
which rights are expressly reserved herein, and the existing rights of the Interconnection
Customer to make a unilateral filing with FERC to modify this Agreement under any applicable provision of the Federal Power Act and FERC’s rules and regulations are also expressly reserved herein; provided that each Party shall have the right to protest any such filing by the other Party and to participate fully in any proceeding before FERC in which such modifications may be
considered. Nothing in this Agreement shall limit the rights of the Parties or of FERC under
Sections 205 or 206 of the Federal Power Act and FERC’s rules and regulations, except to the
extent that the Parties otherwise agree as provided herein.
Article 13: Notices
13.1General
Unless otherwise provided in this Agreement, any written notice, demand, or request required or authorized in connection with this Agreement shall be deemed properly given if delivered in person, delivered by recognized national currier service, or sent by first class mail, postage prepaid, to the person specified below:
If to the Interconnection Customer:
LaChute Hydro Company, LLC Attn: General Counsel
100 Brickstone Square, Suite 300 Andover, MA 01810
Phone: 978-560-7810
Email: generalcounsel@enel.com
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
If to the Connecting Transmission Owner:
Kathryn Cox-Arslan
Director, Transmission Commercial National Grid
40 Sylvan Road
Waltham, MA 02451
Phone: (781) 907-2406
Fax: (781) 907-5707
Email: Kathryn.cox-arslan@nationalgrid.com
If to the NYISO:
Before commercial operation of the Large Generating Facility:
New York Independent System Operator, Inc.
Attn: Vice President, Operations
10 Krey Boulevard
Rensselaer, NY 12144
Phone: (518) 356-6000
Fax: (518) 356-6118
After commercial operation of the Large Generating Facility:
New York Independent System Operator, Inc.
Attn: Vice President, Operations
3890 Carman Road
Schenectady, NY12303
Phone:(518) 356-6000
Fax:(518) 356-6118
13.2Billing and Payment
Billings and payments shall be sent to the addresses set out below: Interconnection Customer:
LaChute Hydro Company, LLC
Attention: Accounts Payable
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
100 Brickstone Square, Suite 300 Andover, MA 01810
Connecting Transmission Owner:
Kathryn Cox-Arslan
Director, Transmission Commercial National Grid
40 Sylvan Road
Waltham, MA 02451
Phone: (781) 907-2406
Fax: (781) 907-5707
Email: Kathryn.cox-arslan@nationalgrid.com
13.3 Alternative Forms of Notice
Any notice or request required or permitted to be given by either Party to the other and not required by this Agreement to be given in writing may be so given by telephone or e-mail to the telephone numbers and e-mail addresses set out below:
If to the Interconnection Customer:
LaChute Hydro Company, LLC Attention: General Counsel
100 Brickstone Square, Suite 300 Andover, MA 01810
Phone: (978) 681-1900
Email: generalcounsel@enel.com
If to the Connecting Transmission Owner:
Kathryn Cox-Arslan
Director, Transmission Commercial National Grid
40 Sylvan Road
Waltham, MA 02451
Phone: (781) 907-2406
Fax: (781) 907-5707
Email: Kathryn.cox-arslan@nationalgrid.com
If to the NYISO:
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
New York Independent System Operator, Inc. Attn: Vice President, Operations
10 Krey Boulevard
Rensselaer, NY 12144
Phone: (518) 356-6000
Fax: (518) 356-6118
13.4 Designated Operating Representative
The Parties may also designate operating representatives to conduct the communications
which may be necessary or convenient for the administration of this Agreement. This person will
also serve as the point of contact with respect to operations and maintenance of the Party’s
facilities.
Interconnection Customer’s Operating Representative:
LaChute Hydro Company LLC
Attention: Stephen Pike
100 Brickstone Square, Suite 300 Andover, MA 02451
Phone: (508) 380-6495
Email: Stephen.pike@enel.com
Connecting Transmission Owner’s Operating Representative:
Kathryn Cox-Arslan
Director, Transmission Commercial National Grid
40 Sylvan Road
Waltham, MA 02451
Phone: (781) 907-2406
Fax: (781) 907-5707
Email: Kathryn.cox-arslan@nationalgrid.com
NYISO’s Operating Representative:
New York Independent System Operator, Inc. Attn: Vice President, Operations
3890 Carman Road
Schenectady, NY 12303
Phone: (518) 356-6000
Fax: (518) 356-6118
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
13.5Changes to the Notice Information
Either Party may change this information by giving five Business Days written notice prior to the effective date of the change.
[SIGNATURE PAGE TO FOLLOW]
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Article 14.Signatures
IN WITNESS WHEREOF, the Parties have caused this Agreement to be executed by their respective duly authorized representatives.
For the Connecting Transmission Owner
For the Interconnection Customer
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Attachment 1 - Glossary of Terms
Affected System - An electric system other than the transmission system owned, controlled or operated by the Connecting Transmission Owner that may be affected by the proposed
interconnection.
Affected System Operator - Affected System Operator shall mean the operator of any Affected
System.
Affected Transmission Owner - The New York public utility or authority (or its designated
agent) other than the Connecting Transmission Owner that: (i) owns facilities used for the
transmission of Energy in interstate commerce and provides Transmission Service under the
Tariff, and (ii) owns, leases or otherwise possesses an interest in a portion of the New York State Transmission System where System Deliverability Upgrades or System Upgrade Facilities are installed pursuant to Attachment Z and Attachment S to the ISO OATT.
Applicable Laws and Regulations - All duly promulgated applicable federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments, directives, or judicial or
administrative orders, permits and other duly authorized actions of any Governmental Authority, including but not limited to Environmental Law.
Applicable Reliability Standards - The criteria, requirements and guidelines of the North
American Electric Reliability Council, the Northeast Power Coordinating Council, the New York State Reliability Council and related and successor organizations, or the Transmission District to which the Interconnection Customer’s Small Generating Facility is directly interconnected, as
those criteria, requirements and guidelines are amended and modified and in effect from time to time; provided that neither Party shall waive its right to challenge the applicability of or validity of any criterion, requirement or guideline as applied to it in the context of Attachment Z to the
ISO OATT and this Agreement. For the purposes of this Agreement, this definition of
Applicable Reliability Standards shall supersede the definition of Applicable Reliability
Standards set out in Attachment X to the ISO OATT.
Base Case - The base case power flow, short circuit, and stability data bases used for the
Interconnection Studies by NYISO, Connecting Transmission Owner or Interconnection
Customer; described in Section 32.2.3 of the Large Facility Interconnection Procedures.
Breach - The failure of a Party to perform or observe any material term or condition of this Agreement.
Business Day - Monday through Friday, excluding federal holidays.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Capacity Resource Interconnection Service - The service provided by NYISO to
Interconnection Customers that satisfy the NYISO Deliverability Interconnection Standard or that are otherwise eligible to receive CRIS in accordance with Attachment S to the ISO OATT; such service being one of the eligibility requirements for participation as a NYISO Installed
Capacity Supplier.
Connecting Transmission Owner - The New York public utility or authority (or its designated agent) that: (i) owns facilities used for the transmission of Energy in interstate commerce and provides Transmission Service under the Tariff, (ii) owns, leases or otherwise possesses an
interest in the portion of the New York State Transmission System or Distribution System at the Point of Interconnection, and (iii) is a Party to this Agreement.
Default - The failure of a Party in Breach of this Agreement to cure such Breach under this Agreement.
Distribution System - The Transmission Owner’s facilities and equipment used to distribute
electricity that are subject to FERC jurisdiction, and are subject to the NYISO’s Large Facility Interconnection Procedures in Attachment X to the ISO OATT or Small Generator
Interconnection Procedures in Attachment Z to the ISO OATT under FERC Order Nos. 2003
and/or 2006. For the purpose of this Agreement, the term Distribution System shall not include LIPA’s distribution facilities.
Distribution Upgrades - The additions, modifications, and upgrades to the Connecting
Transmission Owner’s Distribution System at or beyond the Point of Interconnection to facilitate interconnection of the Small Generating Facility and render the transmission service necessary to effect the Interconnection Customer’s wholesale sale of electricity in interstate commerce.
Distribution Upgrades do not include Interconnection Facilities or System Upgrade Facilities or System Deliverability Upgrades.
Energy Resource Interconnection Service - The service provided by NYISO to interconnect
the Interconnection Customer’s Small Generating Facility to the New York State Transmission
System or Distribution System in accordance with the NYISO Minimum Interconnection
Standard, to enable the New York State Transmission System to receive Energy and Ancillary
Services from the Small Generating Facility, pursuant to the terms of the ISO OATT.
Force Majeure - Any act of God, labor disturbance, act of the public enemy, war, insurrection, riot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, any order, regulation or restriction imposed by governmental, military or lawfully established civilian authorities, or any other cause beyond a Party’s control. A Force Majeure event does not
include an act of negligence or intentional wrongdoing. For the purposes of this Agreement, this definition of Force Majeure shall supersede the definitions of Force Majeure set out in
Section 32.2.11 of the NYISO Open Access Transmission Tariff.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Good Utility Practice - Any of the practices, methods and acts engaged in or approved by a
significant portion of the electric industry during the relevant time period, or any of the practices,
methods and acts which, in the exercise of reasonable judgment in light of the facts known at the
time the decision was made, could have been expected to accomplish the desired result at a
reasonable cost consistent with good business practices, reliability, safety and expedition. Good
Utility Practice is not intended to be limited to the optimum practice, method, or act to the
exclusion of all others, but rather to be acceptable practices, methods, or acts generally accepted
in the region.
Governmental Authority - Any federal, state, local or other governmental regulatory or
administrative agency, court, commission, department, board, or other governmental subdivision, legislature, rulemaking board, tribunal, or other governmental authority having jurisdiction over the Parties, their respective facilities, or the respective services they provide, and exercising or entitled to exercise any administrative, executive, police, or taxing authority or power; provided, however, that such term does not include the Interconnection Customer, NYISO, Affected
Transmission Owner, Connecting Transmission Owner or any Affiliate thereof.
Interconnection Customer - The entity, including the Transmission Owner or any of the
affiliates or subsidiaries, that proposes to interconnect its Small Generating Facility with the New York State Transmission System or the Distribution System.
Interconnection Facilities - The Connecting Transmission Owner’s Interconnection Facilities
and the Interconnection Customer’s Interconnection Facilities. Collectively, Interconnection
Facilities include all facilities and equipment between the Small Generating Facility and the
Point of Interconnection, including any modification, additions or upgrades that are necessary to
physically and electrically interconnect the Small Generating Facility to the New York State
Transmission System or the Distribution System. Interconnection Facilities are sole use
facilities and shall not include Distribution Upgrades or System Upgrade Facilities.
Interconnection Request - The Interconnection Customer’s request, in accordance with the
Tariff, to interconnect a new Small Generating Facility, or to materially increase the capacity of,
or make a material modification to the operating characteristics of, an existing Small Generating
Facility that is interconnected with the New York State Transmission System or the Distribution
System. For the purposes of this Agreement, this definition of Interconnection Request shall
supersede the definition of Interconnection Request set out in Attachment X to the ISO OATT.
Interconnection Study - Any study required to be performed under Sections 32.2 or 32.3 of the
SGIP.
ISO - The NYISO.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Material Modification - A modification that has a material impact on the cost or timing of any Interconnection Request with a later queue priority date.
New York State Transmission System - The entire New York State electric transmission
system, which includes: (i) the Transmission Facilities under ISO Operational Control; (ii) the
Transmission Facilities Requiring ISO Notification; and (iii) all remaining transmission facilities within the New York Control Area.
NYISO - The New York Independent System Operator, Inc. or its successor.
NYISO Deliverability Interconnection Standard - The standard that must be met, unless
otherwise provided for by Attachment S to the ISO OATT, by (i) any generation facility larger
than 2 MW in order for that facility to obtain CRIS; (ii) any Class Year Transmission Project
proposing to interconnect to the New York State Transmission System and receive Unforced
Capacity Delivery Rights; (iii) any entity requesting External CRIS Rights, and (iv) any entity
requesting a CRIS transfer pursuant to Section 25.9.5 of Attachment S to the ISO OATT. To
meet the NYISO Deliverability Interconnection Standard, the Interconnection Customer must, in
accordance with the rules in Attachment S to the ISO OATT, fund or commit to fund any System
Deliverability Upgrades identified for its project in the Class Year Deliverability Study.
NYISO Minimum Interconnection Standard - The reliability standard that must be met by any
generation facility or Class Year Transmission Project that is subject to NYISO’s Large Facility
Interconnection Procedures in Attachment X to the ISO OATT or the NYISO’s Small Generator
Interconnection Procedures in this Attachment Z, that is proposing to connect to the New York
State Transmission System or Distribution System, to obtain ERIS. The Minimum
Interconnection Standard is designed to ensure reliable access by the proposed project to the
New York State Transmission System or to the Distribution System. The Minimum
Interconnection Standard does not impose any deliverability test or deliverability requirement on
the proposed interconnection.
OATT - The Tariff.
Operating Requirements - Any operating and technical requirements that may be applicable due to Regional Transmission Organization, Independent System Operator, control area, or the Connecting Transmission Owner’s requirements, including those set forth in this Agreement. Operating Requirements shall include Applicable Reliability Standards.
Party or Parties - The Connecting Transmission Owner or Interconnection Customer or both.
Point of Interconnection - The point where the Interconnection Facilities connect with the New York State Transmission System or the Distribution System.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Reasonable Efforts - With respect to an action required to be attempted or taken by a Party
under this Agreement, efforts that are timely and consistent with Good Utility Practice and are
otherwise substantially equivalent to those a Party would use to protect its own interests.
Small Generating Facility - The Interconnection Customer’s device no larger than 20 MW for
the production and/or storage for later injection of electricity identified in the Interconnection
Request, but shall not include the Interconnection Customer’s Interconnection Facilities.
System Deliverability Upgrades - The least costly configuration of commercially available
components of electrical equipment that can be used, consistent with Good Utility Practice and Applicable Reliability Requirements, to make the modifications or additions to the existing New York State Transmission System that are required for the proposed project to connect reliably to the system in a manner that meets the NYISO Deliverability Interconnection Standard for
Capacity Resource Interconnection Service.
System Upgrade Facilities - The least costly configuration of commercially available
components of electrical equipment that can be used, consistent with good utility practice and
Applicable Reliability Requirements to make the modifications to the existing transmission
system that are required to maintain system reliability due to: (i) changes in the system,
including such changes as load growth and changes in load pattern, to be addressed in the form
of generic generation or transmission projects; and (ii) proposed interconnections. In the case of
proposed interconnection projects, System Upgrade Facilities are the modification or additions to
the existing New York State Transmission System that are required for the proposed project to
connect reliably to the system in a manner that meets the NYISO Minimum Interconnection
Standard.
Tariff - The NYISO’s Open Access Transmission Tariff, as filed with the FERC, and as amended or supplemented from time to time, or any successor tariff.
Upgrades - The required additions and modifications to the Connecting Transmission Owner’s
portion of the New York State Transmission System or the Distribution System at or beyond the
Point of Interconnection. Upgrades may be System Upgrade Facilities or System Deliverability
Upgrades Distribution Upgrades. Upgrades do not include Interconnection Facilities.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Attachment 2
Detailed Scope of Work, Including Description and Costs of the Small Generating
Facility, Interconnection Facilities, and Metering Equipment
A. Interconnection Customer’s Interconnection Facilities: LaChute Hydro is served by the
Company’s 115kV transmission system via the Ticonderoga-Republic #2 line. The
developer accepts service through their own Customer-owned electric substation which
includes a main disconnect (Switch #6188), and associated ground switch Company
metering at the 115kv service voltage, Circuit Breaker R61, Transformer and various
relay and associated protective devices. The Customer’s Interconnection Facilities also
include an RTU.
B. Connecting Transmission Owner’s Interconnection Facilities: The Connecting
Transmission Owner, National Grid, provides a three-phase 115kV, single circuit service lateral to the Customer’s Facility. The Company attaches to the Customer’s take-off
structure with Company-owned strain insulators, which provide the physical line of
demarcation between the Company and Customer facilities (with exception of Company billing metering transformers and meter). The Connecting Transmission Owner’s
Interconnection Facilities include metering and associated equipment.
C. Point of Interconnection: The Company provides a three phase single circuit tap to the
Customer’s take-off structure. The point of interconnection between the Company and Customer facilities is the jaw-side of Customer-owned switch #6188 located on the Company’s take-off structure.
D. Point of Change of Ownership: The Customer owns all facilities electrically downstream
from the Company’s strain insulators, located on the Customer’s take-off structure (with exception of Company billing metering transformers and meter).
E. O&M Expenses for Interconnection Facilities:
In accordance with Article 4.1 of this Agreement, the Interconnection Customer shall be responsible for all reasonable expenses associated with the operation, maintenance, repair and replacement of the Connecting Transmission Owner’s Interconnection Facilities, as such facilities are detailed in this Attachment 2 (“O&M Expenses”).
F. Legacy ERIS and CRIS Rights:
The Interconnection Customer shall receive Energy Resource Interconnection Service
(“ERIS”) in an amount equal to 9.0 MW, and Capacity Resource Interconnection Service
(“CRIS”) in an amount equal to 8.9 MW, the amount of legacy ERIS and CRIS rights
allocated to the Interconnection Customer in the 2019 NYISO Load & Capacity Gold
Book, found at: https://www.nyiso.com/documents/20142/2226333/2019-Gold-Book-
Final-Public.pdf/. The Interconnection Customer’s ERIS and CRIS values will be
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
limited to their legacy values unless they are subsequently increased pursuant to an applicable provision of the NYISO OATT.
The Interconnection Customer shall have the option to pay such O&M Expenses either under the procedure described in Option 1 or in Option 2 below.
Option 1: Fixed On-Going Charge Payment:
The Connecting Transmission Owner will invoice and Interconnection Customer shall
pay an annual payment to the Connecting Transmission Owner equal to the product of the Gross
Plant Investment associated with the Connecting Transmission Owner Interconnection Facility
and the Annual Transmission Ongoing Charge Factor, for the term of this Interconnection
Agreement.
All payments due to be made by the Interconnection Customer shall be made within thirty (30) days after receiving an invoice from the Connecting Transmission Owner.
The Project’s Gross Connecting Transmission Owner’s Interconnection Facilities Plant Investment cost shall be established in writing by the Connecting Transmission Owner no later than 90 days following commercial operation.
The Annual Transmission On-Going Charge Factor shall be calculated annually
each July based on the Connecting Transmission Owner’s most recent FERC Form 1 data and
will equal the sum of the Revenue Requirement Components as identified in O&M Attachment 1 divided by the Total Gross Plant of the Connecting Transmission Owner. Total Gross Plant shall equal the sum of Item Nos. A (1)(a)(b)(c) in O&M Attachment 1.
Option 2: Annual Actual O&M Expenses:
The Interconnection Customer shall pay for all actual O&M Expenses incurred by the
Connecting Transmission Owner, which expenses shall be billed by the Connecting
Transmission Owner quarterly as accumulated during the quarter for which they were incurred.
All payments due to be made by the Interconnection Customer shall be made within thirty (30) days after receiving an invoice from the Connecting Transmission Owner, which invoice shall be issued after the end of each quarter for the most recent quarter.
Selection by Interconnection Customer:
The Interconnection Customer shall select which option for paying such O&M Expenses by providing written notice to the Connecting Transmission Owner within thirty (30) days after the Gross Connecting Transmission Owner’s Interconnection Facilities Plant Investment cost and the most recent Annual Transmission Ongoing Charge Factor have been provided to the
Interconnection Customer. If the Interconnection Customer fails to provide timely notice to the Connecting Transmission Owner of the option selected, the Interconnection Customer will be deemed to have selected Option 2: Annual Actual O&M Expenses.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
O&M ATTACHMENT 1
Capitalized terms used in this calculation will have the following definitions:
Allocation Factor
(1) General Plant Allocation Factor shall equal Electric General Plant divided by the sum of
Electric General Plant plus gas general plant as reported in the Annual Report filed with the New York State Public Service Commission.
(2) Gross Transmission Plant Allocation Factor shall equal the total investment in
Transmission Plant in Service divided by the sum of the total Transmission Plant in Service plus
the total Distribution Plant in Service, excluding Intangible Plant, General Plant and Common
Plant.
(3) Transmission Wages and Salaries Allocation Factor shall equal the ratio of Connecting
Transmission Owner Transmission-related direct electric wages and salaries including any direct wages or salaries charged to Connecting Transmission Owner by a National Grid Affiliate to Connecting Transmission Owner’s total electric direct wages and salaries including any wages charged to Connecting Transmission Owner by a National Grid Affiliate excluding any electric administrative and general wages and salaries.
Ratebase and Expense Items
(1) Administrative and General Expense shall equal electric expenses as recorded in FERC Account Nos. 920-935.
(2) Amortization of Investment Tax Credits shall equal electric credits as recorded in FERC Account No. 411.4.
(3) Distribution Plant in Service shall equal the gross plant balance as recorded in FERC Account Nos. 360 - 374.
(4) Electric Common Plant shall equal the balance of Common Plant recorded in FERC Account Nos. 389-399 multiplied by the General Plant Allocation Factor.
(5) General Plant shall equal electric gross general plant balance recorded in FERC Account Nos. 389-399.
(6) Materials and Supplies shall equal electric materials and supplies balance as recorded in FERC Account No. 154.
(7) Payroll Taxes shall equal those electric payroll tax expenses as recorded in FERC Account Nos. 408.100, 408.110 and 408.130.
(8) Prepayments shall equal electric prepayment balance as recorded in FERC Account
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
No. 165.
(9) Real Estate Tax Expenses shall equal electric transmission-related real estate tax expense as recorded in FERC Account No. 408.140 and 408.180.
(10) Transmission Operation and Maintenance Expense shall equal electric expenses as recorded in FERC Account Nos. 560, 562-573.
(11) Transmission Plant in Service shall equal the gross plant balance as recorded in FERC Account Nos. 350-359.
(12) Transmission Revenue Credits shall equal the revenue reported in Account 456
(13) Transmission Related Bad Debt Expense shall equal Bad Debt Expense as reported in Account 904 related to transmission billing.
(14) Wholesale Metering Cost shall equal any costs associated with any Revenue or Remote
Terminal Unit (RTU) meters and associated equipment located at an internal or external tie at
voltages equal to or greater than 23V. The cost shall be determined by multiplying the number of wholesale meters in FERC Account No. 370.3 by the average cost of the meters plus the average costs of installation.
In the event that the above-referenced FERC accounts are renumbered, renamed, or otherwise modified, the above sections shall be deemed amended to incorporate such
renumbered, renamed, modified or additional accounts.
Revenue Requirement Components
The Revenue Requirement Components shall be the sum of Connecting Transmission
Owner’s (A) Return and Associated Income Taxes, (B) Transmission Related Real Estate Tax
Expense, (C) Transmission Related Amortization of Investment Tax Credits, (D) Transmission
Related Payroll Tax Expense (E) Transmission Operation and Maintenance Expense, (F)
Transmission Related Administrative and General Expenses, less (G) Revenue Credits, plus (H)
Bad Debt Expense.
A. Return and Associated Income Taxes shall equal the product of the Transmission
Investment Base as identified in A(1) below and the Cost of Capital Rate.
1. Transmission Investment Base shall be defined as:
Transmission Related General Plant plus Transmission Related Common Plant
plus Transmission Related Regulatory Assets plus Transmission Related
Prepayments plus Transmission Related Materials and Supplies plus Transmission Related Cash Working Capital.
(a) Transmission Plant in Service shall equal the balance of Total investment
in Transmission Plant plus Wholesale Metering Cost.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
(b)Transmission Related General Plant shall equal the balance of investment
in General Plant multiplied by the Transmission Wages and Salaries Allocation Factor.
(c) Transmission Related Common Plant shall equal Electric Common Plant
multiplied by the Gross Transmission Plant Allocation Factor and
multiplied by the Transmission Wages and Salaries Allocation Factor.
(d) Transmission Related Regulatory Assets shall equal balances in FERC
Account Nos. 182.3 and 254 for state and federal regulatory assets and
liabilities related to FAS109, and excess AFUDC multiplied by the Gross Transmission Plant Allocation Factor.
(e)Transmission Related Prepayments shall equal the electric balance of
Prepayments multiplied by the Gross Transmission Plant Allocation
Factor.
(f) Transmission Related Materials and Supplies shall equal the balance of
Materials and Supplies assigned to Transmission added to the remainder
of Material and Supplies not directly assigned to either Transmission or
Distribution multiplied by the Gross Transmission Plant Allocation Factor.
(g) Transmission Related Cash Working Capital shall be a 12.5% allowance
(45 days/360 days) of the Transmission Operation and Maintenance
Expense (less FERC Account 565: Transmission of Electricity by
Others) and Transmission-Related Administrative and General Expense.
2.Cost of Capital Rate
The Cost of Capital Rate shall equal the proposed Weighted Costs of Capital plus Federal Income Taxes and State Income Taxes.
(a) The Weighted Costs of Capital will be calculated for the Transmission
Investment Base using Connecting Transmission Owner’s actual capital structure and will equal the sum of (i), (ii), and (iii) below:
(i) the long-term debt component, which equals the product of the
actual weighted average embedded cost to maturity of Connecting Transmission Owner’s long-term debt then outstanding and the actual long-term debt capitalization ratio;
(ii) the preferred stock component, which equals the product of the
actual weighted average embedded cost to maturity of Connecting Transmission Owner’s preferred stock then outstanding and the actual preferred stock capitalization ratio; and
(iii) the return on equity component, shall be the product of the allowed
ROE of 11.9% plus a 50 basis point adder (per FERC Order 697
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
and 697A) and Connecting Transmission Owner’s actual common equity capitalization ratio.
(b)Federal Income Tax shall equal
A x Federal Income Tax Rate
(1 - Federal Income Tax Rate)
where A is the sum of the preferred stock component and the return on equity component, each as determined in Sections 2.(a)(ii) and for the ROE set forth in 2.(a)(iii) above
(c)State Income Tax shall equal
(A + Federal Income Tax) x State Income Tax Rate
(1 - State Income Tax Rate)
Where A is the sum of the preferred stock component and the return on equity component as determined in A.2.(a)(ii) and A.2.(a)(iii) above and Federal income Tax is determined in 2.(b) above.
B. Transmission Related Real Estate Tax Expense shall equal the Real Estate Tax Expenses
multiplied by the Gross Plant Allocation Factor.
C. Transmission Related Amortization of Investment Tax Credits shall equal the electric
Amortization of Investment Tax Credits multiplied by the Gross Transmission Plant Allocation Factor.
D. Transmission Related Payroll Tax Expense shall equal Payroll Taxes multiplied by the
Transmission Wages and Salaries Allocation Factor.
E. Transmission Operation and Maintenance Expense shall equal the Transmission
Operation and Maintenance Expense as previously defined.
F. Transmission Related Administrative and General Expenses shall equal the sum of the
electric Administrative and General Expenses multiplied by the Transmission Wages and Salaries Allocation Factor.
G.Revenue Credits shall equal all Transmission revenue recorded in FERC account 456.
H.Transmission Related Bad Debt Expense shall equal Transmission Related Bad Debt
Expense as previously defined.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Attachment 3
One-line Diagram Depicting the Small Generating Facility, Interconnection
Facilities, Metering Equipment, and Upgrades
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Attachment 4
Milestones
For the purposes of this Agreement the Commercial Operation Date for this facility is: The Developer completed the RTU Upgrade on 11/13/19:
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Attachment 5
Additional Operating Requirements for the New York State Transmission System,
the Distribution System and Affected Systems Needed to Support the
Interconnection Customer’s Needs
The Interconnection Customer must comply with all applicable NYISO tariffs and
procedures, as amended from time to time. The Interconnection Customer must also comply with the Connecting Transmission Owner’s operating instructions and requirements as referenced in Sections 1.5 and 1.6 of this Agreement, which requirements shall include equipment outages and control arrangements, tagging agreements and procedures, maintenance arrangements and
responsibilities, company contacts and phone numbers and supervisory equipment.
The Interconnection Customer must comply with relevant provisions of the Connecting
Transmission Owner’s Electric System Bulletins, including appendices, as amended from time to time, to the extent not inconsistent with the terms of this Agreement or the NYISO OATT.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Attachment 6
Connecting Transmission Owner’s Description of its Upgrades
and Best Estimate of Upgrade Costs
As of the execution of this Agreement no Upgrade costs are identified.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1
NYISO Agreements --> Service Agreements --> SGIA SA2511 NMPC and LaChute Hydro
Attachment 7
Insurance Coverage
Interconnection Customer shall, at its own expense, maintain in force throughout the
period of this Agreement, the following minimum insurance coverage, with insurers authorized to do business in the State of New York:
Commercial General Liability Insurance including, but not limited to, bodily injury,
property damage, products/completed operations, contractual and personal injury liability with a combined single limit of $1 million per occurrence, $2 million annual aggregate.
Effective Date: 12/19/2019 - Docket #: ER20-823-000 - Page 1