NYISO Tariffs --> Open Access Transmission Tariff (OATT) --> 22 OATT Attachment P - Transmission Interconnection Procedur --> 22 OATT Attachment P - Appendix 1 Transmission Interconnecti

Appendix 1
TRANSMISSION INTERCONNECTION APPLICATION

1.The undersigned Transmission Developer submits this request to interconnect its proposed transmission project with the New York State Transmission System pursuant to Section [*] of the NYISO OATT.

 

2.This Transmission Interconnection Application is submitted by:

Name of Transmission Developer:                              

By (signature):                                              

Name (type or print):                                          

Title:                                                    

Date:                                                    


3.Name of project:                                                  

4.Description of proposed project:

a.Description of proposed Point(s) of Interconnection (i.e., name of existing substation or line to which the project proposes to interconnect):

 

                                                                                                                                                                                                                                                                                                                                                                                

b.General description of the equipment configuration and kV level:

                                                                                                                                                                                                                                                                                                                                                                                

c.Attach a conceptual breaker one-line diagram (i.e., breaker-level details for proposed elements along with high-level depiction of proposed interconnection with existing system)

 

d.  Technical data/parameters: [to be provided as attachment to initial study agreement]

 

e.In-Service Date (Month and Year):                               

f.Name, title, company address, telephone number, and e-mail address of the Transmission Developer’s contact person:

 

                                                                                                                                                                                                                                                                                                                                                                                

 

 

Effective Date: 4/1/2016 - Docket #: ER13-102-009 - Page 1