NYISO Tariffs --> Open Access Transmission Tariff (OATT) --> 25 OATT Attachment S - Rules To Allocate Responsibility For --> 25.4 OATT Att S Interconnection Facilities Covered by Attach

25.4Interconnection Facilities Covered by Attachment S

25.4.1Interconnection Standards

The interconnection facilities covered by these cost allocation rules are (i) those required for the proposed project to reliably interconnect to the New York State Transmission System or to the Distribution System in a manner that meets the NYISO Minimum Interconnection Standard for ERIS, and (ii) those required for the project to meet the NYISO Deliverability Interconnection Standard for CRIS.

25.4.2Interconnection Facilities

The interconnection facilities covered by these cost allocation rules are comprised of the following types of facilities:  Attachment Facilities, Distribution Upgrades, System Upgrade Facilities and System Deliverability Upgrades.

 

Effective Date: 5/19/2016 - Docket #: ER16-1213-000 - Page 1