Point‑To‑Point Transmission Service shall be provided by the ISO only if the following conditions are satisfied by the Transmission Customer:
a.The Transmission Customer has pending a Completed Application for service;
b.The Transmission Customer meets the creditworthiness criteria set forth in Attachment W;
c.The Transmission Customer provides an unconditional and irrevocable letter of credit as security to meet its responsibilities and obligations under the Tariff in an amount calculated by the ISO.
d.The Transmission Customer has arrangements in place for any other Transmission Service necessary to effect the delivery from the generating source to the ISO prior to the time when service under Part 3 of the Tariff commences;
e.The Transmission Customer provides the information required by the ISO’s planning process established in Attachment Y.
f.The Transmission Customer agrees to pay for any facilities constructed and chargeable to such Transmission Customer under Part 3 of the Tariff, whether or not the Transmission Customer takes service; and
g.The Transmission Customer has executed a Point‑To‑Point Service Agreement or has agreed to receive service pursuant to Section 3.3.3; and
h.The Transmission Customer has satisfied the communication requirements and the metering requirements established by the ISO.
i.If the Point‑to‑Point Transmission Service involves the use of LIPA's transmission facilities, approval of such transactions has been granted pursuant to Section 2.5.7.
Any scheduling arrangements that may be required by other Control Areas shall be the responsibility of the Transmission Customer requesting service. The Transmission Customer shall provide, unless waived by the ISO, notification to the ISO identifying such systems and authorizing them to schedule the Capacity and Energy to be transmitted by the ISO pursuant to Part 3 of this Tariff on behalf of the Receiving Party at the Point of Delivery or the Delivering Party at the Point of Receipt. However, the ISO will undertake reasonable efforts to assist the Transmission Customer in making such arrangements, including without limitation, providing any information or data required by such other Control Area consistent with Good Utility Practice.
Effective Date: 6/30/2010 - Docket #: ER10-1657-000 - Page 1