NYISO Tariffs --> Open Access Transmission Tariff (OATT) --> 2 OATT Common Service Provisions --> 2.2 OATT Initial Allocation and Renewal Procedures

2.2Initial Allocation and Renewal Procedures

2.2.1Initial Allocation of Available Transfer Capability: 

Firm Transmission Service under this Tariff is obtained when the Transmission Customer agrees to pay the Congestion associated with its service.  A Transmission Customer may fix the price of Congestion costs associated with its Firm Transmission Service through the purchase of a sufficient quantity of Transmission Congestion Contracts (“TCCs”), including Fixed Price TCCs that are obtained under Attachment M to this Tariff, with receipt and delivery points corresponding to its Transmission Service.  TCCs are solely financial instruments that do not establish any rights to, or the availability of, Transmission Service.  For purposes of determining whether existing capability on the NYS Transmission System is adequate to accommodate a request for Firm Transmission Service under this Tariff, the ISO shall employ Security Constrained Unit Commitment (“SCUC”), Real-Time Commitment (“RTC”) and Real-Time Dispatch (“RTD”) programs in accordance with Attachment C.  The availability of TCCs will be determined as described in Attachment M.

2.2.2Reservation Priority For Existing Firm Service: 

Existing firm service customers (wholesale requirements and transmissiononly, with a contract term of extending beyond the ISO implementation date), have the right to take Transmission Service from the ISO in accordance with the provisions of Attachment K.  This transmission reservation priority is independent of whether the existing customer continues to purchase Capacity and Energy from a Transmission Owner or elects to purchase Capacity and Energy from another Supplier. 

At the end of their contract terms, certain LSEs may have the right to obtain Fixed Price TCCs in accordance with Attachment M to this Tariff.

All NYS Transmission Capacity associated with expired Grandfathered Rights and/or Grandfathered TCCs other than that needed to support Fixed Price TCCs, shall be made available to support TCCs available for purchase in the next Centralized TCC auction facilitated by the ISO, pursuant to the provisions of Attachment M.

 

Effective Date: 6/30/2010 - Docket #: ER10-1657-000 - Page 1