UNITED STATES OF AMERICA
BEFORE THE

FEDERAL ENERGY REGULATORY COMMISSION

 

)

New York Independent System Operator, Inc.)Docket Nos. ER12-1653-___;

)ER13-____-000

)

 

NEW YORK INDEPENDENT SYSTEM OPERATOR, INC. REQUEST FOR LIMITED TARIFF WAIVER, SHORTENED COMMENT PERIOD,
AND EXPEDITED COMMISSION ACTION

 

Pursuant to Rule 207(a)(5) of the Federal Energy Regulatory Commission

(“Commission” or “FERC”) Rules of Practice and Procedure, 18 C.F.R. § 385.207(a)(5),
the New York Independent System Operator, Inc. (“NYISO”) respectfully requests a
temporary, limited waiver of Sections 23.3.3.3.1.1 and 23.3.3.3.1.2 of (Attachment H to)
its Market Services Tariff (“Waiver Request”).1  The Tariff rules that NYISO requests a
temporary waiver of require the NYISO to (a) determine whether the application of real-
time guarantee payment (“RTGP”) is appropriate, (b) post settlement results that reflect
the application of RTGP mitigation, and (c) provide notice to Market Parties2 of the effect
that RTGP mitigation has on a Market Party’s real-time Bid Production Cost Guarantee
(“BPCG”), within very tight time deadlines.  The NYISO relies on the RTGP mitigation
software that it has developed to achieve these Tariff-specified deadlines.3

 

 

 

1 Section 23 of (Attachment H to) the NYISO’s Market Services Tariff sets forth the NYISO’s Market Power Mitigation Measures.

2 Capitalized terms that are not expressly defined in this Waiver Request have the meaning ascribed to them in either Section 23.2.1 of (Attachment H to) the NYISO Market Services Tariff, or in Section 2 of the
NYISO’s Market Services Tariff.

3 The NYISO’s “RTGP mitigation software” is not a discrete set of software components that are dedicated solely to applying RTGP mitigation.  Rather the RTGP mitigation software includes components of the
NYISO’s Bid entry, market operation, and settlement software that are all designed to work together to
achieve Tariff compliance.


 

 

The NYISO planned to implement RTGP mitigation of Regulation Movement and
Regulation Capacity Bids outside of its existing guarantee payment mitigation software
until it was able to incorporate Regulation Capacity and Regulation Movement Bids and
reference levels into the existing RTGP mitigation software.4  The NYISO did not
recognize   that   the   existing   RTGP   notification   deadlines   also   apply   to   the
new/additional/supplemental   RTGP  mitigation  of   Regulation  Capacity  Bids   and
Regulation Movement Bids.5  Until Regulation Capacity and Regulation Movement Bids
and reference levels are included and tested in the RTGP mitigation software it is not
possible  for  the  NYISO  to  determine  the  effect  that  conduct-failing  Regulation
Movement or Regulation Capacity Bids have on guarantee payments within the Tariff-
specified time deadlines, nor is it possible for the NYISO to reflect the application of
RTGP mitigation of these Bids in posted settlement results or inform affected Market
Parties within the timelines specified in Sections 23.3.3.3.1.1 and 23.3.3.3.1.2 of its
Mitigation  Measures.    The  NYISO  expects  to  complete  the  necessary  software
improvements by October 23, 2013.

The NYISO respectfully requests that the Commission waive the following Tariff requirements from June 26, 2013 (the date that the NYISO’s Order No. 755 Compliance Filing became effective) to October 23, 2013:

(a) The requirement to determine the impact of conduct-failing  Regulation
Capacity and Regulation Movement Bids on RTGP to a Market Party, for a

 

 

4 See, e.g., P 30 of the Affidavit of Dr. Pallas LeeVanSchaick that was submitted as Attachment I to the

NYISO’s January 22, 2013 Compliance Filing in Docket No. ER12-1653-000 (“the mitigation measures for Ancillary Services are applied manually, rather than in an automated fashion…”).

5 It is not appropriate to separately test particular Bids/Bid components for BPCG impact because the RTGP impact test compares total costs to total revenues over a Real-Time Market day.

 

 

2


 

 

Generator, for a Real-Time Market day, by the time it posts settlement results for that Real-Time Market day.  Settlement results are ordinarily posted approximately two days after each real-time market day6;

(b) the requirement to post settlement results that reflect the application of RTGP
mitigation (that includes the impact of conduct-failing Regulation Capacity
Bids and Regulation Movement Bids) in the initial settlement results it posts
approximately two days after each real-time market day; and

(c) the requirement to send an e-mail to Market Parties informing them of RTGP
mitigation and inviting them to initiate a consultation no more than two
business days after new or revised real-time guarantee payment impact test
settlement results are posted.

The NYISO will continue to apply all other aspects of RTGP mitigation within the timeframes specified in the Mitigation Measures.7

For the reasons explained in Section IV of this Waiver Request, the NYISO’s
error was made as part of a good-faith effort to implement the requirements of Order No.
755.  The requested waiver is of limited scope—it seeks to extend the time that the
NYISO has to consult with and RTGP impact test Regulation Suppliers that (i) submit
conduct-failing Regulation Capacity or Regulation Movement Bids and (ii) receive a

 

 

6 The initial posting of settlement results “ordinarily” occurs two days after the relevant real-time market
day.  The NYISO has not seriously considered or proposed delaying the posting of settlement results in
order to achieve compliance with the RTGP mitigation posting requirements.  Instead, the NYISO
submitted this waiver request to achieve Tariff compliance without disrupting the NYISO settlement
process.

7 If a Market Party’s Bids are determined to exceed the RTGP impact threshold, the NYISO mitigates all conduct-failing Bids.  If including conduct-failing Regulation Capacity and Regulation Movement Bids in the RTGP test causes a Market Party’s Bids for a Generator to exceed the relevant RTGP impact threshold, then the NYISO will mitigate all of the conduct-failing Bids, not just the conduct-failing Regulation
Capacity or Regulation Movement Bids.

 

 

3


 

 

BPCG.  The requested waiver is for a limited duration—from June 26, 2013 to October
23, 2013.  The NYISO’s inability to timely perform RTGP impact tests and provide
Tariff-required notice to some Market Parties presents a concrete problem that needs to
be remedied.  Finally, the requested waiver will not have undesirable consequences, such
as harming third parties.  To the contrary, granting the waiver will protect loads from
possibly overpaying for Regulation Service, while ensuring that regulation providers
have the opportunity to recover their costs of providing Regulation Service.

The NYISO will implement the software improvements as soon as they are
completed, tested, and deployed to production.  The NYISO hopes to complete the
necessary work before the end of the requested waiver period.  The NYISO will provide
notice to the Commission and to its Market Participants at least one week prior to
implementing the software improvements that are necessary to incorporate Regulation
Capacity and Regulation Movement Bids and reference levels into the NYISO’s RTGP
mitigation software.

I.BACKGROUND

In its August 31, 2007 RTGP filing in Docket No. ER07-1334, the NYISO described how it performs RTGP mitigation8:

Under the Services Tariff, generators submit three-part Bids into the Real-
Time Market: (i) Incremental Energy Bids (which are used to set the
LBMP), (ii) Minimum Generation Bids, and (iii) Start-Up Bids.  The three
Bids are collectively used to determine whether a generator is eligible to
receive  a  Bid  Production  Cost  guarantee (“BPCG”  or “guarantee”)

payment for a given 24 hour operating day.  Absent mitigation, a BPCG
payment is made if a given generator’s total as-Bid costs exceed its LBMP
plus Ancillary Service revenues for the operating day.  BPCG payments

 

 

 

8 Citations to specific provisions of the Market Mitigation Measures (“MMM”) in the quoted language have been updated to identify the currently effective tariff provisions.

 

 

4


 

 

 

 

 

are necessarily determined on a unit-by-unit basis after the results of a full day’s schedules are available.

 

Under the MMM, competitive “reference levels”9 are established for each
generator’s Incremental Energy, Minimum Generation and Start-Up Bids.
Bids that exceed the relevant reference level by the conduct thresholds
specified in Section 23.3.1.2 of the MMM fail the conduct test and are
eligible for guarantee payment mitigation if they would also result in a
real-time BPCG payment to the generator that is 50% (in New York City)
or 200% (in the rest of New York State) greater than the “reference”
BPCG payment that would be available for the operating day if all
conduct-failing Bids were replaced with reference levels (the “RTGP

Impact Test”).10  Stated another way, the RTGP Impact Test compares

(i) the BPCG payment that a generator would receive if its Bids that fail
the conduct test were replaced with reference levels (the “Reference

BPCG”), to (ii) the BPCG payment that the generator would receive if the
generator were compensated based on the offers the NYISO used to run its
Real-Time Market (the “Initial BPCG”).  If the comparison of the Initial
BPCG to the Reference BPCG indicates that the generator’s offers
increased its BPCG payment by more than 50% (in New York City) or by
more than 200% (in the rest of New York State), then all of the
generator’s conduct-failing Bids are mitigated for the entire operating day
and a revised BPCG payment (which can never be less than $0) is
calculated based on the mitigated offers.  [Highlighting added.]

In an affidavit submitted in support of the NYISO’s January 22, 2013 compliance
filing in Docket No. ER12-1653, Dr. Pallas LeeVanSchaick of Potomac Economics (the
“Affidavit”), the NYISO’s Market Monitoring Unit, identified the potential for BPCG
payments to be inflated if suppliers were to raise the Regulation Capacity or Regulation
Movement Bids of their inframarginal resources above those resources marginal cost of
providing the service.

For the reasons explained in PP 23-25 of Dr. LeeVanSchaick’s Affidavit, it is no
longer appropriate for the NYISO to simply include net Ancillary Service revenues when
performing the RTGP impact test.  The NYISO’s implementation of the Commission’s

 

 

9 MMM § 23.3.1.4.

10 MMM § 23.3.2.1.

 

 

5


 

 

Order No. 755 requirements necessitates a more sophisticated comparison of Regulation
Bids  to  Regulation  reference  levels  to  accurately  effectuate  BPCG  mitigation.11
Unfortunately, the NYISO and the Market Monitoring Unit did not recognize that all of
the Tariff requirements for applying RTGP mitigation also apply to the new/improved
measures.

II.RELEVANT TARIFF PROVISIONS

Section23.3.3.3.1.1  of  the  NYISO’s  Market  Power  Mitigation  Measures

(“Mitigation Measures”) requires the NYISO to:

[E]lectronically post settlement results informing Market Parties of Bid(s) that failed the real-time guarantee payment impact test.  The settlement results posting shall include the adjustments to the guarantee payment and the mitigated Bid(s).  The initial posting of settlement results ordinarily occurs two days after the relevant real-time market day.

Section 23.3.3.3.1.2 of the Mitigation Measures requires the NYISO to:

 

For real-time guarantee payment mitigation … no more than two business days after new or revised real-time guarantee payment impact test settlement results are posted, the ISO will send an e-mail or other notification to all potentially impacted Market Parties…

The NYISO timely posts real-time settlement results that include the information
required in Section 23.3.3.3.1.1 of its Mitigation Measures.  The NYISO also has a
process in place to timely issue e-mail notices inviting Market Parties to consult with the
NYISO regarding instances of RTGP mitigation.  However, as explained above, the real-
time guarantee payment impact test that was accepted for filing by the Commission in
Docket No. ER07-1334-000 simply includes net ancillary service revenues.12  The

 

 

11 Generators that are submitting Bids into the Real-Time Market, and that are capable of providing

Spinning Reserve, 10-Minute Non-Synchronized Reserves, and 30-Minute Reserves, are required to offer these products at zero cost, so there is no need to conduct or impact test real-time offers of these products. See Section 23.3.1.4.6 of the Mitigation Measures.

12 See New York Independent System Operator, Inc., 121 FERC ¶ 61,112 at P 2 and n.2 (2007).

 

 

6


 

 

NYISO has not previously tested and mitigated specific ancillary service components in its real-time guarantee payment conduct and impact testing process.

III. PROPOSED   PROCEDURE   FOR   INCORPORATING   REGULATION

CAPACITY  AND  REGULATION  MOVEMENT  INTO  GUARANTEE PAYMENT    CONSULTATION/MITIGATION    UNTIL    IMPROVED SOFTWARE IS DEPLOYED

While the requested Tariff waivers are in effect, the NYISO proposes to employ
an extended timeline to incorporate Regulation Capacity and Regulation Movement Bids
into  its  review  of  RTGP,  and  temporary,  alternative  screening  and  consultation
measures: (a) to permit the NYISO to manually screen real-time Regulation Capacity and
Regulation Movement Bids for the exercise of market power until the necessary software
upgrades are completed; and (b) to provide Market Parties adequate time and opportunity
to consult and explain the basis for conduct-failing real-time Regulation Capacity and/or
Regulation Movement Bids.

Because the NYISO implemented its new, two-part Regulation Market less than
one month ago (on June 26, 2013), many Market Parties have not developed a settled
offer strategy, and/or have yet not determined the most effective way to reflect and
recover each Generator’s cost of providing regulation service in that Generator’s
Regulation Capacity and Regulation Movement Bids.  In addition, there are a number of
Generators that did not choose to consult with the NYISO regarding their Generators’
Regulation   Capacity   and   Regulation   Movement   reference   levels   prior   to   the
implementation of the new market construct.  In these cases, the NYISO was forced to
use “place holder” reference levels that may not accurately represent a Generator’s cost
of providing regulation service.  As a result of these factors, the NYISO is seeing a large
number of Regulation Service Bids that appear to exceed the relevant conduct thresholds.

 

 

7


 

 

It is not unusual or surprising for a market to become unsettled when a significant
market change, like the addition of Regulation Movement to the regulation market,
occurs.  From June 26, 2013 to the date of this Waiver Request, total revenues paid to
regulation providers have not significantly increased in comparison to past periods, so it
appears unlikely that suppliers have significantly inflated their offers under the new
market design.  However, the NYISO’s Market Mitigation and Analysis Department
(“MMA”)  still needs to complete  the exercise of developing accurate Regulation
Capacity and Regulation Movement reference levels for all regulation providers.

The NYISO proposes to use the following process to address conduct-failing Regulation Conduct and Regulation Movement Bids submitted by entities that were scheduled to provide Regulation Service and that received a BPCG for the relevant RealTime Market day.

1. Informal consultation process.  Without waiting to perform an impact test,
MMA will send a letter informing the Market Party of (a) the conduct-failing
Bid, and (b) the reference level that the NYISO currently has in place for
Regulation Capacity and/or Regulation Movement and provide the Market
Party an opportunity to submit cost information justifying the bidding
behavior.  Cost information that a Market Party provides to justify its
Regulation Capacity or Regulation Movement Bid is likely to also be relevant
to developing an appropriate reference level for the Generator.

a. The NYISO will try to send the informal consultation/information
requests within two business days of posting to the NYISO’s Decision
Support System (“DSS”), but given the manual nature of the effort and
the  significant number of conduct-failing Bids, the  NYISO  may

 

8


 

 

require up to six business days to send the initial informal consultation letter.  The letter will require Market Parties to respond within 10 business days.

b. The NYISO will complete all informal consultations in a timeframe
that will permit the NYISO to perform a manual RTGP impact test and
apply RTGP mitigation, where appropriate, in the four-month true-up
invoice for the relevant market month.

c. NYISO expects that, in most cases, it will not be necessary to proceed
beyond the informal consultation process.

2. Manually perform RTGP impact test.  If the justification(s) provided by the

Market Party in the informal consultation process are determined to be
inadequate, or if no response is received, the NYISO will manually perform a
RTGP impact test that replaces all conduct-failing Bids, including conduct-
failing Regulation Capacity and/or Regulation Movement Bids, with reference
levels to determine if a RTGP impact that exceeds the impact threshold
specified  in  Section 23.3.2.1(2)  of  the  Mitigation  Measures  occurred.

Performing this test manually takes a significant amount of time because the
NYISO must manually identify and  calculate the impact on guarantee
payments of each of the 5-minute intervals of the day in which the Generator
being tested received a regulation schedule.  In addition to considering
conduct-failing regulation Bids, the NYISO must also account for any/all

 

 

 

 

 

 

 

9


 

 

other conduct-failing Bids.13  Due to the significant amount of time each RTGP impact test is expected to take, the NYISO proposes to offer the opportunity for the Market Party to participate in informal consultation before it performs a RTGP impact test.

3. Apply RTGP mitigation.  If RTGP impact is determined, the NYISO will

manually adjust the Market Party’s bill to reflect the change and send an e-
mail informing the Market Party of the mitigation and its impact on the Market Party’s guarantee payment, and inviting the Market Party to initiate a formal consultation regarding the mitigation.

a. NYISO will manually apply RTGP mitigation on or before the date of
the four-month true-up invoice for the relevant market month.
4. Formal consultation process.  Following the application of mitigation, the
NYISO proposes to follow all of the consultation rules and requirements set
forth in Section 23.3.3.3 of the Mitigation Measures.  The NYISO will treat
the date that the NYISO informed the Market Party of the RTGP mitigation
and its impact on the Market Party’s guarantee payment as the date on which
electronic settlement results are posted (see  Section 23.3.3.3.1.1 of the

Mitigation Measures).  The e-mail MMA sends informing the Market Party of
the mitigation and inviting the Market Party to participate in a formal
consultation will also  satisfy the notice obligation set forth in Section

23.3.3.3.1.2 of the Mitigation Measures.

 

 

13 For example, in addition to failing conduct for Regulation Capacity or Regulation Movement, the

Generator’s Minimum Generation Bid might also exceed the relevant conduct threshold.  All conduct-

failing Bids must be taken into consideration when calculating the guarantee payment impact of a Market Party’s bidding behavior for a Generator, for a market day.

 

 

10


 

 

5. End result.  RTGP mitigation may stand, or it may be wholly or partially
overturned, based on the results of the formal consultation process.

 

 

IV. THE REQUESTED WAIVER CONFORMS TO THE COMMISSION’S

APPLICABLE CRITERIA AND IS IN THE PUBLIC INTEREST

For the reasons explained in this Waiver Request, the NYISO requests waiver of
Sections 23.3.3.3.1.1 and 23.3.3.3.1.2 of its Mitigation Measures. “The Commission has

previously   granted   Independent   System   Operators   and   Regional   Transmission
Organizations limited waivers of their own tariff provisions when: (1) the underlying
error was made in good faith; (2) the waiver is of limited scope; (3) a concrete problem
needed to be remedied; and (4) the waiver did not have undesirable consequences, such
as harming third parties.”14  NYISO’s waiver request meets each of these criteria.

A.Good Faith

The NYISO acted in good faith to develop tariff rules and software to implement
its Order No. 755 compliance filing.  However, as described above, neither the NYISO
developers, nor its Market Monitoring Unit, understood that the supplemental, manual
review of Regulation Capacity Bids and Regulation Movement Bids for possible RTGP
mitigation remains subject to the same impact determination, posting and Market Party
notice deadlines that apply, more generally, to the application of RTGP mitigation.

 

 

 

 

14 New York Independent System Operator, Inc., 139 FERC ¶ 61,108, at P 14 (2012).  See also, e.g., PJM
Interconnection, LLC, 137 FERC ¶ 61,184, at P 13 (2011); PJM Interconnection, LLC, 137 FERC ¶
61,109, at P 11 (2011); PJM Interconnection, LLC, 135 FERC ¶ 61,069, at P 8 (2011); ISO-New England,
Inc., 134 FERC ¶ 61,182, at P 8 (2011); California Independent System Operator Corp., 132 FERC
¶ 61,004, at P 10 (2010); Hudson Transmission Partners, 131 FERC ¶ 61,157, at P 10 (2010); Pittsfield
Generating Co., L.P., 130 FERC ¶ 61,182, at P 9-10 (2010); ISO New England Inc. - EnerNOC, 122 FERC
¶ 61,297 (2008); Central Vermont Public Service Corp., 121 FERC ¶ 61,225 (2007); Waterbury
Generation LLC, 120 FERC ¶ 61,007 (2007); Acushnet Co., 122 FERC ¶ 61,045 (2008).

 

 

11


 

 

 

 

 

B.The Requested Temporary Waiver is Limited in Scope

The requested temporary waiver is limited in scope.  First, the waiver applies to
the finite period of June 26, 2013, which is the date the Tariff revisions that the

Commission accepted in response to the NYISO’s Order No. 755 compliance filing took
effect, through October 23, 2013, which is the anticipated date by which the NYISO will
have the software necessary to achieve Tariff compliance in-place.  Second, the waiver
only applies to entities that are selected to provide regulation, that submit conduct-failing
Regulation Capacity or Regulation Movement Bids, and that receive a BPCG for the
relevant Real-Time Market day.  RTGP mitigation continues to be timely applied to all
other Market Parties.

C. The Temporary Waiver Will Remedy a Concrete Problem

The requested temporary waiver will remedy a concrete problem.  Until the
NYISO is able to improve its RTGP software to incorporate Regulation Capacity and
Regulation Movement Bids and reference levels into the conduct and RTGP impact tests,
the NYISO will not be able to comply with the testing/notice deadlines set forth in
Sections 23.3.3.3.1.1 and 23.3.3.3.1.2 of its Mitigation Measures.  Granting the requested
waiver and permitting the NYISO to temporarily implement a manual process that
requires an impact determination, and that provides Generators a full opportunity to
engage in consultation, addresses the concerns presented by the NYISO’s application of
RTGP mitigation to Regulation Capacity and Regulation Movement providers Bids.

D. Granting the Temporary Waiver Will Not Harm Third Parties

Granting this Waiver Request will protect loads in New York that might
otherwise be required to pay BPCG compensation to Generators that are scheduled to
provide Regulation Capacity or Regulation Movement in the NYISO’s Real-Time

 

12


 

 

Market, and that submit Bids that significantly exceed their cost(s) of providing these services.  Affected Generators will not be harmed because the NYISO will provide both an  impact  determination  and  a  full  opportunity  for  consultation  regarding  their Regulation Capacity and Regulation Movement reference levels and the NYISO’s application of RTGP mitigation.  Therefore, the Commission’s granting of this Waiver Request will not harm third parties.

 

 

V. REQUEST FOR SHORTENED NOTICE PERIOD AND FOR

COMMISSION ACTION BY AUGUST 23, 2013

The NYISO respectfully requests that the Commission grant the requested,
temporary waiver request by no later than August 23, 2013.  To meet this expedited
schedule, the NYISO respectfully requests that the Commission immediately issue notice
of this Waiver Request and provide, in accordance with its Rule 210(b),15 for a shortened
comment period of ten days.  Expedited action is necessary because the NYISO is not
able to timely comply with the notice requirements in its Mitigation Measures when
applying RTGP mitigation to accepted Regulation Capacity and Regulation Movement
Bids.  Until the Commission acts, the NYISO will be out-of-compliance with the
requirements of its Tariffs.  Expedited Commission action on this Waiver Request will
also provide the NYISO and its Regulation Suppliers certainty regarding how guarantee
payment consultation and mitigation of Regulation Capacity Bids and Regulation
Movement Bids will be conducted during the requested waiver period.


 

 

 

 

 

 

 

 

 

 

15


 

 

 

 

 

18 C.F.R. § 385.210(b).

 

 

13


 

 

 

 

 

 

 

VI.CORRESPONDENCE AND COMMUNICATIONS

Please send all correspondence regarding this Waiver Request to the following NYISO representatives:

Belinda Thornton, Director of Market Mitigation and Analysis *Raymond Stalter, Director of Regulatory Affairs
Mollie Lampi, Assistant General Counsel

Leonard Ashley, Supervisor of Energy Market Mitigation *Alex M. Schnell

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144
bthornton@nyiso.com
rstalter@nyiso.com
mlampi@nyiso.com
lashley@nyiso.com
aschnell@nyiso.com
(518) 356-8707

* Persons designated for receipt of service.

 

 

VII.   SERVICE

This filing will be posted on the NYISO’s website at www.nyiso.com.  In
addition, the NYISO will e-mail an electronic link to this filing to the official representative of each party to this proceeding, to each of its customers, to each participant on its stakeholder committees, to the New York State Public Service Commission, and to the New Jersey Board of Public Utilities.

 

 

 

 

 

 

 

 

 

 

 

14


 

 

 

 

 

 

 

VIII.   CONCLUSION

For the reasons stated above, from June 26, 2013 through October 23, 2013, the
NYISO requests an expedited, temporary, waiver of the RTGP impact testing/mitigation
and notice requirements set forth in Sections 23.3.3.3.1.1 and 23.3.3.3.1.2 of its

Mitigation Measures.  The NYISO further requests that the Commission provide for a shortened comment period and act on this Waiver Request by August 23, 2013.

 

 

Respectfully submitted,

 

/s/ Alex M. Schnell

Mollie Lampi, Assistant General Counsel Alex M. Schnell

New York Independent System Operator, Inc.

 

 

Dated:  July 23, 2013

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

15


 

 

 

 

 

 

CERTIFICATE OF SERVICE

I hereby certify that I this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Rensselaer, New York this 23rd day of July 2013.

 

/s/ Joy A. Zimberlin

Joy A. Zimberlin

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144 518-356-6207

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

16