10 Krey Boulevard   Rensselaer, NY  12144

 

 

 

 

September 27, 2013

 

 

 

ELECTRONICALLY SUBMITTED

 

 

Kimberly D. Bose

Secretary

Federal Energy Regulatory Commission 888 First Street, N.E.

Washington, D.C. 20426

 

 

Re:     New York Independent System Operator, Inc.’s Sixth Informational Report on
Efforts to Develop Rules Addressing Compensation to Generators that Are
Determined to be Needed for Reliability; Docket No. ER10-2220-000.

 

 

Dear Secretary Bose:

 

In accordance with paragraph 54 and ordering paragraph “(C)” of the Federal Energy
Regulatory Commission’s (“Commission’s”) October 12, 2010, Order On Proposed Mitigation Measures in Docket No. ER10-2220-000 (“Order”),1 the New York Independent System
Operator, Inc. (“NYISO”), hereby submits this Sixth Informational Report on Efforts to Develop Rules Addressing Compensation to Generators that Are Determined to be Needed for Reliability (“September 2013 Informational Report”).  The NYISO submitted its Fifth Informational Report on Efforts to Develop Rules Addressing Compensation to Generators that Are Determined to be Needed for Reliability on April 1, 2013, (“April 2013 Informational Report”).  In footnote 44 of its Order the Commission stated that it does not intend to issue public notices, accept
comments, or issue orders on this Informational Report.

 

 

1New York Independent System Operator, Inc., 133 FERC ¶ 61,030.  Since issuance of this Order in

October 2010, the Commission has accepted tariff revisions to establish a New Capacity Zone comprised of Load Zones G, H, I and J, and a corresponding revision to the definition of “Rest of State.”  See New York Independent System Operator, Inc., 144 FERC ¶ 61,126, (Docket No. ER13-1380-00, accepting Services Tariff Sections 2.7, 2.18.)  Rest of State is presently defined as Load Zones A through I, and on January 27, 2014 it will be comprised of Load Zones A through F.


 

 

Kimberly D. Bose, Secretary September 27, 2013

Page 2

 

Paragraph 54 of the Order stated, in part, as follows:

Because fixed cost recovery issues do not go to whether NYISO’s mitigation
proposal is in itself just and reasonable, this proceeding is not the appropriate
forum in which to raise such issues.  Further, commenters do not present factual
evidence that demonstrates that market participants generally will be unable to
recover their costs due to application of the proposed mitigation provisions.  We
note, however, that the NYISO Board of Directors, in its July 29, 2010 decision
on the appeal of the NYISO Management Committee’s adoption of the instant
mitigation proposal, directed NYISO management to work with stakeholders to
examine the generation owners’ claims that existing cost recovery mechanisms
are inadequate and to review the process that evaluates permanent solutions to
reliability problems.  Accordingly, we believe the better course is to await the

outcome of the stakeholder process as directed by the NYISO Board of Directors. In this regard, we direct NYISO to file status reports every 180 days beginning 180 days from the date of this order for informational purposes only.44

 

44 The Commission does not intend to issue public notices, accept comments, or issue orders on such informational filings.

 

In compliance with the cited sections of the Order, the NYISO submits this Informational

Report.

 

I. Informational Report

A. Summary of the April 2013 Informational Report

 

The NYISO did not present new or updated proposals to its stakeholders between the
October 2012 Informational Report and the April 2013 Informational Report.  Also during this
time, the NYISO did not receive any new or updated proposals from its stakeholders or New
York State Department of Public Service (“DPS”) staff.  Between October 2012 and April 2013,
the NYISO continued to actively monitor and assess whether additional rules addressing
compensation to generators needed for reliability, such as the Alternative RRC proposal
discussed in the October 2012 Informational Report, are necessary to improve the NYISO
administered markets.

 

B.September 2013 Informational Report

The NYISO has not presented new or updated proposals to its stakeholders since filing the April 2013 Informational Report.  In addition, the NYISO has not received any new or
updated proposals from its stakeholders or DPS staff.  The NYISO continues to actively monitor and assess whether additional rules addressing compensation to generators needed for reliability, such as the Alternative RRC proposal discussed in the October 2012 Informational Report, are necessary to improve the NYISO administered markets.


 

 

Kimberly D. Bose, Secretary September 27, 2013

Page 3

 

 

C.Additional Market Activity Update

The April 2013 Informational Report included information on a matter that involved

certain New York Control Area resources seeking to retire.  The New York State Public Service
Commission (“NYPSC”) issued an order that approved a mechanism for a transmission owner to
compensate specific generating units that were seeking to retire but were determined to be
necessary to address a reliability need.2  The subject of the order was a proposal for the
transmission owner (Niagara Mohawk Power Corp. d/b/a/ National Grid) to compensate the
generator owner (Dunkirk Power LLC, “Dunkirk”) for “reliability support services” (“RSS”)
provided by two of the four generating units at the Dunkirk facility.  National Grid filed its
contract with Dunkirk for RSS with the PSC for approval and cost recovery.  National Grid then
issued a Request for Proposal (“RFP”) for solutions to address the continuing reliability needs
beyond May 31, 2013.  The Dunkirk unit provided the least cost solution and the only solution
available to operate starting on June 1, 2013.  National Grid filed a request with the PSC to
extend the RSS agreement for one of the Dunkirk units on March 5, 2013.  The agreement
provides for the deferral of mothballing one 115 kV-connected 80 MW Dunkirk generating unit.
The deferral would allow the continued operation and maintenance of the one Dunkirk unit from
June 1, 2013 through May 31, 2015 for a fixed total price of approximately $72.741 million.

 

Since the April 2013 Informational Report, National Grid filed proposed tariff revisions
to certain National Grid-specific components of the Wholesale Transmission Service Charge
formula under Attachment H of the NYISO Open Access Transmission Tariff.3  National Grid’s
filing requested amendments to its Scheduling, System Control and Dispatch Costs formula to
incorporate costs incurred for RSS, which secure the reliability of the company’s transmission
system.  National Grid stated that its filing was necessitated by costs incurred during calendar
year 2012 under the first of two RSS contracts.  This RSS contract, as approved by the NYPSC,
deferred the mothballing of the Dunkirk generating station and allowed for continued operation
pending the completion of upgrades to National Grid’s transmission system.  The Commission
rejected National Grid’s proposed tariff revisions without prejudice, therefore allowing National
Grid to submit another filing.

Also since April 2013, the Independent Power Producers of New York, Inc. (“IPPNY”)
filed a complaint with the Commission4 alleging the artificial suppression of prices in the New
York Control Area (“NYCA”) installed capacity (“ICAP”) market from below-cost offers of
capacity from resources that would have exited the market but for out-of-market revenues under

 

2 NYPSC Case No. 12-E-0136, Order Deciding Reliability Issues and Addressing Cost Allocation and Recovery (issued August 16, 2012).  Order may be retrieved from

<http://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId={34D25567-D7B7-41EA-
822F-6585B344BC0E}>

3 See Federal Energy Regulatory Commission Docket No. ER13-1182.

4 See Federal Energy Regulatory Commission Docket No. EL13-62.


 

 

Kimberly D. Bose, Secretary September 27, 2013

Page 4

 

reliability must-run (“RMR”) contracts and similar mechanisms and requesting that the

Commission order the NYISO to revise its Market Administration and Control Area Services
Tariff (“Services Tariff”).  IPPNY’s complaint also specifically referenced Reliability Support
Services Agreements (“RSSAs”) like those approved by the NYPSC, and discussed in the
NYISO’s April 2013 Information Report, as causes of price suppression resulting from facilities
that would have otherwise been mothballed.  The NYISO and several other parties have filed
protests and comments on that filing.  This proceeding remains pending before the Commission.

 

D.Next Steps

The NYISO will continue to assess whether enhancements to the prior proposals or

additional alternate approaches are necessary to address compensation to generators needed for
reliability and to improve the NYISO administered markets.  The NYISO does not have any
presentations scheduled at this time.  The NYISO will continue to discuss this topic with its
stakeholders.

II. Service

The NYISO will send an electronic link to this Informational Report to the official

representative of each of its customers, to each participant on its stakeholder committees, to the
New York Public Service Commission, to all parties listed on the Commission’s official service
list in this Docket and to the New Jersey Board of Public Utilities.  In addition, the complete
filing will be posted on the NYISO’s website at www.nyiso.com.

 

III. Conclusion

The NYISO respectfully submits this Informational Report in compliance with the

Commission’s Order.  For the reasons explained above, the NYISO is continuing to monitor and assess whether additional rules addressing compensation to generators needed for reliability are necessary to improve the NYISO administered markets.  The NYISO’s next informational report is due on March 27, 2014.

Respectfully submitted,

 

/s/ James H. Sweeney

Rana Mukerji, Senior Vice President of Market Structures Robert E. Fernandez, General Counsel

James H. Sweeney, Attorney

New York Independent System Operator, Inc.