UNITED STATES OF AMERICA
BEFORE THE

FEDERAL ENERGY REGULATORY COMMISSION

 

)

New York Independent System Operator, Inc.)Docket No. ER11-4338-001

)

 

REQUEST FOR LEAVE TO ANSWER AND ANSWER OF THE
NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.

Pursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal

Energy Regulatory Commission (“Commission”),1 the New York Independent System Operator,
Inc. (“NYISO”) respectfully submits this motion for leave to answer, and answers, the request
for rehearing filed in the above-captioned proceeding on June 17, 2013, by EnerNOC, Inc.,
Viridity, Inc., Wal-Mart Stores, Inc., Comverge, Inc., the American Forest and Paper
Association, and EnergyConnect, a Johnson Controls Company (collectively, the “Demand
Response Supporters”).2  The Demand Response Supporters request rehearing of the
Commission’s determination regarding behind-the-meter generation in its May 16, 2013, order
addressing the NYISO’s compliance with Order No. 7453 (“May 16 Order”).4  Specifically, the
Demand Response Supporters allege that the May 16 Order erred by not finding that Order
No. 745 requires the NYISO to allow behind-the-meter generation to participate as Demand Side

 

 

 

1 18 C.F.R. §§ 385.212, 213.

2 New York Independent System Operator, Inc., Request for Rehearing of Demand Response
Supporters, Docket No. ER11-4338-001 (June 17, 2013) (“Demand Response Supporters Request”).

3 Demand Response Compensation in Organized Wholesale Energy Markets, Order No. 745,
134 FERC ¶ 61,187 (March 15, 2011) (“Order No. 745”); reh’g denied, Order No. 745-A, 137 FERC
¶ 61,215 (Dec. 15, 2011) (“Order No 745-A”); reh’g denied, Order No. 745-B, 138 FERC ¶ 61,148
(2012).

4 New York Independent System Operator, Inc. Order on Compliance Filing, 143 FERC ¶ 61,134 (2013) (“May 16 Order”).


 

 

Resources5 in the NYISO’s Day-Ahead Demand Response Program (“DADRP”) and receive the
Locational Based Marginal Price (“LBMP”)6 for the demand reduction that it facilitates.7
The Commission should deny the Demand Response Supporters’ request for rehearing. The May 16 Order’s determination regarding behind-the-meter generation is consistent with Order No. 745.  The Commission has been clear that Order No. 745 does not require
Independent System Operators (“ISOs”) and Regional Transmission Organizations (“RTOs”) to
make any changes to the eligibility of behind-the-meter generation for demand response
compensation.  It has been equally clear that to the extent that ISOs/RTOs and their stakeholders
desire to make such changes they should do so through a separate proceeding.8  The NYISO is
already exploring with its stakeholders the development of new market rules that would
incorporate behind-the-meter generation into a revised NYISO economic demand response
program.  Granting rehearing would needlessly preempt this stakeholder process.

I.REQUEST FOR LEAVE TO ANSWER

The NYISO recognizes that the Commission generally discourages answers to requests
for rehearing.9  Nonetheless, the Commission has the discretion to accept answers to rehearing

 

 

5 Capitalized terms not otherwise defined herein shall have the meaning specified in the NYISO’s Market Administration and Control Area Services Tariff.

6 For purposes of this proceeding, LBMP and locational marginal price (“LMP”) are comparable and are referred to interchangeably.

7 See Demand Response Supporters Request at p 3.

8 Demand Response Supporters, consisting of substantially the same parties that submitted the
Demand Response Supporters Request, filed a complaint under Section 206 of the Federal Power Act on
June 17, 2013, in FERC Docket No. EL13-74 requesting that the Commission require the NYISO to
revise its tariffs to allow demand response facilitated by behind-the-meter generation to be compensated
at full LMP.  The NYISO will address Demand Response Supporters’ allegations in its answer to the
complaint.

9 See 18 C.F.R. § 385.213(a)(2).

 

 

2


 

 

requests and has done so when those answers help to clarify complex issues, provide additional information, or are otherwise helpful in the development of the record or assist in its decision making process.10  The NYISO’s answer satisfies these standards and should be accepted
because it addresses inaccurate or incomplete statements and provides additional information that the Commission needs to fully evaluate the arguments in this proceeding.

II.BACKGROUND

The May 16 Order denied requests by the Demand Response Supporters11 and Joint

Commenters12 to find that the NYISO is required under Order No. 745 to allow behind-the-meter generation to participate as a Demand Side Resource in the DADRP and receive LBMP for the demand reduction that it facilitates.13  The Commission determined that such a finding was
outside of the scope of Order No. 745.  Specifically, the Commission stated:

In Order No. 745, the Commission did not require an RTO or ISO to differentiate
between demand response resources for which demand response is facilitated by
behind-the-meter generation and other demand response resources.  Order
No. 745 also did not prohibit such differentiation.  If NYISO or its stakeholders
determine that changes are warranted with respect to NYISO's existing practices
in this area, such changes should be presented to the Commission in a separate
proceeding.14

 

10 See, e.g., Black Oak Energy, L.L.C. v. PJM Interconnection, L.L.C., 125 FERC ¶ 61,042 at P 14 (2008) (accepting answer to rehearing request because the Commission determined that it has “assisted us in our decision-making process.”); FPL Marcus Hook, L.P. v. PJM Interconnection, L.L.C., 123 FERC ¶ 61,289 at P 12 (2008) (accepting “PJM’s and FPL’s answers [to rehearing requests], because they have provided information that assisted us in our decision-making process”).

11 Demand Response Supporters consisted of: Demand Response Partners, Energy Curtailment Specialists, Inc., Energy Spectrum, Inc., EnerNOC, Inc., Viridity, Inc., Wal-Mart Stores, Inc., Comverge, Inc., and EnergyConnect, a Johnson Controls Company.

12 Joint Commenters consisted of: the American Council for an Energy Efficient Economy,

American Forest & Paper Association, Industrial Energy Consumers of America, and U.S. Clean Heat & Power Association.

13 May 16 Order at P 101.

14 Id.

 

 

3


 

 

 

In their request for rehearing, Demand Response Supporters argue that the Commission erred in this determination and request that the Commission grant rehearing on this matter and impose certain revisions to the NYISO’s tariffs to allow behind-the-meter generation to participate as a Demand Side Resource in the DADRP and receive LBMP compensation for the demand
reduction that it facilitates.

III.ANSWER

The Commission should deny Demand Response Supporters’ request.  The May 16

Order’s determination regarding behind-the-meter generation is consistent with Order No. 745.
The Commission has been clear that ISOs/RTOs are not required under Order No. 745 to make
changes to the eligibility of behind-the-meter generation for demand response compensation.
The Commission has stated that Order No. 745 “focused exclusively on the amount of payment
demand response would receive and did not require any changes with respect to whether load
relying on behind-the-meter generation would be entitled to demand response compensation.”15
For this reason, the Commission has rejected, as outside the scope of Order No. 745, changes to
the eligibility of behind-the-meter generation for demand response compensation.16  The

NYISO’s DADRP does not provide for the participation of behind-the-meter generation and does
not provide demand response compensation to such resources.  Consistent with the
Commission’s clear statements regarding the scope of Order No. 745, the NYISO was not

 

15 Midwest Independent Transmission System Operator, Inc., Order on Rehearing and Compliance, 140 FERC ¶ 61,059 (2012) at P 29.

16 See, e.g., Midwest Independent Transmission System Operator, Inc., Order on Compliance

Filing, 137 FERC ¶ 61,212 (2011) at P 71, on reh’g, Order on Rehearing and Compliance, 140 FERC

¶ 61,059 (2012) at P 29 (rejecting a change in behind-the-meter generation’s eligibility to receive demand response compensation as outside the scope of Order No. 745); PJM Interconnection, L.L.C., Order on
Compliance Filing, 137 FERC ¶ 61,216 (2011) at P 94 (rejecting protesters’ arguments for the elimination of demand response compensation to demand response customers with behind-the-meter generation as not required under Order No. 745).

 

 

4


 

 

required to include in its compliance filing revisions to its DADRP to allow behind-the-meter
generation to participate in the program and receive LBMP for the demand reduction that it
facilitates.

Demand Response Supporters’ claims that the May 16 Order is somehow inconsistent with unrelated Commission orders17 or with Order No. 745 compliance approaches that were chosen by ISOs/RTOs facing factual circumstances different than the NYISO’s18 are irrelevant. Demand Response Supporters’ objection to the fact that Order No. 745 did not require
ISOs/RTOs to change eligibility rules applicable to behind-the-meter generation is an untimely collateral attack on Order No. 745.19

The Commission has indicated that any such changes to the eligibility requirements

should be presented to the Commission in a separate proceeding.20  As the Commission stated in
its May 16 Order, “[i]f NYISO or its stakeholders determine that changes are warranted with
respect to NYISO's existing practices in this area, such changes should be presented to the
Commission in a separate proceeding.”21  A robust stakeholder process is necessary to determine
to what further extent behind-the-meter generation may participate in the NYISO demand

 

 

17 See Demand Response Supporters Request at pp 11-12.

18 See id. at pp 8-10.

19 See, e.g., San Diego Gas & Electric Co. v. Sellers of Energy and Ancillary Services, et al.,

134 FERC ¶ 61,229 at P 15 (2011) (“[collateral attacks on final orders and relitigation of applicable

precedent by parties that were active in the earlier cases thwart the finality and repose that are essential to administrative efficiency and are strongly discouraged.”) (citing Entergy Nuclear Operations, Inc. v.
Consolidated Edison Co., 112 FERC ¶ 61,117, at P 12 (2005)); see also EPIC Merchant Energy NJ/PA, LP v. PJM Interconnection, LLC, 131 FERC ¶ 61,130 (2010) (dismissing as an impermissible collateral attack a complaint that merely sought to re-litigate the same issues that were raised in the prior case citing no new evidence or changed circumstances).

20 May 16 Order at P 101.

21 Id.

 

 

5


 

 

 

 

 

response programs.22  The eligibility and size requirements for behind-the-meter generation,

measurement and verification protocols, and related issues such as addressing air emissions,

energy injections and double counting are complex and require further evaluation and discussion.
The NYISO is already in the process of exploring with its stakeholders new market rules that would, among other things, incorporate behind-the-meter generation into a revised economic demand response program that will facilitate demand response resources directly participating in both the day-ahead and real-time energy markets.23  As part of this process, the NYISO began work in June 2013 on a study on distributed energy resources to determine their current

penetration, anticipated development, meter configuration, and other information that will inform
the development of requirements for the participation of behind-the-meter generation in a revised
economic demand response program.  The NYISO has informed stakeholders of this study and is
currently planning a workshop involving the consultant performing the study and stakeholders to
identify issues regarding behind-the-meter generation that should be addressed in the study’s
scope.

The Commission should not preempt this process and act inconsistently with Order

No. 745 by requiring the NYISO to include behind-the-meter generation in the DADRP.  Such

 

 

22 Behind-the-meter generation is eligible to participate in the NYISO’s reliability demand response programs.

23 In 2012 the NYISO proposed and brought through its governance process its conceptual design
for a dispatchable demand response program.  This concept will ultimately supplant the NYISO’s
DADRP program and will allow all demand response resources that qualify to bid directly into the day-
ahead and real-time energy markets.  The NYISO anticipates engaging in a discussion with stakeholders
regarding the market rules for this dispatchable demand response program during this second half of
2013.  The NYISO expects that these discussions will explore market rule changes that will enable
behind-the-meter generation to participate in this program.  See NYISO’s December 5, 2012, Business
Issues Committee presentation entitled “Market Design Concepts for Demand Response in the Real-Time
Energy Market,” available at:

http://www.nyiso.com/public/webdocs/markets_operations/committees/bic/meeting_materials/2012-12-
05/agenda_08_Demand_Response_in_the_Real-Time_Energy_Market-for_12-5-12_BIC.pdf.

 

 

6


 

 

action cannot simply be accomplished by adopting new tariff language, such as the language
proposed by Demand Response Supporters, but would, instead, require a careful evaluation of
market and reliability impacts, measurement and verification processes, the input of NYISO
stakeholders, and the development and implementation of revised market rules.  The NYISO
should be permitted to continue to work with its stakeholders to address these issues as it
develops the market rules for a revised NYISO economic demand response program.

III.CONCLUSION

WHEREFORE, for the foregoing reasons, the NYISO respectfully requests that the Commission grant its motion for leave to answer, accept this answer, and deny Demand Response Supporters’ request for rehearing.

 

Respectfully submitted,

 

/s/ Michael J. Messonnier, Jr.

Michael J. Messonnier, Jr. Counsel for the

New York Independent System Operator, Inc.

 

 

July 2, 2013

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

7


 

 

 

 

 

CERTIFICATE OF SERVICE

I hereby certify that I have this day caused the foregoing document to be served upon each person designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Commission Rules of Practice and Procedure, 18 C.F.R. § 385.2010 (2013).

Dated at Washington, D.C. this 2nd day of July 2013.

 

/s/  Catherine Karimi

Catherine Karimi

Sr. Professional Assistant

Hunton & Williams LLP

2200 Pennsylvania Ave, NW
Washington, DC  20037
Tel: (202) 955-1500
Fax: (202) 778-2201

E-mail: ckarimi@hunton.com