Amanda C. Downey
Counsel

 

 

February 6, 2013

 

 

The Honorable Kimberly D. Bose Secretary

Federal Energy Regulatory Commission 888 First Street, NE

Washington, DC  20426

 

Re:Niagara Mohawk Power Corporation, d/b/a National Grid

Docket No. ER13-___-000

Filing of Cost Reimbursement Agreement with Erie Boulevard Hydropower, L.P. and

Request for Waiver of Commission Notice Requirement

 

Dear Secretary Bose:

Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and Part 35 of the
Federal Energy Regulatory Commission’s (“Commission”) regulations,2 Niagara
Mohawk Power Corporation d/b/a/ National Grid (“National Grid”) submits a Cost
Reimbursement Agreement (“Reimbursement Agreement”) between National Grid and
Erie Boulevard Hydropower, L.P. (“Erie”).  The Reimbursement Agreement is
designated as Service Agreement No. 1953 under the New York Independent System
Operator, Inc.’s (“NYISO”) Open Access Transmission Tariff (“OATT”).

The Reimbursement Agreement is an undisputed agreement between National Grid and Erie that will expedite the interconnection process for the expansion of an
existing generation plant owned by Erie.  National Grid respectfully requests that the Commission grant waiver of its prior notice requirement to permit the Reimbursement Agreement to go into effect as of November 9, 2012, the effective date set forth in the Reimbursement Agreement.

 

I.Background

National Grid is a public utility with a transmission system in the State of New

York.  Erie owns the Stewarts Bridge Hydropower Generation Plant (“Plant”) located

near the Town of Hadley in Saratoga County, New York.  The Plant is interconnected to


 

 

 

 

 

 

 

 

1

 

 

2


 

 

 

 

16 U.S.C. § 824d.

 

18 C.F.R. Part 35.


 

 

The Honorable Kimberly D. Bose February 6, 2013

Page 2

 

 

the National Grid system pursuant to the terms of an interconnection agreement filed with and accepted by the Commission in 2010.3

Erie is expanding the Plant by 3 MW, from its existing capacity of 37.5 MW, to
a planned capacity of 40.5 MW.  The expansion is being processed under the NYISO’s
generator interconnection procedures in accordance with Attachment X to the NYISO
OATT.  A draft facilities study report for the expansion was issued on November 6,
2012 and is attached as Schedule E to the Reimbursement Agreement.  Erie has
requested that National Grid perform certain design, engineering, procurement,
construction, and testing work to expedite the interconnection process associated with
the expansion of the Plant.4

As stated in the recitals of the Reimbursement Agreement, the parties anticipate the negotiation of a new interconnection agreement in connection for the expanded Plant after the NYISO’s Class Year process.

Under Section 30.9 of Attachment X to the NYISO OATT, prior to finalization of an interconnection agreement, “a Developer may, in order to advance the
implementation of its interconnection, request and Connecting Transmission Owner shall offer the Developer, an [Engineering and Procurement] Agreement that authorizes the Connecting Transmission Owner to begin engineering and procurement of long leadtime items necessary for the establishment of the interconnection.”

 

II. Description of the Reimbursement Agreement and Filing Requirements

Pursuant to the Reimbursement Agreement, Erie will reimburse National Grid
for the actual costs and expenses incurred in connection with work performed by
National Grid to expedite the interconnection process for the expanded Plant.  The
Reimbursement Agreement sets forth the terms and conditions of this work and certain
related commitments by Erie.  The Reimbursement Agreement includes provisions
addressing performance and schedule of the work, indemnification and liability,
insurance, and various standard provisions for utility cost reimbursement agreements.

The parties have agreed to a provision in the Reimbursement Agreement which
will affect the implementation of the interconnection agreement for the Plant once it is
finalized.  Under Article 2 of the Reimbursement Agreement, National Grid will have
no further obligation to perform work under the Reimbursement Agreement upon the
date the Commission accepts the new interconnection agreement.  Under Article 7.5 of
the Reimbursement Agreement, any remaining balance of prepayments made to


 

 

3


See Niagara Mohawk Power Corp., Docket No. ER10-690-000 (Mar. 25, 2010) (unpublished


letter order).


 

 

4


Reimbursement Agreement, Article 3.0 and Schedule A.


 

 

The Honorable Kimberly D. Bose February 6, 2013

Page 3

 

 

National Grid by Erie under the Reimbursement Agreement will be applied to invoices
charged to Erie under the new interconnection agreement.  Article 7.5 also provides that
National Grid will adjust the security to be provided under the new interconnection
agreement to reflect such prepayments.  This provision is intended to facilitate the
transition from the Reimbursement Agreement to the new interconnection agreement.

Consistent with Section 30.9 of Attachment X, National Grid is performing the
services under the Reimbursement Agreement at actual cost as set forth in Article 1 to
the Agreement and has not collected any funds pursuant to the Reimbursement
Agreement prior to the instant filing.5  The Commission should find the price of the
services to be performed pursuant to the Reimbursement Agreement to be just and
reasonable because National Grid will perform these services at actual cost.

 

III. Effective Date and Request for Waiver

Pursuant to Section 35.11 of the Commission’s regulations,6 National Grid

respectfully requests waiver of the requirement contained in Section 35.3 of the

Commission’s regulations to file service agreements not more than 30 days after service has commenced,7 to allow the Reimbursement Agreement to become effective upon the effective date set forth in the agreement, i.e., November 9, 2012.

 

Granting waiver will not result in prejudice to any party.  National Grid and Erie have agreed to project milestones that anticipate completion of work pursuant to the Reimbursement Agreement by February 2013.8  Granting the requested waiver will
benefit a customer seeking to modify its facilities interconnected to the transmission system and is therefore consistent with the standard set forth by the Commission in
Central Hudson.9  For these reasons, the Commission should find that good cause exists to grant an effective date of November 9, 2012.


 

 

 

 

 

 

 

5


 

 

 

 

See definition of “Company Reimbursable Costs.”  See also Section 11.1, stating “The Company


is not in the business of performing design or construction services for profit and is not receiving any fee


or profit (as contrasted with cost reimbursement) for its performance of the work hereunder.”


 

 

6

 

 

7

 

 

8

 

 

9


18 C.F.R. § 35.11.

 

18 C.F.R. § 35.3.

See Schedule B to the Reimbursement Agreement.
See Central Hudson Gas & Electric Corp., 60 FERC ¶ 61,106, at 61,338, reh’g denied, 61


FERC ¶ 61,089 (1992).


 

 

The Honorable Kimberly D. Bose February 6, 2013

Page 4

 

 

IV.Communications and Service

Communications regarding this filing should be addressed to the following

individuals, whose names should be entered on the official service list maintained by

the Secretary for this proceeding:10


 

Amanda C. Downey Counsel

National Grid USA
Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451 Tel: 781-907-2136

amanda.downey@nationalgrid.com

 

 

William L. Malee

Director, Transmission Commercial National Grid USA

40 Sylvan Road

Waltham, MA 02451 (781) 907-2422

bill.malee@nationalgrid.com


Sean A. Atkins

Bradley R. Miliauskas Alston & Bird LLP The Atlantic Building 950 F Street, NW

Washington, DC  20004 Tel:  202-239-3300

Fax:  202-239-3333

sean.atkins@alston.com
bradley.miliauskas@alston.com


 

Copies of this filing have been served on Erie, the NYISO, and the New York State Public Service Commission.


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

National Grid requests waiver of 18 C.F.R. § 385.203(b) to allow four persons to be added to the


service list in this proceeding.


 

 

The Honorable Kimberly D. Bose February 6, 2013

Page 5

 

 

V.Conclusion

For the reasons stated herein, National Grid respectfully requests that the

Commission accept the Reimbursement Agreement effective as of November 9, 2012.

 

Respectfully submitted,

 

/s/ Amanda C. Downey

Amanda C. Downey
Counsel

National Grid USA

Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451

Attorney for Niagara Mohawk Power
Corporation d/b/a National Grid