Amanda C. Downey
Counsel
June 14, 2013
The Honorable Kimberly D. Bose Secretary
Federal Energy Regulatory Commission 888 First Street, N.E.
Washington, DC 20426
Re: Niagara Mohawk Power Corporation d/b/a National Grid
Docket No. ER13-______-000
Service Agreement No. 2006 Under the NYISO OATT Small Generator Interconnection Agreement with Synergy Biogas LLC
Dear Secretary Bose:
Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and Part 35 of the
regulations of the Federal Energy Regulatory Commission (“Commission”),2 Niagara
Mohawk Power Corporation d/b/a National Grid (“Niagara Mohawk”), submits for filing a Small Generator Interconnection Agreement (the “Agreement”) between Niagara Mohawk and Synergy Biogas LLC (“Synergy”), designated as Service Agreement No. 2006 under the New York Independent System Operator, Inc.’s (“NYISO”) Open Access Transmission Tariff (“OATT”).3 Niagara Mohawk requests that the Commission accept the Agreement effective 61 days after the date of this filing, i.e., August 14, 2013.
I.Background
Niagara Mohawk, a subsidiary of National Grid, is a public utility subject to the Commission’s jurisdiction which owns transmission facilities located in New York. Niagara Mohawk’s New York transmission facilities have been placed under the
operational control of the NYISO.
1
2
3
16 U.S.C. § 824d.
18 C.F.R. Part 35.
The Agreement is captioned as a Small Generator Interconnection Agreement (“SGIA”) because its
terms and conditions are based upon the terms and conditions of the Commission-approved pro forma SGIA
that was set forth in Appendix 9 of Attachment Z to the NYISO OATT at the time the Agreement was
finalized. Niagara Mohawk uses this “modified SGIA” to document the interconnection of generators when
Commission jurisdiction does not attach or the NYISO is not required to be a party to the interconnection
agreement. Differences between the pro forma SGIA and the “modified SGIA” include the fact that the
former is a three-party agreement including NYISO, while the latter is written to be bilateral between Niagara
Mohawk and the generator.
40 Sylvan Road, Waltham, MA 02451
T: 781-907-2136 F: 781-907-5701 amanda.downey@nationalgrid.com www.nationalgrid.com
The Honorable Kimberly D. Bose June 14, 2013
Page 2
Synergy owns a farm waste-fueled generating plant located in Wyoming County, New York with a nameplate capacity of approximately 1.4 MW (the “Plant”). On July 2, 2010, Synergy self-certified the Plant as a Qualifying Facility (“QF”).4 The Plant began commercial operation on December 30, 2011.
The Agreement was entered into on August 30, 2010 and amended on December 15, 2011.5 The Agreement provides for the construction and operation of facilities
interconnecting the Plant with Niagara Mohawk’s 13.2 kV distribution facilities, as well as terms governing metering, cost responsibility, etc.
On December 29, 2011, Niagara Mohawk and Synergy entered into a power
purchase agreement (“PPA”) pursuant to which Synergy agreed to sell and deliver, and
Niagara Mohawk agreed to purchase and accept, all of the excess electric output produced by the Plant that was not used by Synergy.6 On August 20, 2012, Synergy sent Niagara Mohawk a notice stating that Synergy elected to terminate the PPA effective September 1, 2012.7 Thereafter, Synergy could begin selling the output of the Plant to entities other than Niagara Mohawk at wholesale in interstate commerce.
II.Filing Obligation
Section 205 of the FPA authorizes the Commission to require utilities to file all rates
and charges that are “for or in connection with,” and all agreements that “affect or relate
to,” jurisdictional transmission or sales of electric energy.8 The Commission has provided
guidance regarding some of the specific agreements that must be filed under this authority.
The Commission has found that “[i]nterconnection agreements between utilities come
within section 205 of the FPA.”9 The Commission has also explained that its jurisdiction
over an agreement “is limited to the provisions of the agreement that facilitate the exchange
of energy between the parties, i.e., the sale of electric energy at wholesale in interstate
commerce.”10 As the activities covered by the provisions of the Agreement described
above all relate to activities needed to facilitate the delivery of the Plant’s energy to the grid
for sales at wholesale in interstate commerce, Niagara Mohawk believes that these
provisions likely bring the Agreement within the Commission’s jurisdiction and make it
subject to the Commission’s filing requirements.
4
5
Synergy Biogas, LLC, Notice of Self-Certification, Docket No. QF10-590-000 (July 28, 2010).
The Agreement and the amendment thereto are provided in Attachments A and B, respectively, to
this filing. A copy of the Agreement incorporating the amendment is provided in Attachment C.
6
7
8
9
The PPA is provided in Attachment D to this filing.
The notice of termination of the PPA is provided in Attachment E to this filing.
16 U.S.C. §§ 824d(a), -(c).
Prior Notice and Filing Requirements Under Section II of the Federal Power Act, 64 FERC ¶
61,139, at 61,991 (1993).
10
PSI Energy, Inc., 56 FERC ¶ 61,237, at 61,908 n.4 (1991).
The Honorable Kimberly D. Bose June 14, 2013
Page 3
Specifically, Niagara Mohawk believes that the Agreement became Commission-
jurisdictional on August 20, 2012, when Niagara Mohawk received notification that Synergy
elected to terminate the PPA and thereby be able to begin making sales to a third party
buyer. Pursuant to Commission policy, “[w]hen an electric utility . . . purchases the QF’s
total output, the state has authority over the interconnection and the allocation of
interconnection costs. But when an electric utility interconnecting with a QF does not
purchase all of the QF’s output and instead transmits the QF’s power in interstate commerce,
the Commission exercises jurisdiction over the rates, terms, and conditions affecting or
related to such service, such as interconnections.”11 Further, where the interconnected utility
is on notice that a QF plans to make wholesale sales of its output to a third party, either by
way of contractual provisions or otherwise, the Commission has exclusive jurisdiction over
the interconnection between the QF and the interconnected utility from the date the utility
receives this notice, even where the QF has not engaged in third party sales or where the
interconnected utility is still purchasing the full output of the QF.12 On August 20, 2012,
Niagara Mohawk was put on notice that Synergy elected to terminate the PPA effective
September 1, 2012, and therefore Niagara Mohawk was also put on notice that Synergy
could begin making sales to third party buyers in the future. Therefore, Commission
jurisdiction attached to the Agreement as of August 20, 2012.
III. The Charges Authorized Under the Agreement Are Just and Reasonable
The Agreement states that Niagara Mohawk will bill Synergy for the design,
engineering, construction, and procurement costs of interconnection facilities and upgrades
contemplated by the Agreement.13 The Agreement also states that Synergy is responsible
for its share of all reasonable expenses, including overheads, associated with operating,
maintaining, repairing, and replacing the Niagara Mohawk interconnection facilities
defined in the Agreement.14 Since the Agreement became subject to the Commission’s
jurisdiction, Niagara Mohawk has collected no charges from Synergy for operating,
maintaining, repairing, and replacing Niagara Mohawk interconnection facilities.15
11
Standardization of Small Generator Interconnection Agreement and Procedures, Order No. 2006,
FERC Stats. & Regs. ¶ 31,180, at P 516 (citation omitted) (2005) (“Order No. 2006”).
12
In Order No. 2006, the Commission explained that:
This Final Rule applies when the owner of the QF seeks interconnection with a facility subject to the OATT to sell any of the output of the QF to a third party. This applies to a new QF that plans to sell any of its output to a third party and to an existing QF
interconnected with an electric utility or on-site customer that decides in the future to sell any of its output to a third party.
Id. at P 517. See also Florida Power & Light Co., 133 FERC ¶ 61,121, at P 22 (2010).
13
14
15
Agreement, Article 6.1.1.
Agreement, Article 4.1.2.
Niagara Mohawk has invoiced Synergy for its actual costs in providing interconnection service to
Synergy but has received no payment since the Agreement became subject to the Commission’s jurisdiction on August 20, 2012. Niagara will refund the interest, at the FERC rate (see 18 C.F.R. § 35.19a), on any
charges which are collected after the date the Agreement became subject to the Commission’s jurisdiction and prior to the Commission’s approval of the Agreement.
The Honorable Kimberly D. Bose June 14, 2013
Page 4
IV.Effective Date
Niagara Mohawk requests that the Commission accept the Agreement effective 61 days after the date of this filing, i.e., August 14, 2013.
V.Attachments
In addition to this transmittal letter, this filing includes the following attachments:
Attachment AAgreement between Niagara Mohawk and Synergy dated
August 30, 2010
Attachment BAmendment to the Agreement dated December 15, 2011
Attachment CAgreement with the Amendment incorporated therein
(Service Agreement No. 2006)
Attachment DPPA between Niagara Mohawk and Synergy dated December
29, 2011
Attachment ESynergy notice of termination of PPA dated August 20, 2012
VI.Communications
Communications and correspondence regarding this filing should be addressed to
the following individuals:
Amanda C. Downey Counsel
National Grid USA
Service Company, Inc.
40 Sylvan Road
Waltham, MA 02451 (781) 907-2136
amanda.downey@nationalgrid.com
William L. Malee
Director, Transmission Commercial National Grid USA
40 Sylvan Road
Waltham, MA 02451 (781) 907-2422
bill.malee@nationalgrid.com
Sean A. Atkins
Bradley R. Miliauskas Alston & Bird LLP The Atlantic Building 950 F Street, NW
Washington, DC 20004 (202) 239-3300
sean.atkins@alston.com
bradley.miliauskas@alston.com
The Honorable Kimberly D. Bose June 14, 2013
Page 5
VII. Service
Copies of this filing have been served on Synergy, the NYISO, and the New York State Public Service Commission.
VIII. Conclusion
For the foregoing reasons, Niagara Mohawk requests that the Commission accept the enclosed Agreement, effective as of August 14, 2013.
Respectfully submitted,
/s/ Amanda Downey
Amanda C. Downey
Counsel
National Grid USA
Service Company, Inc.
40 Sylvan Road
Waltham, MA 02451
Attorney for Niagara Mohawk Power
Corporation d/b/a National Grid