Daniel Galaburda
Senior Counsel

 

 

 

 

 

 

 

 

December 9, 2010

The Honorable Kimberly D. Bose Secretary

Federal Energy Regulatory Commission 888 First Street, NE, Room lA
Washington, D.C. 20426

 

RE: Niagara Mohawk Power Corporation Lyonsdale Biomass, LLC Interconnection Agreement Docket No. ER10-

Dear Secretary Bose:

Pursuant to Section 205 of the Federal Power Act, 16 U.S.C. § 824d, and Part

35.12 of the Federal Energy Regulatory Commission's ("Commission") regulations, 18 C.F.R. Part 35.12 (2006), Niagara Mohawk Power Corporation, d/b/a National Grid ("Niagara Mohawk"), submits for filing a Second Revised Service Agreement No. 1152 (" Second Revised Service Agreement") between Niagara Mohawk and Lyonsdale
Biomass, LLC ("Lyonsdale" or "Producer") under the New York Independent System
Operator, LLC's ("NYISO") open access transmission tariff, FERC Electric Tariff, Original Volume No. 1.  Under the Second Revised Service Agreement, Niagara Mohawk will
continue to provide interconnection service to Lyonsdale for Lyonsdale's 20 MW
generating facility located in Lewis County, New York.

 

I.Information Submitted with Filing

Niagara Mohawk filed the original interconnection agreement on July 28, 2007 in

Docket No. ER07-1094 ("Original Agreement").  It was accepted pursuant to a

Commission Order on November 2, 2007 in Docket No. ER07-1094.  On December 3, 2007, Niagara Mohawk filed a First Revised Service Agreement and this Agreement was accepted by Commission Order on April 4, 2008.

 

 

 

 

 

 

 

 

 

40 Sylvan Road, Waltham, MA 02451

T: 781-907-1847 F: 781-907-5701 daniel.galaburda@us.ngrid.com www.nationalgrid.com


 

 

 

 

 

The First Revised Agreement set the term to expire in June 2008.  Niagara

Mohawk and Lyonsdale desire that the interconnection relationship continue for an
additional ten years.  Due to the expiration of the First Revised Agreement and in an
effort to ensure the justness and reasonableness of the Second Revised Service
Agreement, Producer and Niagara Mohawk mutually agree to use as the form of the Second Revised Service Agreement the pro forma Large Generator Interconnection Agreement in Attachment X of the NYISO OATT.

The Second Revised Service Agreement restates, supersedes and replaces the First Revised Agreement in its entirety. Under the Second Revised Service Agreement, Niagara Mohawk will charge Producer for its actual costs of operating and maintaining the interconnection facility.

 

Pursuant to the Commission's order in New England Power Company, 109 FERC ¶
61, 364 (2004) (“NEP”), the Commission's standard interconnection rules promulgated in
Order No. 2006, and the procedures and agreements related thereto, including the NYISO
Small Generating Facility Interconnection Procedures, do not apply in this case. In NEP,
the Commission held that, where there are no proposed increases in capacity or material
modifications of the characteristics of an existing generating facility, Order No. 2003 did
not apply to generator interconnection agreements because they were not "new

interconnection requests.” Id. at P 13; see also Jersey Central Power & Light Company,
110 FERC ¶ 61,273 at P 11 (2005)(“because the revision to the existing interconnection
agreement does not 'increase the capacity of a generating unit in the PJM Region,’ PJM’s
interconnection procedures in its OATT...do not apply”). The Lyonsdale generating
facility is an existing facility, and there are no proposed increases in capacity or material
modifications to the characteristics of the facility. Thus, as the Commission held in NEP,
the Commission should also find here that the Commission's standard interconnection
rules promulgated in Order No. 2003, and the procedures and agreements related thereto,
including the NYISO Large Generator Interconnection Procedures, do not apply in this
case.

 

II.Communications and Service

Communications regarding this filing should be addressed to the following individuals, whose names should be entered on the official service list maintained by the Secretary for the docket established with respect to this filing:

Daniel Galaburda

Senior Counsel

National Grid USA Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451 Phone: (781) 907-1847 Fax: (781) 907-5701

Email: daniel.galaburda@us.ngrid.com


 

 

 

 

 

Mary Ellen Paravalos

Vice President of Transmission Regulation & Commercial Services Niagara Mohawk Power Corporation,

d/b/a National Grid 40 Sylvan Road Waltham, MA 02451

Phone: (781) 907-5706

Email: Mary.ellen.paravalos@us.ngrid.com

 

William Malee

Director of Transmission Commercial Services

Niagara Mohawk Power Corporation, d/b/a National Grid

40 Sylvan Road

Waltham, MA 02451
Phone: (781) 907-2422

Email: bill.malee@us.ngrid.com

 

A copy of this filing has been served on Lyonsdale Biomass, LLC, the New York Independent System Operator and the New York State Department of Public Service.

 

III. Proposed Effective Date

In accordance with section 35.3 of the Commission's Regulations, Niagara Mohawk respectfully requests that the Commission accept this Second Revised Service Agreement for filing, effective as of February 7, 2010.

 

IV.   Order No. 614 Designations

 

Pursuant to the Commission's orders in Designation of Electric Rate Schedule Sheets, Order No. 614, 90 FERC ¶ 61,352 (2000) and Southwest Power Pool, Inc., 92 FERC ¶ 61,109 (2000), Niagara Mohawk is required to designate the Revised Service Agreement as a service agreement under the NYISO OATT. As a result, Niagara

Mohawk has designated the Service Agreement as:

New York Independent System Operator, Inc. FERC Electric Tariff, Original Volume No. 1 Second Revised Service Agreement No. 1152 Issued by: Mary Ellen Paravalos

Vice President of Transmission Regulation & Commercial Services
National Grid USA for Niagara Mohawk Power Corporation
Issued on: December 9, 2010

Effective: February 7, 2010

V.Documents Enclosed

 

Enclosed please find:


 

 

 

 

 

i.This filing letter;

ii.A Second Revised Service Agreement No. 1152

Copies of this filing have been served on Lyonsdale Biomass, LLC, the NYISO and New York Public Service Commission.

Respectfully submitted, /s/ Daniel Galaburda

 

Daniel Galaburda
Senior Counsel

National Grid USA Service Company, Inc. 40 Sylvan Road

Waltham, MA 02451

Attorney for

Niagara Mohawk Power Corporation,

Enclosuresd/b/a National Grid