UNITED STATES OF AMERICA
BEFORE THE

FEDERAL ENERGY REGULATORY COMMISSION

 

 

 

 

New York Independent System Operator, Inc.)

and)Docket No. ER11-3479-000

Consolidated Edison Company of)

New York, Inc.)

 

 

 

 

MOTION FOR LEAVE TO FILE ANSWER
AND ANSWER TO PROTEST

 

Pursuant to Rules 212 and 213 of the Commission’s Rules of Practice and Procedure (18 CFR §§385.212, 385.213), the New York Independent System Operator, Inc. (“NYISO”) and Consolidated Edison Company of New York, Inc. (“Con Edison”) (collectively, “Joint Filing Parties”) file this Motion for Leave to File an Answer and Answer to the Protest that the New Jersey Board of Public Utilities (“NJBPU”) filed in this proceeding on May 23, 2011.

 

Motion for Leave to File Answer

Rule 213 states that an answer to a protest may be made only if allowed by the
Commission.  The Joint Filing Parties submit that good cause exists in this instance for
the submission of an answer to the NJBPU Protest and move the Commission to accept
this  Answer.    The  Commission  allows  unscheduled  answers  where  they  correct
misstatements  in  other  pleadings,  complete  the  record,  or  otherwise  assist  the


 

 

Commission in reaching an informed decision.  See, e.g., New York Independent System Operator, Inc., 108 FERC ¶61,188, P 7 (2004); Morgan Stanley Capital Group v. New York Independent System Operator, Inc., 93 FERC ¶ 61,017, at 61,036 (2000).  As indicated   by   the   following   discussion,   this   Answer   satisfies   those   standards. Accordingly, the Joint Filing Parties move pursuant to Rule 212 for leave to file this Answer to the NJBPU’s Protest.

 

 

Answer

The NJBPU’s Protest raises issues that are beyond the scope of this proceeding
and the NYISO’s interconnection process.  To a large extent, the NJBPU’s issues have
been addressed in other proceedings and need not - indeed, may not - be revisited here.

The   NJBPU’s   Protest   challenges   the   Merchant   Transmission   Facility
Interconnection Agreement among Hudson Transmission Partners, LLC (“HTP”), the
NYISO, and Con Edison (the “NY Interconnection Agreement”) which the NYISO and
Con Edison jointly filed in this proceeding on April 29, 2011.1  The NY Interconnection
Agreement provides for the interconnection to the New York State Transmission System
of a 660 MW transmission line and related equipment that will originate in New Jersey
and extend to New York City.  The facility will connect the control area operated by PJM
Interconnection, LLC (“PJM”) to the control area operated by the NYISO.

The NY Interconnection Agreement is one of the final requirements of the
NYISO’s interconnection process for the HTP project.  That process is conducted in
accordance with the procedures prescribed by Attachment S and Attachment X to the

 

 

1 See letter dated April 29, 2011 to Honorable Kimberly D. Bose in Docket No. ER11-3479-000 (“Filing
Letter”).

2


 

 

NYISO Open Access Transmission Tariff (“OATT”) for the review of generation and transmission interconnection proposals.  That process requires a series of studies “to evaluate the impact of the proposed interconnection on the reliability of the New York State Transmission System.”2  The NY Interconnection Agreement specifies the System Upgrade Facilities that must be constructed to preserve the reliability of the New York State Transmission System when the HTP project is interconnected.

The NY Interconnection Agreement substantially conforms to the NYISO’s pro
forma Large Generator Interconnection Agreement (“LGIA”) contained in Attachment X
of the NYISO OATT.  The agreement reflects a limited set of modifications to the pro
forma LGIA.  As discussed in the Filing Letter, those modifications are necessary to
adapt the pro forma LGIA to the unique characteristics of the HTP project.3  For
example, the textual modifications account for the difference in characteristics of a
transmission facility as compared to a generating facility and reflect the execution of the
NY Interconnection Agreement prior to HTP’s submission of an application for Unforced
Capacity   Deliverability   Rights. The   NYISO   and   Con   Edison   filed   the   NY

Interconnection Agreement because of its limited non-conforming provisions.  Therefore,
the only issue in this proceeding is whether those modified provisions are appropriate.
The NJBPU’s Protest raises issues that are beyond the scope of this proceeding and the interconnection process governing the NY Interconnection Agreement.  The NJBPU protest raises issues regarding the PJM capacity markets, the PJM Open Access Transmission Tariff, the processes that PJM uses to delist generation capacity, and the

 

2  See NYISO OATT, Attachment X, §30.7.3, at

http://www.nyiso.com/public/webdocs/documents/tariffs/oatt/oatt_attachments/att_x.pdf(Emphasis

added).

Filing Letter, pp. 2-8.

 

3


 

 

schedules for expanding the PJM system.  None of those matters are at issue in this proceeding.  The NJBPU’s issues regarding the reliability and economics of electric service in New Jersey do not relate in any way to the NY Interconnection Agreement or its non-conforming terms which are subject to review in this proceeding.

To a large extent, the NJBPU’s issues have been addressed in other proceedings
before the Commission.  Those proceedings include the proceeding in which PJM filed
its HTP Interconnection Service Agreement (“PJM Interconnection Agreement”),4 the
proceeding regarding HTP’s request for negotiated rate authority,5 and the proceeding
regarding PJM’s Minimum Offer Price Rule.6  The NJBPU’s issues which were not
addressed in those proceedings could have been raised in those proceedings.  In its
interconnection process, PJM reviewed the HTP project, concluded that the project would
not jeopardize reliability, and executed the PJM Interconnection Agreement with HTP
and Public Service Electric and Gas Company.7  The Commission accepted the PJM
Interconnection  Agreement,  noting  that  it  provided  HTP  with 320  MW  of  Firm

Transmission Withdrawal Rights.8  The NJBPU did not intervene in the docket in which
that agreement was filed.  The reliability implications of the HTP project were further
considered  in  connection  with  HTP’s  request  in  Docket  No.  ER11-3017-000  for

 

 

 

4  See PJM Interconnection, L.L.C., Docket No. ER10-1740-000 (2010).

5  See Hudson Transmission Partners, LLC, 135 FERC ¶ 61,104 (2011).

6  See PJM Interconnection, L.L.C., et al., 135 FERC ¶ 61,022 (2011).

7  Interconnection  Service  Agreement  By  and  Among  PJM  Interconnection,  L.L.C.  and  Hudson Transmission Partners, L.L.C. and Public Service Electric and Gas Company, Service Agreement No. 2536, effective June 9, 2010.

8   PJM Interconnection, L.L.C., Docket No. ER10-1740-000, Letter Order, dated August 31, 2010.  NJBPU
states, throughout its Protest, that the HTP Project will result in the removal of 660 MWs of existing
capacity from the PJM system; however, the PJM Interconnection Agreement limits the amount of firm

capacity that may be exported from PJM to 320 MW.

 

4


 

 

authorization to charge negotiated rates for transmission rights on its project.9  In granting
HTP’s request, the Commission found that HTP “has met the regional reliability and
operational efficiency requirement subject to [HTP’s] continued participation in the

regional planning process.”10  The NJBPU did not intervene in Docket No. ER11-3017-
000.

The  NJBPU  requests,  in  this  case,  that  the  Commission  reject  the  NY
Interconnection Agreement or hold it in abeyance and initiate a proceeding to further
consider the asserted impacts on New Jersey.  However, the NJBPU’s issues are beyond
the scope of this case and could have been raised in more appropriate proceedings.
Accordingly, the NJBPU’s relief request must be denied and its protest dismissed.

 

 

Conclusion

For the reasons stated in this Answer, the NYISO and Con Edison respectfully request that the Commission reject the NJBPU’s Protest.

Respectfully submitted,

 

/s/ Sara B. Keegan

Sara B. Keegan
Counsel for the

New York Independent System Operator, Inc.

 

/s/  Donald J. Stauber

Donald J. Stauber

Counsel for Consolidated Edison Company of New York, Inc.

 

 

9  Hudson Transmission Partners, L.L.C., 135 FERC ¶ 61,104 (April 29, 2011) (“HTP Market Rate
Order”).

10 HTP Market Rate Order, P 37.

 

5


 

 

 

 

CERTIFICATE OF SERVICE

 

 

 

I hereby certify that I have this 8th day of June, 2011 caused the foregoing

document to be served upon each party designated on the official service list compiled by the Secretary in this proceeding by email.

 

 

/s/  Donald J. Stauber

Donald J. Stauber

Counsel for Consolidated Edison Company of New York, Inc.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6