10 Krey Boulevard Rensselaer, NY 12144
June 30, 2015
By Electronic Delivery
Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE
Washington, DC 20426
Re: Filing of an Executed Engineering, Procurement, and Construction Agreement
Among the New York Independent System Operator, Inc., New York State
Electric & Gas Corporation, and CPV Valley, LLC; and Request for Waiver of
the 60-Day Notice Period; Docket No. ER15-___000
Dear Ms. Bose:
Pursuant to Section 205 of the Federal Power Act1 and Section 35.12 of the
Commission’s regulations,2 the New York Independent System Operator, Inc. (“NYISO”) and New York State Electric & Gas Corporation (“NYSEG”) (together, the “Joint Filing Parties”) hereby tender for filing an executed engineering, procurement, and construction agreement (“EPC Agreement”) among the NYISO, NYSEG, and CPV Valley, LLC (“CPV”). The EPC Agreement is labeled as Service Agreement No. 2215.
CPV is developing a nominal 680 MW combined-cycle generating facility (“Facility”)
that will interconnect with the transmission facilities of the New York Power Authority
(“NYPA”). The NYISO’s Class Year 2011 Interconnection Facilities Study (“Facilities Study”)
determined that this interconnection will also have impacts on NYSEG’s transmission system,
which is part of the New York State Transmission System.3 The Facilities Study identified
certain System Upgrade Facilities that are required on NYSEG’s system for the Facility to
interconnect reliably to the New York State Transmission System. The EPC Agreement governs
the rates, terms, and conditions regarding the engineering, procurement, and construction of the
System Upgrade Facilities on NYSEG’s transmission system. The EPC Agreement is based on
and generally conforms with the pro forma Large Generator Interconnection Agreement (“Pro
Forma LGIA”) contained in Attachment X to the NYISO Open Access Transmission Tariff
(“OATT”).
The Joint Filing Parties respectfully request that the Commission accept the EPC
Agreement for filing. Further, as described in Part III of this letter, the Joint Filing Parties
1 16 U.S.C. § 824d (2014).
2 18 C.F.R. § 35.12 (2014).
3 Capitalized terms that are not otherwise defined in this filing shall have the meaning specified in
Attachments X and S of the NYISO OATT, and if not defined therein, in Section 1 of the NYISO OATT.
Honorable Kimberly D. Bose June 30, 2015
Page 2
respectfully request a waiver of the Commission’s prior notice requirements4 to make the EPC Agreement effective as of the June 9, 2015, which is the date of its execution.
I.BACKGROUND
CPV is developing a nominal 680 MW combined-cycle generating facility that will be
located in Orange County, New York. The Facility will interconnect to certain transmission
facilities of NYPA that are part of the New York State Transmission System. CPV’s Facility
was included in and studied as part of the Class Year 2011 Facilities Study. The Facilities Study
determined that the interconnection of the Facility will have certain impacts on the transmission
system of NYSEG and identified NYSEG as an Affected Transmission Owner.5 The Facilities
Study identified certain System Upgrade Facilities that must be constructed on NYSEG’s system
to provide for the reliable interconnection of the Facility to the New York State Transmission
System (“Affected System Upgrade Facilities”). CPV accepted and provided security to
NYSEG to cover the costs identified in the Facilities Study for the construction of the Affected
System Upgrade Facilities.
The NYISO and NYPA, as the Connecting Transmission Owner, have jointly filed an executed Large Generator Interconnection Agreement among the NYISO, NYPA, and CPV for the interconnection of the Facility to the transmission facilities of NYPA (“CPV LGIA”).6 In the CPV LGIA, the parties indicated that the construction of the Affected System Upgrade Facilities on NYSEG’s system would be addressed through a separate EPC Agreement among the NYISO, NYSEG, and CPV. Consistent with Commission precedent and NYISO practice, the parties
developed and executed the EPC Agreement for the construction of the Affected System
Upgrade Facilities using the Pro Forma LGIA as a template.7
4 See Prior Notice and Filing Requirements Under Part II of the Federal Power Act, 64 FERC ¶ 61,139, clarified, 65 FERC ¶ 61,081 (1993).
5 The Facilities Study also identified that the interconnection of the Facility will have certain
impacts on the transmission system of Central Hudson Gas & Electric Corporation (“Central Hudson”) and identified Central Hudson as an Affected Transmission Owner as well. The NYISO is separately filing an EPC Agreement among the NYISO, Central Hudson, and CPV for the engineering, procurement, and construction of the System Upgrade Facilities that are required on Central Hudson’s system for the Facility to interconnect reliably to the New York State Transmission System.
6 New York Independent System Operator, Inc. and New York Power Authority, Filing of
Executed Large Generator Interconnection Agreement Among the New York Independent System
Operator, Inc., the New York Power Authority, and CPV Valley, LLC; Request for Waiver of 60-Day
Notice Period; and Request for Critical Energy Infrastructure Information Designation, Docket No. ER15-
1895-000 (June 10, 2015).
7 There is no pro forma EPC Agreement in the NYISO OATT. The parties have based the EPC
Agreement on the Pro Forma LGIA, consistent with Commission precedent. See New York Independent
System Operator, Inc., and Niagara Mohawk Power Corporation, Ltr. Order, Docket No. ER08-230-000
(December 18, 2007); see also Midwest Independent Transmission System Operator, Inc., 113 FERC ¶
61,048 (2005); Duke Electric Transmission, a Division of Duke Energy Corp., 113 FERC ¶ 61,139
(2005).
2
Honorable Kimberly D. Bose June 30, 2015
Page 3
II. DESCRIPTION OF THE EPC AGREEMENT
NYSEG, as the Affected Transmission Owner, will engineer, procure, and construct the
Affected System Upgrade Facilities in accordance with the terms of the EPC Agreement (“EPC
Services”). CPV has posted security to NYSEG to cover the costs of constructing these facilities
identified in the Facilities Study in accordance with the requirements in Attachment S of the
NYISO OATT. Any differences in cost between the posted security and the final cost of
constructing the facilities will be allocated in accordance with the tariff requirements for
addressing such differences in Section 25.8.6 of Attachment S of the NYISO OATT. The
NYISO’s role in the EPC Agreement will be limited to certain oversight rights and
responsibilities.
The EPC Agreement is based on the Pro Forma LGIA, as modified: (i) to reflect the
different purpose of the agreement, (ii) to allocate the parties’ responsibilities for the
performance of the EPC Services and the payment for such performance, and (iii) to set forth the scope of work, cost estimate, and milestone schedule for the construction of the Affected System Upgrade Facilities.
The EPC Agreement varies from the Pro Forma LGIA primarily as follows, consistent
with the approach the Commission approved with regard to a similar EPC agreement in 2007:8
• The EPC Agreement governs only the performance of the EPC Services and
terminates upon the completion of the Affected System Upgrade Facilities and the payment of related invoices. For this reason, the EPC Agreement does not include the provisions of the Pro Forma LGIA that govern the ongoing operation or
maintenance of the constructed facilities.9
• The EPC Agreement is limited to the activities required to construct and place in
service the Affected System Upgrade Facilities. For this reason, the EPC Agreement does not include the provisions of the Pro Forma LGIA that govern the activities
required to construct and place in service the Large Generating Facility, the
Attachment Facilities, other System Upgrade Facilities, or System Deliverability
Upgrades. These requirements are addressed under the CPV LGIA among the
NYISO, NYPA, and CPV.
• The EPC Agreement does not include the provisions of the Pro Forma LGIA that
govern the NYISO’s provision of interconnection service to CPV, which is addressed under the CPV LGIA among the NYISO, NYPA, and CPV.
8 See New York Independent System Operator, Inc., and Niagara Mohawk Power Corporation, Ltr. Order, Docket No. ER08-230-000 (December 18, 2007).
9 Once completed, NYSEG will own the Affected System Upgrade Facilities and be responsible for their operation and maintenance. The requirements for the ongoing operation and maintenance of the Facility are set forth in the CPV LGIA among the NYISO, NYPA, and CPV.
3
Honorable Kimberly D. Bose June 30, 2015
Page 4
• As NYSEG will perform the EPC Services, the EPC Agreement does not include the
provisions of the Pro Forma LGIA that address the developer’s options and
responsibilities for performing such work.
• As the parties have already completed the interconnection studies necessary to
determine the impact of the interconnection, the EPC Agreement does not include the provisions of the Pro Forma LGIA that address such studies.
• The EPC Agreement replaces the use of the term “Connecting Transmission Owner”
(i.e., NYPA”) with “Affected Transmission Owner” (i.e., NYSEG), except where the
language is referring to the interconnection of CPV’s Facility with NYPA’s
transmission facilities.
• The EPC Agreement also includes minor clean-ups and revisions agreed upon among
the NYISO, NYSEG, and CPV as consistent with the terms of the EPC Agreement.
The Joint Filing Parties provide in Attachement I of this filing letter a matrix that
describes in greater detail the differences between the EPC Agreement and the Pro Forma
LGIA.10
III. EFFECTIVE DATE AND REQUEST FOR WAIVER
The Joint Filing Parties request an effective date of June 9, 2015, for the EPC Agreement,
which is the date of its execution. The Joint Filing Parties respectfully request that the
Commission waive its prior notice requirement to permit the requested effective date. The
Commission has previously permitted similar agreements to become effective upon the date of
execution.11
10 As described in this filing letter, the Joint Filing Parties have replaced “Connecting
Transmission Owner” with “Affected Transmission Owner” throughout the EPC Agreement with limited exceptions. The Joint Filing Parties have not highlighted this change, which applies in most provisions of the EPC Agreement, in the matrix in Attachment I.
11 See, e.g., New York Independent System Operator, Inc. and New York State Electric & Gas
Corporation, Docket No. ER11-2953-000 (April 7, 2011) (accepting interconnection agreement effective as of date of execution); see also New York Independent System Operator, Inc. and Niagara Mohawk Power Corp., Letter Order, Docket No. ER08-985-000 (June 26, 2008) (same); New York Independent System Operator, Inc. and New York Power Authority, Letter Order, Docket No. ER08-861-000 (May 27, 2008) (same); New York Independent System Operator, Inc. and New York Power Authority, Letter
Order, Docket No. ER08-699-000 (May 16, 2008) (same).
4
Honorable Kimberly D. Bose June 30, 2015
Page 5
IV. COMMUNICATIONS AND CORRESPONDENCE
Communications regarding this filing should be directed to:
For the NYISO12
Robert E. Fernandez, General Counsel
Karen Georgenson Gach, Deputy General Counsel
*Sara B. Keegan, Senior Attorney
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-6000
Fax: (518) 356-4702
skeegan@nyiso.com
*Ted J. Murphy
Hunton & Williams LLP
2200 Pennsylvania Avenue, NW Washington, D.C. 20037
Tel: (202) 955-1500
Fax: (202) 778-2201
tmurphy@hunton.com
*Michael J. Messonnier Jr. Hunton & Williams LLP 951 East Byrd Street
Richmond, VA 23219
Tel: (804) 788-8200
Fax: (804) 344-7999
mmessonnier@hunton.com
For NYSEG:
*Jeffrey A. Rosenbloom
Director, NY Legal Services
New York State Electric & Gas Corporation
c/o Rochester Gas and Electric Corporation
89 East Avenue,
Rochester, NY 14649
Tel (585) 724-8132
Fax: (585) 724-8668
jeffrey_rosenbloom@rge.com
*Designated to receive service.
V.DOCUMENTS SUBMITTED
The NYISO submits the following documents:
• this filing letter;
12 The NYISO respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) (2014) to permit service on counsel in both Washington, D.C. and Richmond, VA.
5
Honorable Kimberly D. Bose June 30, 2015
Page 6
• the matrix describing the differences between the EPC Agreement and the Pro Forma
LGIA (Attachment I);
• a clean version of the EPC Agreement (Attachment II);
• a blacklined version of the EPC Agreement showing the changes from the body of the
Pro Forma LGIA (Attachment III); and
• the signature pages for the EPC Agreement (Attachment IV). VI. SERVICE
The NYISO will send an electronic link to this filing to the official representative of each
of its customers, to each participant on its stakeholder committees, to the New York Public
Service Commission, and to the New Jersey Board of Public Utilities. In addition, a complete
copy of the Public documents included with this filing will be posted on the NYISO’s website at
www.nyiso.com.
VII. CONCLUSION
Wherefore, the Joint Filing Parties respectfully request that the Commission accept the EPC Agreement for filing with an effective date of June 9, 2015.
Respectfully submitted,
/s/ Sara B. Keegan
Sara B. Keegan
Counsel for the
New York Independent System Operator, Inc.
/s/ Jeffrey A. Rosenbloom
Counsel for
New York State Electric & Gas Corporation
cc:Michael Bardee
Gregory Berson
Anna Cochrane
Morris Margolis
David Morenoff
Daniel Nowak
Kathleen Schnorf
Jamie Simler
Kevin Siqveland
6