10 Krey Boulevard     Rensselaer, NY  12144

 

 

 

November 29, 2010


 

 

By Electronic Delivery

Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE

Washington, DC 20426


 

CONTAINS CRITICAL ENERGY
INFRASTRUCTURE INFORMATION


Re:    Filing of an Executed Large Generator Interconnection Agreement Among the
New York Independent System Operator, Inc., Consolidated Edison Company of
New York, Inc., and Bayonne Energy Center, LLC and Request for Critical
Energy Infrastructure Information Designation, Docket No. ER11- ___-000

Dear Ms. Bose:

Pursuant to Section 205 of the Federal Power Act,1 Section 35.12 of the Commission’s
Regulations,2 and Section 11.3 of its Large Facility Interconnection Procedures (“LFIP”), the
New York Independent System Operator, Inc. (“NYISO”) and Consolidated Edison Company of
New York, Inc. (“Con Edison”) (“Joint Filing Parties”) hereby tender for filing an executed
standard large generator interconnection agreement (“Interconnection Agreement”) as Service
Agreement No. 1668 among the NYISO, Con Edison as the Transmission Owner, and Bayonne
Energy Center, LLC (“BEC”) as the Developer.3  With the limited exceptions noted in Section II
of this letter, the Interconnection Agreement conforms to the NYISO’s pro forma Large
Generator Interconnection Agreement (“LGIA”) that is contained in Attachment X of the
NYISO’s OATT.

 

I.Background

The Interconnection Agreement governs the interconnection of BEC’s Large Generating Facility (“BEC Facility”).  The BEC Facility is a nominal 512 MW multi-unit, simple-cycle natural gas-fired (with ultra low sulfur diesel oil as a backup fuel) Large Generating Facility to be located in Bayonne, New Jersey.  The BEC Facility has a net summer capability of 500 MW at 95º F, and a net winter capability of 500 MW at 10º F.  The BEC Facility will not deliver in excess of 500 MW to the Point of Interconnection at any time.

 

 

1 16 U.S.C. § 824d (2006).

2 18 C.F.R. § 35.12 (2008).

3 Capitalized terms not otherwise defined in this letter have the meaning set forth in Attachments S and X of the NYISO’s Open Access Transmission Tariff (“OATT”).


 

 

Honorable Kimberly D. Bose November 29, 2010

Page 2

 

 

The Large Generating Facility will consist of eight 64 MW generating units connecting to a 138 kV ring bus.  From the ring bus, power will be delivered to Con Edison’s Gowanus 345 kV Substation via a two winding, 138-345 kV switchyard step up transformer (SSU) and a 6.75 mile AC land/submarine cable.  The Point of Interconnection will be between Breakers #20 and #22 of the 345kV ring bus to be developed, at Gowanus, as a result of this project.  The Point of
Interconnection is identified on Figure A-1 of Appendix A of the Interconnection Agreement which is designated as CEII for the reasons discussed in Section III, infra.

 

II. Variations From the NYISO’s Pro Forma LGIA

As noted above, the Interconnection Agreement is based on the NYISO’s pro forma

LGIA; however, the parties have agreed to make a limited set of modifications to the pro forma LGIA.  These modifications are described below and are primarily necessary to reflect (A) the timing of the execution of the Interconnection Agreement vis-à-vis the Class Year 2009
Interconnection Facilities Study (“Class Year 2009 Study”); (B) the operational control of the Con Edison facilities affected by the Interconnection Agreement; and (C) the existence of preexisting license and easement agreements between Con Edison and BEC.  All of the parties to the Interconnection Agreement (“Parties”) agree to these changes.

The Commission has accepted changes to the pro forma LGIA terms where, as here,

there are unique circumstances associated with the interconnections, including “reliability

concerns, novel legal issues or other unique factors.”4  In fact, certain of the modifications to the pro forma LGIA in this Interconnection Agreement are substantially similar or identical to those previously accepted by the Commission.5   The Joint Filing Parties have included a blackline of the Interconnection Agreement against the NYISO’s pro forma LGIA to highlight these changes. The NYISO respectfully requests that the Commission accept these modifications in light of the unique factors and novel legal issues explained below.

A.Revisions to reflect the timing of the execution of the Interconnection

Agreement

The BEC Facility is completing its Interconnection Facilities Study as a member of

Class Year 2009, which is not yet completed.  Because the Interconnection Agreement was

executed prior to completion of the Class Year Study, the Parties have modified Articles 2.3.1.1
and 2.3.1.2 regarding the effect of non-acceptance of Project Cost Allocation for Class Year
2009 and post termination responsibilities, should BEC elect not to accept its Project Cost
Allocation for Class Year 2009.  Specifically, BEC’s election not to accept its Project Cost
Allocation for Class Year 2009 shall be deemed a termination of the Interconnection Agreement

 

 

4 See PJM Interconnection, LLC, 111 FERC ¶ 61,163 at PP-10-11, reh’g denied 112 FERC ¶ 61,282

(2005).

5 See New York Independent System Operator, Inc. and Consolidated Edison Company of New York, Inc., 123 FERC ¶ 61,093 (Apr. 29, 2008).


 

 

Honorable Kimberly D. Bose November 29, 2010

Page 3

 

 

by BEC under Article 2.3.1.  BEC may effect such election not to accept its Project Cost

Allocation for Class Year 2009 by (i) providing Notice of Non-Acceptance of the Project Cost
Allocation, or (ii) failing to post Security for SUFs for which it is responsible in accordance with
Attachment S.  Article 2.3.1.2 provides that once BEC elects not to accept its Project Cost
Allocation for Class Year 2009, it shall promptly (i) demobilize and cease further construction at
the Gowanus Substation site, and (ii) remove or cause the removal of all equipment, tools and
materials of BEC, its contractors and vendors from the Gowanus Substation site.  Article 2.3.1.2
further provides that Con Edison shall take such steps as reasonably necessary to return the
Gowanus Substation location to a safe and reliable condition in accordance with Article 5.16 of
this Agreement and bill BEC for the reasonable costs of same under Article 12 of the
Interconnection Agreement.

BEC has elected to seek both Energy Resource Interconnection Service and Capacity Resource Interconnection Service.  The Class Year Study includes evaluation of deliverability that determines eligibility for Capacity Resource Interconnection Service (“CRIS”).
Accordingly, the Parties modified the Interconnection Agreement by making Article 4.1.1, which indicates that the project is taking CRIS, subject to the requirements of Appendix A, Section 5. Appendix A, Section 5 specifically provides that BEC may not supply Unforced Capacity to the New York Control Area from the BEC Facility until it has complied with the deliverability
requirement pursuant to Attachment S of the NYISO OATT, including acceptance of any cost allocation for SDUs and the posting of associated security or payments.

B.Deviations required due to the operational control of the Connecting

Transmission Owner’s facilities

Con Edison Attachment Facilities and Stand Alone System Upgrade Facilities involved in the interconnection of the BEC Facility (“Con Edison Facilities”) are classified as
“Transmission Facilities Requiring ISO Notification” pursuant to Appendix A-2 of the
Agreement Between NYISO and Transmission Owners (NYISO/TO Agreement), not as
“Transmission Facilities Under ISO Operational Control” set forth in Appendix A-1 of the
NYISO/TO Agreement.  Accordingly, the Parties have modified Article 5.1.1 of the
Interconnection Agreement to reflect that Con Edison will not transfer operational control of its Attachment Facilities and Stand Alone System Upgrade Facilities, but that such facilities will be treated as Transmission Facilities Requiring ISO Notification.

C. Deviations required due to the existence of related contractual agreements

Con Edison and BEC are parties to a license agreement and easement agreement

described in section 2(g) of Appendix C of the Interconnection Agreement (“Additional

Agreements”).  Accordingly, the Parties have agreed to modifications to Articles 28.1.3 and 29.6
to address these Additional Agreements.  With respect to the interaction between the
Interconnection Agreement and the pre-existing contractual obligations set forth in the
Additional Agreements, Appendix C, Section 2(g) indicates that “[i]t is the belief and intention
of the Parties that nothing in this [Interconnection] Agreement conflicts in any material way with
those Additional Agreements.”  Further, as reflected in Appendix C, Section 2(g), if the Parties


 

 

Honorable Kimberly D. Bose November 29, 2010

Page 4

 

 

become aware of a conflict, the Parties will discuss “what, if any, amendment of this [Interconnection] Agreement would be appropriate under the circumstances.”

D.Deviations required to reflect principles associated with construction activity

at Con Edison’s Gowanus Substation

The parties have also added new Appendix H to the Interconnection Agreement which provides the detailed principles associated with construction activity at Con Edison’s Gowanus substation.  A similar such Appendix was added to the Interconnection Agreement accepted by the Commission on April 29, 2008 in Docket No. ER08-618-000. 6

Appendix H specifically refers to an agreement executed, prior to the Interconnection
Agreement, between Con Edison and BEC for certain engineering services.  These agreements
are a Master Services Agreement and Transaction Form 3 (Engineering Agreement) and are
described in Appendix H, Section 2 and attached as H-2.  These two agreements were previously
filed with the Commission in Docket No. ER10-477-000 and accepted by letter Order dated
February 17, 2010.  Under the Interconnection Agreement, the Parties agree that Con Edison will
complete these specific engineering services pursuant to the terms and conditions of the
Engineering Agreement.

E. Deviations expressly contemplated by the LGIA

Article 29.2 of the Interconnection Agreement provides for discrepancies or conflicts
between or among terms and conditions of the cover agreement and its Appendices.  The
language of this Article specifically provides that the terms and conditions of the cover
agreement shall be given precedence over the Appendices, “except as otherwise expressly
agreed in writing by the Parties.”  (emphasis added)  Exercising the rights afforded to them by
this last clause, italicized above, the Parties added a provision to this article expressly agreeing
that the terms and conditions of the Appendices shall take precedence over the provisions of the
cover agreement in case of a discrepancy or conflict between or among the terms and conditions
of same.

 

III. Request for CEII Treatment

Pursuant to the Commission’s regulations at 18 C.F.R. §388.112 and 18 C.F.R. §

388.113, Con Edison requests that the one-line diagram included as part of Appendix A to the
Interconnection Agreement (Figure A-1) be protected from disclosure as Critical Energy
Infrastructure Information (“CEII”).  This one-line diagram contains detailed, one-line
schematics of transmission lines, the Gowanus substation and generation facilities that, if
disclosed, could pose a threat to the security and the reliability of the New York State bulk power

 

 

6 See New York Independent System Operator, Inc. and Consolidated Edison Company of New York, Inc., 123 FERC ¶ 61,093 (Apr. 29, 2008).


 

 

Honorable Kimberly D. Bose November 29, 2010

Page 5

 

 

system.  This diagram provides more than simply the general location of critical infrastructure.
Unlike publicly available maps of power transmission lines and generation and substation
facilities, this schematic shows the exact nature and specific location of facilities and
transmission lines used to maintain the reliability of the New York State bulk power system.
This diagram, in Con Edison’s assessment, reveals such critical information related to the
facilities and transmission depicted therein that, if disclosed, could be useful to a person seeking
to disable the power grid.  Therefore, the disclosure of this CEII diagram would pose a threat to
the reliability of the New York State bulk power system and to the health and safety of New
York residents.  Moreover, the information revealed in this schematic reveals CEII which FERC
has determined to be exempt from mandatory disclosure under 5 U.S.C. § 552(b)(7)(F). The
diagram has been omitted from the Public version of the Interconnection Agreement included in
this filing. The diagram is included only in the CEII version of the Interconnection Agreement in
the filing.

All communications relating to this request for CEII treatment should be addressed to the following:

 

 

John BeckDonald J. Stauber

Section ManagerAssistant General Counsel

Consolidated Edison Company of New York,Consolidated Edison Company of New York,

Inc.Inc.

4 Irving Place, Room 1450-S4 Irving Place, Room 1815-S

New York, NY  10003New York, NY  10003

Fax: (212) 529-1130Fax: (212) 677-5850

Phone: (212) 460-4244Phone: (212) 460-4494

 

IV.    Effective Date

The parties request an effective date of November 10, 2010, the date of execution of the
Interconnection Agreement.  The Commission has allowed interconnection agreements to
become effective on the date of execution, even when that date precedes the date that an
interconnection agreement is filed.  Accordingly, the parties request that the Commission grant a
waiver of its prior notice requirements to the extent necessary to accommodate this requested
effective date.

 

V.Communications and Correspondence

Communications regarding this filing should be directed to:


 

 

Honorable Kimberly D. Bose November 29, 2010

Page 6

 

 

For the NYISO

Robert E. Fernandez, General Counsel

Karen Georgenson Gach, Deputy General Counsel *Sara B. Keegan, Senior Attorney

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144
Tel:  (518) 356-6000
Fax: (518) 356-4702
rfernandez@nyiso.com
kgach@nyiso.com
skeegan@nyiso.com

For Consolidated Edison Company of New York, Inc.

*Donald J. Stauber, Assistant General Counsel

Consolidated Edison Company of New York, Inc.

4 Irving Place, Room 1815-S

New York, NY  10003
Fax: (212) 677-5850
Phone: (212) 460-4494
stauberd@coned.com

*Designated to receive service.

 

VI.    Documents Submitted

The NYISO submits the following documents:

A.this filing letter;

B.a clean Public version of the Interconnection Agreement;

C.a blacklined Public version showing the Interconnection Agreement’s

changes from the body of the NYISO’s pro forma LGIA and the addition of Appendix H; and

D. a clean CEII version of the Interconnection Agreement.

 

VII.   Service

The NYISO will send an electronic link to this filing to the official representative of each of its customers, to each participant on its stakeholder committees, to the New York Public


 

 

Honorable Kimberly D. Bose November 29, 2010

Page 7

 

 

Service Commission, and to the electric utility regulatory agency of New Jersey.  In addition, a
complete copy of this filing will be posted on the NYISO’s website at www.nyiso.com.

 

VIII. Conclusion

Wherefore, the NYISO respectfully requests that the Commission accept the attached Agreement effective as of November 10, 2010.

 

 

Respectfully submitted,

 

/s/ Sara B. Keegan

Sara B. Keegan
Counsel for the

New York Independent System Operator, Inc.

 

/s/Donald J. Stauber

Donald J. Stauber

Counsel for Consolidated Edison Company of New York, Inc.