HUNTON & WILLIAMS LLP
1900 K STREET, N.W.

WASHINGTON, D.C.  20006-1109

 

TEL202 • 955 • 1500

FAX202 • 778 • 2201

 

WILLIAM F. YOUNG, ESQ.
DIRECT DIAL:  202-955-1684
EMAIL:  wyoung@hunton.com

August 13, 2010FILE NO: 55430.000055

 

 

 

Submitted Electronically

 

Kimberly D. Bose, Secretary

Federal Energy Regulatory Commission 888 First St., N.E.

Washington, D.C. 20426

 

Re:    New York Independent System Operator, Inc. Request for Authority to Apply a Market
Power Mitigation Measure to Rest-of-State Generators Committed or Dispatched for
Reliability, Docket No. ER10-___-000

Dear Secretary Bose:

Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and consistent with

paragraphs 66, 101 and 102 and ordering paragraph (C) of the Commission’s May 20, 2010
Order on Proposed Application of Mitigation Measures and Compliance Filings in Docket
ER09-1682-000 et al. (“May 20 Order”),2 the New York Independent System Operator, Inc.
(“NYISO”) submits this Request for Authority to Apply a Market Power Mitigation Measure to
Rest-of-State Generators Committed or Dispatched for Reliability.  This filing proposes to apply
a market power mitigation measure that is similar to the mitigation measure that was accepted by
the Commission in the May 20 Order, but that will apply to all Rest-of-State (“ROS”)3
Generators that can exercise market power when they are committed or dispatched to maintain
system reliability.4

 

 

116 U.S.C. § 824d.

2N.Y. Indep. Sys. Operator, Inc., 131 FERC ¶ 61,169 (2010).

3In this filing, the term Rest-of-State or ROS refers to Generators located outside a

designated Constrained Area.  “Constrained Area” is defined in Section 23.2.1 of Attachment H to the NYISO’s Market Administration and Control Area Services Tariff.

4Unless otherwise specified, capitalized terms have the meanings specified in the
NYISO’s Market Administration and Control Area Services Tariff (“Services Tariff”).

 

 

ATLANTA   AUSTIN   BANGKOK   BEIJING   BRUSSELS   CHARLOTTE   DALLAS   HOUSTON   LONDON   LOS ANGELES
McLEAN   MIAMI   NEW YORK   NORFOLK   RALEIGH   RICHMOND   SAN FRANCISCO   WASHINGTON

www.hunton.com


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 2

I. List of Documents Submitted with this Filing

1.This filing letter.

2.A clean version of proposed revisions the NYISO’s Market Power Mitigation

Measures (“MMM”).  The MMM are set forth in Attachment H to the Services Tariff.

3.A blacklined version of the proposed revisions to the MMM.

4.A clean version of proposed revisions to the NYISO’s Market Monitoring Plan.

The Market Monitoring Plan is set forth in Attachment O to the Services Tariff.

5.A blacklined version of the proposed revisions to the Market Monitoring Plan.

6.The NYISO Board of Directors’ Decision on Appeal of the Management

Committee’s May 28, 2010 Decision Adopting Mitigation Measures that will Apply to Rest-Of-

State Generators that are Committed for Reliability (July 29, 2010).

7.The Dissenting Opinion of Thomas F. Ryan on Appeal of the Management

Committee’s May 28, 2010 Decision Adopting Mitigation Measures that will Apply to Rest-Of-

State Generators that are Committed for Reliability (July 29, 2010).

II. Copies of Correspondence


Robert E. Fernandez
General Counsel
Elaine D. Robinson

Director of Regulatory Affairs *Alex M. Schnell

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144
Tel: (518) 356-8707
Fax: (518) 356-7678
aschnell@nyiso.com

 

*Persons designated for receipt of service


*William F. Young
Hunton & Williams LLP 1900 K St., N.W.

Washington, D.C. 20006-1109 Tel: (202) 955-1684

Fax: (202) 828-3740
wyoung@hunton.com


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 3

III. Background

The Commission’s May 20 Order accepted as just and reasonable a market power

mitigation measure proposed by the NYISO that applies to three identified ROS Generators that
can exercise market power when they are needed for system or local reliability.  The measure
mitigates those Generators’ guarantee payments; that is, “the payments that generators receive as
revenue from NYISO when they are dispatched out of economic merit order for reliability
purposes.”5

In paragraph 73 of the May 20 Order, the Commission noted that “in a competitive

market, a generator lacking market power would be expected to submit bids into the NYISO spot
market at a level that, if accepted at that bid price, would be expected to cover the generator’s
marginal costs.”6  The Commission also explained that “the ability to include and recover costs
in excess of marginal cost, including fixed costs, in bids during periods when the generators are
required to run for reliability is evidence of market power.”7  The mitigation measure for the
three generators is based on thresholds that would be triggered by bidding in a manner that is not
consistent with the principles articulated by the Commission.  The May 20 Order found that the
proposed mitigation measure is appropriate because “when a pivotal generator is required out-of-
merit for reliability, there is no dispute that it possesses market power, and thus that mitigation
may be required.”8

In the May 20 Order, the Commission stated that:  “We are concerned with the absence
of a generally applicable mitigation measure to address the exercise of market power in those
instances where a generator is the only solution to a reliability need.”9  The Commission further
stated its belief

that it may be appropriate for the NYISO to be authorized to immediately mitigate
such conduct rather than having to not only investigate whether the conduct and
impact thresholds of section 3.2.3 have been met on a case-by-case basis for

 

 

 

5May 20 Order at P2.

6Id. at P73.

7Id.

8Id. at P78.
9Id. at P101.


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 4

specified individual generators but then delay mitigation by having to file a mitigation proposal under section 205.10

Thus, the Commission “encourage[d] NYISO’s efforts to develop a generally applicable version
of Rate Schedule M-1 which would be applied to all market participants located outside of New
York City . . . ,” and instructed the NYISO to either file a proposed, generally applicable
mitigation measure, or to file a progress report on its efforts to develop such a measure, within

90 days.11  This filing fulfills the Commission’s requirement.

Following the September 4, 2009 filing that resulted in the May 20 Order, the NYISO
engaged in extensive stakeholder discussions to develop a mitigation measure targeted at ROS
Generators that are committed for reliability, and that will apply at times when a single Supplier
is pivotal to solving an identified reliability need.  In order to address transparency concerns
raised by the Generation Owners sector in the stakeholder process, the NYISO agreed to require
a Transmission Owner that requests a local reliability commitment to identify the Suppliers that
are capable of meeting the reliability need, or to inform the NYISO that the requested Supplier is
the only one that can meet the reliability need.  At the request of the Generation Owners sector,
the NYISO also deleted language from its initial mitigation proposal specifying that a Generator
would be subject to mitigation if it “was the only resource designated by a Transmission Owner
to solve a local reliability need.”  These changes clarify that a Supplier whose Generator is
committed or dispatched for reliability will have access to information supporting the application
of the mitigation measure proposed in this filing.

Also in response to a request from the Generation Owners sector, the NYISO developed a
proposal for temporarily providing additional compensation to Generators that are not able to
recover their going-forward costs in the NYISO’s markets.12  While most stakeholders indicated
that they were willing to participate in further discussions to determine if such a measure is
needed and, if so, to develop a compensation mechanism, no stakeholder supported the NYISO’s
proposed measure.  Based on the comments it received (both in writing and at the stakeholder
meetings), the NYISO determined that it would not be appropriate to delay the submission of this
filing until an acceptable compensation mechanism (if needed) was developed.  The NYISO

 

10Id.

11Id. at P66; see also May 20 Order at PP101 and 102.

12See presentations by Dr. Nicole Bouchez, the manager of the NYISO’s Market

Mitigation and Analysis Department, to the February 25, 2010, March 25, 2010 and April 19,
2010 Market Issues Working Groups.  The stakeholder comments that the NYISO received are
posted with the NYISO’s March 25, 2010 Market Issues Working Group meeting materials.
These materials can be found on the NYISO’s website (www.nyiso.com).


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 5

believes its decision is consistent with paragraphs 66, 101 and 102 of the May 20 Order, although the NYISO’s decision was made before the May 20 Order was issued.

The improved mitigation measure proposed in this filing was approved for submission as a Section 205 filing by the Business Issues Committee on May 5, 2010, and by the Management Committee at its meeting on May 28.  Both votes were contested, with all of the Generation Owners and many members of the Other Suppliers sector voting against the proposal.

Following the May 28 Management Committee meeting, the Independent Power

Producers of New York and TC Ravenswood each appealed the Management Committee

decision approving the tariff filing to the NYISO Board of Directors (“Board”).  As discussed in greater detail in Section V of this filing letter, the Board denied the appeals and directed the
NYISO to file the tariff revisions approved by the Management Committee.  The Board also
directed the NYISO to continue certain related efforts in the stakeholder process.  A copy of the Board’s decision is included with this filing, along with a copy of the dissenting opinion of
Board member Thomas F. Ryan.

IV. Description of Proposed Mitigation Measure

The proposed mitigation measure for general applicability to ROS must-run units

submitted with this filing is similar to the mitigation measure approved in the May 20 Order. The principle substantive provisions are set forth in proposed Sections 23.3.1.2.3 and

23.3.3.3.1.3 of the NYISO’s MMM.

Consistent with the mitigation measure approved in the May 20 Order, the generally

applicable measure applies only to exercises of market power by Generators that are committed
“outside the ISO’s economic evaluation process to protect NYCA or local area reliability” in the ROS area.13  Specifically, the measure applies to a Generator committed as a Day-Ahead
Reliability Unit (“DARU”) or via a Supplemental Resource Evaluation (“SRE”), or committed
as a DARU or via SRE and subsequently dispatched Out-of-Merit above its minimum generation level to protect or maintain NYCA or local reliability.14  As with the mitigation measure that was accepted in the May 20 Order, the proposed generally applicable measure requires a
determination that a Supplier is in a position to exercise market power by requiring that one of
the following three conditions be met:

 

13Attachment H § 23.3.1.2.3.
14Attachment H § 23.3.1.2.3.1.


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 6

i. the Market Party (including its Affiliates) that owns or offers the

Generator is the only Market Party that could effectively solve the

reliability need for which the Generator was committed or dispatched, or

ii. when evaluating an SRE that was issued to address a reliability need that

multiple Market Parties' Generators are capable of solving, the NYISO
only received bids from one Market Party (including its Affiliates), or

iii.when evaluating a DARU, if the Market Party was notified of the need for

the reliability of the of its Generator prior to the close of the Day-Ahead

Market.15

If a Generator meets one or more of the above three conditions, the generally applicable
measure specifies conduct thresholds for assessing the Generator’s Bid parameters relative to the
applicable reference level.  Specifically, the thresholds would apply mitigation if a Bid or Bid
component:

i.exceeded the Generator’s Minimum Generation Bid reference level by the

greater of 10% or $10/MWh, or

ii.exceeded the Generator’s Incremental Energy Bid reference level by the

greater of 10% or $10/MWh, or

iii.exceeded the Generator’s Start-Up Bid reference level by 10%, or

iv.exceeded the Generator’s minimum run time, start-up time, and minimum

down time reference levels by more than one hour in aggregate, or

v.exceeded the Generator’s minimum generation MW reference level by

more than 10%, or

vi.decreased the Generator’s maximum number of stops per day below the

Generator’s reference level by more than one stop per day, or to one stop

per day.16

The thresholds are almost identical to those approved by the May 20 Order, but with the
inclusion of a further threshold, in subsection (vi), to address the potential for the maximum
number of stops per day specified in a Generator’s Bid parameters to be manipulated to
artificially increase its guarantee payment (by extending the required commitment period) if the
Generator is in a position to exercise market power.  In addition, the threshold in subsection (iv)

 

15Attachment H § 23.3.1.2.3.2.

16Attachment H § 23.3.1.2.3.3.


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 7

would apply to start-up time and minimum down time in addition to minimum run time, for the
same reason.  Here, as with the mitigation measure approved in the May 20 Order, “imposing
[guarantee payment] mitigation when the above conduct thresholds are exceeded will,
effectively, recognize that conduct at or exceeding the threshold will always have a material
impact.”17

In a Motion for Leave to Respond, and Response filed on October 13, 2009 in Docket
No. ER09-1682, the docket for the May 20 Order, the NYISO notified the Commission of its
agreement with the use of a modified version of the timeline specified in Section 23.3.3.1 of its
MMM for consultation with any of the three specified Generators about possible legitimate
justifications for Bids that exceed the applicable must-run mitigation conduct thresholds.  In the
May 20 Order, the Commission directed the NYISO to incorporate the mitigation measure for
specific ROS must-run units, filed as Rate Schedule M-1, into Attachment H, and noted in a
footnote that: “This will also facilitate NYISO’s use of other related Attachment H provisions
such as the consultation timelines.”18  The NYISO made a filing to comply with this directive on
August 6, 2010 that incorporated the agreed consultation timeline, and stating that the “NYISO
and the three Generators that are presently subject to the mitigation measure have been using this
consultation process and timeline to implement the Rate Schedule M-1 mitigation measure for
nearly a year, and it has worked well from the NYISO’s perspective.”19  The current filing brings
forward this consultation process for the generally applicable mitigation measure.20  The
experience with the three Generators that are subject to Rate Schedule M-1 indicates that this
consultation process and timeline are appropriate for the generally applicable measure.

The remaining tariff revisions are conforming changes for the substantive provisions

described above.21  In addition, a minor numbering change is also necessary in the Market

Monitoring Plan, Attachment O to the Services Tariff, in order to incorporate the role of the

Market Monitoring Unit (“MMU”) in the implementation of the foregoing consultation

procedures.  The procedures require the NYISO to submit its preliminary determination in

response to a request for consultation from a Market Party to the MMU for review and comment,

 

17See May 20 Order at P13.

18May 20 Order at P99, n.94 (citing the NYISO’s Oct. 13, 2009 filing at 27). 19August 6, 2010 filing letter at 2.

20See proposed revisions to § 23.3.3.3.1.3 of Attachment H.

21See. e.g., §§ 23.3.3.2.2, 23.3.3.3.1.1 and 23.3.3.3.1.2 (incorporating appropriate crossreferences to make clear the applicability of the consultation procedures specified for different types of market power mitigation).


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 8

and to consider the MMU’s recommendations in reaching a final mitigation determination.

These duties of the MMU are reflected in the proposed renumbering of the cross-references in Section 30.4.6.2.7 of Attachment O.

In sum, the proposed mitigation measure would identify any ROS Generator that has

become a pivotal supplier as a result of being required for reliability, and thus possesses market power and should be subject to mitigation.  Mitigation will only be applied if such a pivotal supplier engages in bidding conduct that is substantially inconsistent with competitive conduct, as measured by proposed thresholds that are consistent with those previously approved by the Commission.  Any such Bids will necessarily have a significant impact on guarantee payments. Accordingly, the proposed measure should be accepted by the Commission for all the reasons articulated by the Commission in its May 20 Order.

V. NYISO Board Decision

As noted above, the Management Committee’s approval of the tariff revisions submitted
with this filing was appealed to the NYISO Board.  In approving the submission of this filing,
the Board directed the NYISO management to work with stakeholders in the governance process
to examine claims by Generation Owners that existing cost recovery mechanisms do not provide
an adequate opportunity for must-run units to recover their fixed costs.22  In doing so, the NYISO
Board noted that the claims of deficient compensation had not been substantiated, and that the
“Gap Solution” in Attachment Y to the NYISO’s Open Access Transmission Tariff
“contemplates that non-transmission Gap Solutions will receive ‘full and prompt recovery of all
reasonably-incurred costs . . .’ .”23  Thus, while the Board found that a need to delay this filing
has not been established, the Board took seriously the Generation Owners’ concerns about the
recovery of fixed costs by a Generator that must be run for system or local reliability.  Consistent
with the Board’s directives, the NYISO’s ongoing review of the existing Gap Solution process
with its stakeholders will continue to be an important effort going forward.

The Board also directed the NYISO management to work with stakeholders in the

governance process to “review the process by which permanent solutions to specific reliability
needs are evaluated and planned for, particularly in terms of timing and cost to consumers.”24
The Board emphasized that:  “Market signals which drive appropriate investments in generation,

 

 

 

22Board Decision at 1.

23Board Decision at 4.
24Board Decision, at 1.


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 9

transmission or demand response are the preferred outcome.”25  The Board identified a set of objectives to be achieved by NYISO management through the stakeholder process:

1. exploration of methods of improving the transparency of costs that the NYISO incurs for the regular/repeated commitment of a generator for reliability; and

2. exploration of methods of developing a market-based signal that will more accurately reflect the alternative costs of addressing regularly recurring reliability needs than permitting a generator to exercise market power, or using a mitigated offer.

Consistent with the Board’s directives, NYISO staff will address these issues in their ongoing discussions with stakeholders.

VI. Requested Effective Date

The NYISO requests an effective date of October 12, 2010, that is, 60 days from the date of this filing.

VII. Intent to Request Permission to Withdraw Existing Must-Run Mitigation Measure

Once a generally applicable mitigation measure for ROS units committed or dispatched for reliability has been accepted by the Commission, the NYISO intends to seek permission to remove from the MMM the ROS must-run mitigation measure for three specified Generators. Those Generators will instead be subject to the generally applicable measure, rendering the generator-specific measure unnecessary.

VIII. Service

The NYISO will electronically send a link to this filing to the official representative of

each of its Customers, to each participant on its stakeholder committees, to the New York Public
Service Commission, and to the electric utility regulatory agency of New Jersey.  The filing will
be posted on the NYISO’s website at www.nyiso.com.  The NYISO will also make a paper copy
available to any interested party that requests one.  To the extent necessary, the NYISO requests waiver of the requirements of Section 35.2(d) of the Commission’s Regulations to permit it to
provide service in this manner.26

 

 

 

25Board Decision at 4.

2618 C.F.R. § 35.2(d).


 

 

 

 

 

 

Kimberly D. Bose
August 13, 2010
Page 10

IX. Waiver of Cost of Service Filing Requirements

To the extent necessary, the NYISO respectfully requests that the Commission grant it waivers of the requirements of Section 35.12(b) of the Commission’s regulations27 addressing the filing of initial rate schedules and requiring the submission of certain cost-of-service
information.  The information required under Section 35.12(b) is not applicable to this filing, because it does not propose a traditional cost-of-service rate schedule.  The NYISO also requests waiver, to the extent necessary, of any other Part 35 requirements that the Commission may
deem to be applicable, but which are not addressed in this filing.28

X. Conclusion

For the reasons explained in this filing letter, the NYISO respectfully requests that the Commission accept the market power mitigation measure for ROS Generators committed or dispatched for reliability submitted with this filing.

 

 

Respectfully submitted,

/s/ William F. Young_________ William F. Young

Hunton & Williams LLP Counsel to the

New York Independent System Operator, Inc.

 

 

 

 

 

 

 

 

 

 

 

 

 

2718 C.F.R. § 35.12(b).

2818 C.F.R. Part 35.

 

 

 

 

55430.000055 EMF_US 32062188v4