Re:    Service   Agreement   No. 1160   Second   Amended   and   Restated

Interconnection Agreement Between Niagara Mohawk Power Corporation d/b/a National Grid and Sithe/Independence Power Partners, L.P.
Docket No. ER00-

Dear Secretary Bose:

Enclosed  please  find  the  Second  Amended  and  Restated  Interconnection
Agreement  between Niagara Mohawk Power Corporation d/b/a National Grid (“Niagara
Mohawk”) and Sithe/Independence Power Partners, L.P. (“Sithe) for electronic filing with
the Commission pursuant to section 205 of the Federal Power Act, 16 U.S.C.§ 824d,
and section 35 of the Commission’s Regulations, 16 C.F,R. § 35 (2010).   Pursuant to
the Commission’s Order No. 714, the Second Amended IA has been designated by the
New York Independent System Operator, Inc. (“NYISO”) as Service Agreement No.
1160  (“SA 1160”) under NYISO’s Open Access Transmission Tariff (“OATT”).

 

The SA 1160 supersedes the First Amended and Restated Interconnection Agreement between Niagara Mohawk and Sithe, which was filed with the Commission on June 21, 2001 in Docket No. EL999-65-000 and approved by the Commission as Niagara Mohawk’s Rate Schedule FERC No. 189 by order dated March 27, 2002. Niagara Mohawk Power Corporation, 98 FERC ¶ 61,316 (2002).

SA 1160 modifies the provisions of Article 12 thereof dealing with taxes.  In
particular, the provisions requiring Niagara Mohawk to compensate Sithe for certain tax
benefits were deleted, and the percentage of real property tax on the Interconnection
Facility for which Sithe is obligated to compensate Niagara Mohawk was reduced from

50 percent to 46 percent.  Niagara Mohawk respectfully requests that the Commission
accept the Second Amended IA for filing with an effective date of October 26, 2010.

 

 

 

 

 

 

1 MetroTech Center, Legal Department 14th Floor, Brooklyn, NY 11201

T: (718) 403-3320    F: (718) 403-2809 Katherine.Lovette@us.ngrid.com    www.nationalgrid.com


 

 

 

Sithe has agreed to the changes proposed in SA 1160 and to the proposed
effective date thereof.  Accordingly, the Commission should review and approve this
filing under the “just and reasonable” standard of FPA § 205.  Approval of this

submission on less than 60 days notice is appropriate under the Commission’s Central Hudson policy on filing requirements, since this change will reduce Sithe’s payments to Niagara Mohawk under this interconnection agreement.  See Central Hudson Gas & Electric Corporation, 60 FERC ¶ 61,106 (1992).

 

A copy of this filing has been served on Sithe, the New York Independent System Operator, and the New York State Department of Public Service.

If you have any questions with regard to this filing, please do not hesitate to call me at 718-403-3320.

Respectfully Submitted,
/s/ Katherine E. Lovette

Katherine E. Lovette Counsel

 

KEL:

Encl.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1 MetroTech Center, Legal Department 14th Floor, Brooklyn, NY 11201

T: (718) 403-3320    F: (718) 403-2809 Katherine.Lovette@us.ngrid.com    www.nationalgrid.com