UNITED STATES OF AMERICA
BEFORE THE

FEDERAL ENERGY REGULATORY COMMISSION

 

 

New York Independent System Operator, Inc.)Docket No. ER11-2224-000

 

REQUEST FOR REHEARING, ALTERNATIVE REQUEST FOR CLARIFICATION,
AND PARTIAL REQUEST FOR EXPEDITED ACTION

OF THE NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.

 

In accordance with Rules 212 and 713 of the Commission’s Rules of Practice and

Procedure,1 the New York Independent System Operator, Inc. (“NYISO”) hereby submits this
request for rehearing of four aspects of the Commission’s January 28, 2011 order regarding its
proposed updates to the Installed Capacity2 (“ICAP”) Demand Curves for Capability Years
2011/2012, 2012/2013, and 2013/2014 (“January Order”).3  It also seeks clarification, or in the
alternative, rehearing of two additional issues (in one case on an expedited basis.) On rehearing,
the Commission should reverse the January Order’s determinations that the NYISO must: (1)
assume that there will be no property tax abatements when establishing the New York City
(“NYC”) ICAP Demand Curve;4 (2) provide additional support for its proposed excess Capacity
levels or continue to use the excess Capacity levels that are incorporated in the currently
effective ICAP Demand Curve;5 (3) include the cost of System Deliverability Upgrades

 

 

 

1 18 C.F.R. §§ 385.212 and 713 (2010).

2 Terms with initial capitalization that are not otherwise defined herein shall have the meaning set forth in the NYISO’s Market Administration and Control Area Services Tariff (“Services Tariff”), and if not defined therein, in the NYISO’s Open Access Transmission Tariff (“OATT”).

3 New York Independent System Operator, Inc., 134 FERC ¶ 61,058 (2011) (“January Order”).

4 Id. at PP 88-90.

5 Id. at P 114. References herein to currently effective ICAP Demand Curves and similar terms mean the ICAP Demand Curves for Capability Year 2010/2011.


 

 

(“SDUs”) in the ICAP Demand Curves;6 and (4) provide additional support for its estimates of NYC System Upgrade Facility (“SUF”) costs.7  None of these determinations was based on
reasoned decision-making.  All contained legal errors including misinterpreting the requirements of the Services Tariff and holding the NYISO to an unlawfully stringent evidentiary standard. All should, therefore, be overturned.

In addition, the NYISO also requests expedited clarification of Paragraphs 122 and 129

of the January Order which directed the NYISO to use a “consistent level” of excess Capacity for
all purposes.  Specifically, the Commission should clarify that the NYISO need not alter the
level of excess used to determine Energy and Ancillary Services revenue offsets to the net cost of
new entry (“CONE”).  The Commission should confirm the determination clearly stated in the
January Order that the level of excess used for years one through three to determine those offsets
is just and reasonable.  In the alternative, if the Commission meant to require a change to the
Energy and Ancillary Services revenue offsets, then the NYISO respectfully requests rehearing
of that determination.

The NYISO also requests clarification of Paragraph 161 of the January Order, which

addresses its proposed winter/summer adjustment.  Specifically, the Commission should clarify
that the NYISO need not modify the winter/summer adjustment methodology which was
accepted by the January Order.  Instead the NYISO should apply the accepted winter/summer
adjustment methodology to the ICAP Demand Curves that are established in compliance with the
January Order’s other directives, to the extent that they are not overturned on rehearing.  In the
alternative, if the Commission meant to require a change to the winter/summer adjustment
methodology, then the NYISO respectfully requests rehearing of that determination.

 

6 Id. at P 53.

7 Id. at P 140.

 

 

2


 

 

None of these determinations was based on reasoned decision-making and all should be
overturned for the reasons specified in Sections III and IV below.  In all, it appears that the
Commission may not have fully considered that the January Order will substantially raise prices
in a market that is functioning well, that is already experiencing a “significant capacity surplus . .
..”8, and that is continuing to attract new Capacity. The Commission has previously directed the
NYISO to design Capacity market rules that “provide a level of compensation that will attract
and retain needed infrastructure and thus promote long-term reliability while neither over-
compensating nor under-compensating generators.”9  They will increase Capacity prices
substantially beyond those proposed in the November Filing.10  They also will raise prices
substantially beyond the current levels which have attracted and are continuing to attract and
retain needed Capacity.  As discussed in Section VI below, the January Order will disrupt this
balance, particularly in New York City, by raising clearing prices well above levels required to
meet the basic goals of the NYISO’s Capacity markets. On rehearing, the Commission should
carefully consider the risk that the cumulative impact of its decisions will be to inefficiently
perpetuate the current Capacity surplus, and thus distort the Capacity markets and unnecessarily
increase prices for consumers.

 

 

I.COMMUNICATIONS

Communications regarding this pleading should be addressed to:

 

 

 

 

8 January Order at P 117.

9 New York Independent. System Operator, Inc., 118 FERC ¶ 61,182 at P 17 (2007).

10 See New York Independent System Operator, Inc., Request for Leave to Answer and Answer at Affidavit of David Lawrence (“Lawrence Affidavit”), Docket No. ER11-2224-000 (filed January 6, 2011) (“January Answer”).

 

 

3


 


 

 

 

 

Robert E. Fernandez, General Counsel
Raymond Stalter, Director of Regulatory Affairs Gloria Kavanah, Senior Attorney

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144
Tel: (518) 356-6103
Fax: (518) 356-7678
rfernandez@nyiso.com
rstalter@nyiso.com

gkavanah@nyiso.com

 

 

II.BACKGROUND


 

 

 

Ted J Murphy
Vanessa A. Colón

Hunton & Williams LLP 1900 K Street, N.W.

Washington, D.C. 20006 Tel: (202) 955-1588

Fax: (202) 778-2201
tmurphy@hunton.com
vcolon@hunton.com


On November 30, 2010 the NYISO submitted a filing (the “November Filing”) to revise
the ICAP Demand Curves for Capability Years 2011/2012, 2012/2013, and 2013/2014.11
Among other things, the November Filing proposed ICAP Demand Curve values that: (1) for the
NYC Demand Curve, reflected full abatement of NYC property taxes; (2) used a level of excess
Capacity based on the NYISO’s independent assessment and evaluation, consistent with the
Services Tariff; (3) used a different excess Capacity assumption to estimate Energy and
Ancillary Services revenue offsets for years one through three; (4) did not include SDU costs in
the cost of new entry (“CONE”) for the peaking units (“peaking plant”); and (5) included the
Consultant’s12 best estimate of NYC SUF costs, with which the NYISO concurred.
The January Order accepted the NYISO’s proposed tariff changes subject to
modification, suspended them for five months, and directed the NYISO to make a compliance
filing.  The Commission rejected the NYISO’s proposals to recognize full property tax

 

 

11 New York Independent System Operator, Inc., Tariff Revisions to Implement ICAP Demand Curves for Capability Years 2011/2012, 2012/2013, and 2013/2014, Docket No. ER11-2224-000 (filed November 30, 2010) (“November Filing”).

12 National Economic Research Associates, Inc. (“NERA”), with Sargent and Lundy as subcontractor to NERA (collectively, “the Consultant”).

 

 

4


 

 

abatement in NYC and to exclude Deliverability costs.  The Commission also found that the
NYISO had not fully supported its level of excess Capacity assumption. The January Order
further: (1) directed the NYISO to address a protestor’s arguments regarding the SUF costs
incorporated in the ICAP Demand Curves proposed in the November Filing;13 (2) directed the
NYISO to use a consistent level of excess Capacity for all purposes, which was incongruous
because it also determined that the NYISO’s proposed Energy and Ancillary Services revenue
offsets were just and reasonable,14 and (3) found the NYISO’s proposed winter/summer

adjustment was just and reasonable but also, again incongruously, directed the NYISO to revise it to reflect any adjustments to the assumed level of excess Capacity.15

 

 

III.REQUEST FOR REHEARING

A.It Was Arbitrary and Capricious for the Commission to Require the NYISO

to Include NYC Property Taxes in the Cost of New Entry for the NYC Peaking Plant

The January Order concluded that “it is not just and reasonable to assume full, or in fact,
any tax abatement for the NYC LMS 100 peaking unit when granting the tax abatement is
discretionary under the UTEP and not a matter of right.... 16 The Commission stated that the

NYISO “had not shown” that property taxes “will not be incurred by peaking units that will be
constructed in New York City.”17  It also said that it was convinced by the “debate” between the

 

 

 

 

13 January Order at P 140.

14 Id. at PP 122-129.

15 Id. at P 161.

16 Id. at P 88.  The UTEP is the NYCIDA’s Third Amended and Restated Uniform Tax Exemption

Policy.

17 Id.

 

 

5


 

 

NYISO and New York City Suppliers18 that it was “unclear whether an LMS100, the peaking
unit used by the NYISO in determining the CONE for the NYC demand curve, would qualify
under the program criteria.”19 Accordingly, because of the supposedly “questionable eligibility

of a peaking unit and the fact that such abatement was discretionary.... ” the NYISO was

 

“directed to exclude tax abatement from the calculation of net CONE for NYC.”20

 

The Commission held that the NYISO may not assume any level of property tax

abatement in formulating the NYC Demand Curve because there is a chance that the actual

abatement level might be lower than 100 percent.  The Commission appears to have reached this
conclusion without giving any weight to the affidavits submitted by the government agency
responsible for administering NYC’s property tax abatement program, and without considering
the potential alternative, i.e., the adoption of a partial abatement assumption, as was proposed by
the protestors.21 The only evidence that would have supported the Commission’s determination
that no abatement should be assumed is evidence that there is no chance that a developer would
receive the abatement (or that it is highly unlikely).  No such evidence exists in the record.  In
fact, the Commission did not even find that the abatement is unlikely, only that it is unclear a
developer would receive the abatement because it is discretionary.  Hence, assuming a developer
will not receive an abatement is unreasonable based on the evidence in the record.

 

 

 

 

 

18 The New York City Suppliers are: (1) Astoria Generating Company, L.P.; NRG Power

Marketing LLC, Arthur Kill Power LLC, Astoria Gas Turbine Power LLC, Dunkirk Power LLC, Huntley Power LLC, and Oswego Harbor Power LLC (collectively “the NRG Companies”); and (3) and TC
Ravenswood, LLC.

19 January Order at P 88.

20 Id. at 90.

21 New York Independent System Operator, Inc., Protest of the New York City Suppliers at 50-53, Docket No. ER11-2224-000 (filed December 21, 2010) (“New York City Suppliers Protest”).

 

 

6


 

 

It also appears that the Commission did not adequately consider the significant negative financial impact on NYC consumers of the zero abatement assumption as it is legally required to do.  The extent of that impact is clearly illustrated by Table 1, which was included in the
November Filing22 but not addressed by the January Order.

TABLE 1 - Sensitivity Analysis, NYC Tax Abatement

 

Summer Reference Point ($/kW-mo)2011 Est. Capacity Revenue ($/kW-yr)

NYCANYCLINYCA    NYCLI

Current Demand Curve (2011$)$17.24$  117.23

with 100% tax abatement$20.35$  138.38

with 80% tax abatement$21.89$  148.85

with 70% tax abatement$22.66$  154.09

with 50% tax abatement$24.20$  164.56

no tax abatement$28.85$  196.18

Additionally, because the granting of the full tax abatement is likely (although not an absolute certainty), establishing an ICAP Demand Curve that assumes no abatement will
substantially overcompensate NYC suppliers and contravene the Commission’s own principles for establishing a just and reasonable ICAP Demand Curve.

The Commission also contravened its own policy of giving deference to state and local
governmental bodies on matters that fall within the expertise or jurisdictional prerogatives of the
respective body.  In sum, the Commission has not met its obligation to offer a “reasoned
explanation” for its tax abatement decision and has not engaged in reasoned decision-making.23

 

 

22 See  November Filing at “Proposed NYISO Installed Capacity Demand Curves for Capability
Years 2011/2012, 2012/2013 and 2013/2014 Final” at 12 (as revised October 30, 2010) (“NYISO Final
Report”). Note that the table demonstrates the magnitude of impacts.  It is based on the Consultant’s
proposed NYC Demand Curve, with the current (2010/2011) Demand Curve used for reference.

23 See, e.g., Panhandle Eastern Pipe Line Co. v. FERC, 881 F.2d 1101, 1118 (D.C. Cir. 1989)
(“The agency’s determination must reflect reasoned decision making that has adequate support in the
record and must include an ‘understandable’ agency analysis and rationale.”).  KN Energy, Inc. v. FERC,
968 F.2d 1295, 1303 (D.C. Cir. 1992) (finding that “[i]t most emphatically remains the duty of this Court
to ensure that an agency engage the arguments raised before it-that it conduct a process of reasoned
decisionmaking,” citing, American Mining Congress v. U.S. EPA, 907 F.2d 1179, 1187 (D.C. Cir. 1990)
(emphasizing that deference to an agency’s judgment does not relieve a reviewing court of its

 

7


 

 

 

 

 

1.  The Record in this Proceeding Clearly Supports the Conclusion that the
NYC Peaking Plant Would Be Eligible for, and Would Receive, a Full
Property Tax Abatement Under the New York City Industrial
Development Agency’s Established Criteria

The record in this proceeding clearly supports a finding that the NYC peaking plant that
is the basis for the NYC Demand Curve would receive a property tax abatement under the New
York City Industrial Development Agency’s (“NYCIDA’s”) UTEP.  As the Commission and the
courts repeatedly recognized, the Commission’s principal responsibility under the Federal Power
Act (“FPA”) is to protect consumers against unjust and unreasonable rates.24  The January Order
acknowledges as much, observing that “[i]n choosing a general methodology and inputs into the
demand curve model, judgments must be made, and it is the Commission’s responsibility to

determine whether these judgments and the resultant outcomes fall within a zone of

reasonableness.”25  The January Order, however, did not address, and appears to have not even

 

 

responsibility to ensure that the agency has articulated a satisfactory explanation for its action) (emphasis
in original)); Mid-Tex Electric Cooperative, Inc. v. FERC, 773 F.2d 327, 358 (D.C. Cir. 1985) (finding
that the Commission failed to offer a “reasoned basis” for its decision); Farmers Union Cent. Exchange,
Inc. v. FERC, 734 F.2d 1486, 1499 (1984 ) (finding that “[u]nder the ‘arbitrary and capricious’ standard, a
reviewing court must conduct a ‘searching and careful’ inquiry into the record in order to assure itself that
the agency has examined relevant data and articulated a reasoned explanation for its action including a
“rational connection between the facts found and the choice made” and that “[m]ost fundamentally our
task is ‘to ensure that the [agency] engaged in reasoned decision-making,” citing, Burlington Truck Lines

v. United States, 371 U.S. 156, 168 (1962); International Ladies’ Garment Workers’ Union v. Donovan,
722 F.2d 795 815 (D.C. Cir. 1983); American Gas Association v. FPC, 567 F.2d 1016, 1029-30 (D.C.
Cir. 1977)).

24 See, e.g., Pennsylvania Water & Power Co. v. FPC, 343 U.S. 414, 418 (1952) (stating that “[a]
major purpose of the . . . [FPA] is to protect power consumers against excessive prices”); NAACP v. FPC,
425 U.S. 662, 669-70 (1976) (finding that the “principal purpose [behind passage of the Federal Power
Act] was to encourage the orderly development of plentiful supplies of electricity . . . at reasonable
prices”); Williams Pipeline Co., 21 FERC ¶61,260 at p. 61,583 (1982) (explaining that the Commission’s
“essential mission” is “to protect consumers against exploitation” and that “[c]onsumer protection is what
we are here for. Of course, that function must be performed with scrupulous regard for the legitimate
claims of those we regulate. Nevertheless, it is the consumer’s interest that is paramount. The statutes on
which we spend most of our time and energy were carefully designed to close gaps in the protective fabric
that the states had previously fashioned for the consumer’s benefit. That is so clear that even lawyers have
been unable to dispute it. Thus history gives us a good light by which to steer when we deal with electric
power and with the transportation of natural gas”).

25 January Order at P 119 (internal citations omitted).

 

 

8


 

 

considered, the “resultant outcomes” that would follow its conclusion, which has no basis in the record, that property tax abatements will not be granted.

It is unjust and unreasonable to require consumers to pay rates predicated on an

assumption that the NYC Demand Curve peaking plant would receive zero property tax

abatements.  The record adequately demonstrates that such abatements would be granted.  The
record is also clear that incorporating NYC property taxes at a level of 100 percent into the
peaking unit’s CONE would substantially inflate the NYC Demand Curves.  Yet the January
Order does not address this “resultant outcome” in any way.  Instead, the Commission leapt from
its finding that a full abatement might not be granted to its conclusion that zero abatement must
be assumed without adequately considering consumer impacts.  Even if there were legitimate
doubts about the application of the UTEP, it is arbitrary, capricious, and inconsistent with
reasoned decision-making for the Commission to resolve those doubts entirely against
consumers.  Although it is not a certainty that 100 percent abatement will be granted to each
peaking plant, there is no evidence in the record suggesting that a developer would not receive an
abatement or even that the abatement would be unlikely.  The Commission’s determination could
only be deemed unreasonable in light of such evidence.  Moreover, the Commission did not
venture to provide a reasoned explanation.

a. The NYCIDA’s Rules and Economic Motivation Support
the Conclusion That It Will Grant Property Tax Abatements

The January Order’s analysis disregarded, without explanation, the rationales offered by
the NYISO and others26 that it would be irrational to assume that the NYCIDA, as an economic
development agency, would exercise its discretion in a way that would inflate NYC Capacity

 

26 See New York Independent System Operator, Inc., Request for Leave to Answer and Answer of the New York Transmission Owners at 12-17, Docket No. ER11-2224-000 (filed January 10, 2011)
(“NYTOs Answer”).

 

 

9


 

 

prices. It is readily foreseeable that doing so would harm economic development and contravene
both the stated public policy goals of the UTEP and NYC, and the NYCIDA’s statutory purpose.
The City of New York’s (“City”) Comments, noted that “the role of the NYCIDA is to actively
foster and facilitate economic development and job growth retention in New York City” and that
it achieves this objective by granting property tax abatements and providing other incentives.27
The City stated that the NYCIDA’s “core purpose” is economic development, particularly

through job creation and retention, and “there can be no question that the construction and

 

operation of a new generating facility will accomplish this important purpose.”28               Further, the

City has no incentive to unreasonably deny property tax abatement, as “the impact on NYC

Locality electricity consumers related to the exclusion of the tax abatement benefits is massive, equating to potentially hundreds of millions of dollars annually.”29

Even the New York City Suppliers, who objected to full abatement, acknowledged a

likelihood that the NYC peaking plant would receive a significant abatement of property taxes.30
Two affidavits submitted by the City in this proceeding establish that the NYCIDA has a
statutory mandate to promote economic development and job retention and creation, and that
granting tax abatements to new generators would serve these objectives.31  The January Order
acknowledged that the UTEP was recently revised for the express purpose of “induc[ing] the

 

27 New York Independent System Operator Inc., Motion to Intervene Protest and Comments of the City of New York at 16 (filed December 21, 2010) (“City of New York Comments”).

28 Id. at 17.

29 Id. at 18, n. 34.

30 New York City Suppliers’ Protest at 46-47, 51-52; New York Independent System Operator, Inc., Answer to Motion, Motion for Leave to Answer and Limited Answer of the New York City
Suppliers at 7-8 (filed January 14, 2011) (“New York City Suppliers Answer”).

31 City of New York Comments at Affidavit of Maureen Babis (“Babis Affidavit”) filed

December 21, 2010); New York Independent System Operator, Inc., Request for Leave to Answer and Answer of the City of New York at Response Affidavit of Maureen Babis (“Basis Response”) filed January 5, 2011 (“City of New York Answer”).

 

 

10


 

 

installation of peaking units in NYC.”32  The City noted that “inasmuch as the NYCIDA Board adopted a tax abatement program specifically designed for new peaking generating units, it is reasonable to presume that the NYCIDA Board will consider applications for assistance under that program in a manner that is consistent with its statutory mission              33

The City further explained that given the plain language of the UTEP, it was reasonable
to expect that the peaking plant would most likely be granted full tax abatement.34 While new

LMS100 peaking units are not entitled to tax abatements as a matter of right, the NYCIDA
testified that its discretion was constrained by the UTEP and that it was reasonable to assume that denials would be unusual.35  The City also described that New York State law applicable to all Industrial Development Agencies, including the NYCIDA, requires that it have a policy that delineates how and when it could deviate from its policy.36  The UTEP provides those guidelines and prevents the NYCIDA from arbitrarily denying a request for abatement.37

b.The NYC Peaking Plant Will Meet the UTEP’s Criteria to

Qualify for Property Tax Abatement

The City demonstrated that there was no merit to the New York City Suppliers’ claims
that the peaking plant would not be eligible for an abatement under the UTEP and submitted

 

 

 

32 January Order at P 65.

33 Babis Affidavit at P 12.

34 Babis Response at PP 8, 14.

35 City of New York Answer at 17-18.

36 See Babis Affidavit at 11 (“Section 874(a) of the New York General Municipal Law requires each industrial development agency to establish a uniform tax exemption policy, and Section 874(b)
requires each agency to ‘. . . establish a procedure for deviation from the uniform tax exemption policy required pursuant to this subdivision.  The agency shall set forth in writing the reasons for deviation from such policy, and shall further notify the affected local taxing jurisdictions of the proposed deviation from such policy and the reasons therefor.’  In accordance with this statutory requirement, Section III of the UTEP lays out the NYCIDA’s deviation policy.)

37 See id.

 

 

11


 

 

evidence that discredited the New York City Suppliers’ witness, Mr. David Perri on this issue.38
The City stated that it developed the UTEP criteria after consulting with Mr. Perri regarding the
expected operating characteristics of an LMS100 unit in NYC and that Mr. Perri provided the
City with information that provided the basis for the criteria in the UTEP.39  Inexplicably, the
information on the LMS100’s heat rates and parasitic load information provided to the City by
Mr. Perri was different from the heat rate and parasitic load information that was later included
in Mr. Perri’s affidavit on behalf of the New York City Suppliers.40 That affidavit was intended

to cast doubt on whether an LMS100 unit would qualify under the UTEP criteria.

The NYISO also submitted an affidavit by its Demand Curve Consultant which explained
that the LMS100 unit would satisfy the second of the UTEP’s two objective criteria, and thus be
eligible for abatement.41 As explained in the Ungate Affidavit, the UTEP criteria require that

“the proposed Peaking Unit will have a full-load heat rate not exceeding either (aa) 7,850

 

btuLHV/kwh … as measured at generator terminals, or (bb) 8,250 btuLHV/kwh (9,150

btuHHV/kwh) as measured net of parasitic load.”42  If the parasitic losses for the LMS100 unit are properly estimated, as provided in the Ungate Affidavit, the heat rate for the peaking plant meets the (bb) requirement, and the auxiliary power would have to increase “to approximately 4,240 kW before the section (bb) heat rate requirement cannot be met.”43

 

 

 

 

 

 

38 City of New York Answer at 12-14 and Exhibit A.

39 Id. at 12-13.

40 Id. at 13.

41 January Answer at Affidavit of Christopher D. Ungate at PP 7-11 (“Ungate Affidavit”).

42 UTEP Art 1(e)(ii).

43 See also January Answer at Ungate Affidavit at P 10.

 

 

12


 

 

 

 

 

The January Order did not accord appropriate weight to this evidence44 and instead

reached the erroneous conclusion that NYCIDA’s discretion to deny tax abatements meant that the NYISO should assume that zero abatement would be granted.  It did so despite the fact that the New York City Suppliers conceded that significant levels of partial abatements - in the range of an abatement of 89 to 94 percent of property taxes -- were likely.45

 

 

2. The Commission Failed to Afford Proper Deference to the Expertise

and Jurisdictional Prerogatives of Local Government Agencies by Disregarding the NYCIDA’s Testimony

The January Order directly contravenes the Commission’s normal policy of deference to the expertise and jurisdictional prerogatives of State and local government bodies.46 The

Commission has previously noted that it is not its “intent to interfere with state programs that

 

 

 

 

44 The January Order only acknowledged the City’s pleadings in passing and only with respect to the question of whether the ICAP Demand Curve CONE Plant would meet the UTEP criteria.  See
January Order at P 70.

45 See New York City Suppliers’ Protest at 46-47, 51-52, New York City Suppliers’ Answer at 7-

8.

46 See, e.g., City of Vernon, California, 111 FERC ¶61,092 at P 39 (2005) (“Of course, the

Commission respects state and local regulatory authorities and makes every effort not to intrude on their
jurisdiction.”);  Entergy Services, Inc., 120 FERC ¶61,020 at P 29 (2007) (“the Commission has found
that where there is a strong local interest it may give deference to a state commission on a matter subject
to the Commission's jurisdiction.”)  See also New York Independent System Operator, Inc., 109 FERC
¶ 61,372 at PP 18-19 (2004) (stating that the Commission’s “goal” in transmission planning is to
“appropriately recognize the respective state-federal authorities over transmission matters” and accepting
a NYISO proposal that afforded the New York Public Service Commission a large role in the
transmission planning process for New York state); Consolidated Edison Co. of New York, Inc., 15 FERC
¶ 61,174 at p. 61,405 (1981) (deferring to the New York Public Service Commission with respect to
certain rates for Consolidated Edison Company’s delivery services to the New York Power Authority
which the Commission found presented “unusual circumstances which create strong local interest”);
Consolidated Edison Co. of New York, Inc., Letter Order, Docket No. ER11-1961-000 (continuing the
practice of deferring to the New York Public Service Commission with respect to certain rates).
Deference in this context does not mean that the Commission should cede responsibility for the justness
and reasonableness of Capacity prices to the NYCIDA but certainly means, at a minimum, that it should
attach significant weight to the NYCIDA’s sworn statements.

 

 

13


 

 

further specific legitimate policy goals.”47  Rather than showing an appropriate level of regard
for the NYCIDA’s testimony that an LMS100 unit would be eligible for, and would be granted,
full abatement, the Commission arbitrarily determined that the NYCIDA would grant zero
abatements merely because it was possible that it might deny them.  Further, the Commission
should not have given Mr. Perri’s or the New York City Suppliers’ speculation the same weight
as the NYCIDA’s and the City’s statements supporting full abatements.
It also is not reasoned decision-making for the Commission to base a conclusion of zero abatement on a party’s disagreement with the NYISO and the NYCIDA, which the Commission characterizes as a “debate” regarding the eligibility of the LMS100 unit under the UTEP.48  The Consultant’s Report,49 the Consultant’s Affidavit, and the City’s pleadings including affidavits, fully support a finding that the peaking plant would qualify for full tax abatement under the
UTEP.  The New York City Suppliers relied on Mr. Perri’s affidavit to argue that it would not be
eligible but it was unreasonable for the Commission to rely on it after the City demonstrated that
Mr. Perri had recently contradicted himself on the very point at issue.

The New York City Suppliers did not argue that every LMS100 unit would fail to

 

qualify.  The Perri Affidavit only provided an example of how one particular unit, USPG’s South

 

 

 

 

 

 

 

 

47 New York Independent System Operator, Inc., 131 FERC ¶61,170 at P 137 (2010).

48 January Order at P 88.

49 See November Filing at Independent Study to Establish Parameters of the ICAP Demand Curve for the New York Independent System Operator at 73 (September 3, 2010, as revised September 7, 2010 and November 15, 2010) (stating that “[t]he EDC policy statement appears to indicate an inclination to provide the above-described abatement to the peaking unit that will be used in the Demand Curve reset”) (“NERA/S&L Report”); see also January Answer at Ungate Affidavit at PP 7-11.

 

 

14


 

 

Pier Project, and perhaps other projects with the same characteristics as the USPG project, might not qualify.50

As noted above, Mr. Perri apparently provided inconsistent information on heat rates and parasitic load information for an LMS100 unit.  In an email sent to the City in response to the City’s request for information regarding the LMS100, Mr. Perri provided heat rates and parasitic load information that were lower than the information submitted in his affidavit.51 The

discrepancies in the information provided by Mr. Perri demonstrate that it is not reasonable to rely on his statements. Further, even if the information provided by Mr. Perri in this proceeding were accurate, the Commission should not rely on his data because they were introduced after the completion of the Consultant’s Report and stakeholder process, and after the submittal of the November Filing.  The only reasonable conclusion, based on the evidence provided in the
Consultant’s Report, the Consultant’s affidavit (the Ungate Affidavit), and the City’s pleadings including the NYCIDA’s affidavits, is that new peaking plants in NYC would generally be
expected to qualify for full property tax abatement.

Even if there was room for doubt as to the treatment of the USPG’s South Pier Project
unique characteristics and configuration, such doubts would be irrelevant because the ICAP
Demand Curves are to be established based on the treatment to be afforded the Demand Curve
peaking plant.  The New York City Suppliers’ focus on the particular circumstances of an
individual unit, instead of the characteristics of the hypothetical peaking plant is contrary to the
Services Tariff.  It amounts to a collateral attack on earlier Commission rulings approving the
use of the peaking plant to set the ICAP Demand Curves.  To the extent that the Commission

 

50 See New York City Suppliers Protest at Perri Affidavit at P 9 (stating that he “reviewed the

UTEP to determine whether the SPIP would meet the objective criteria”) and P 10 (stating that “the SPIP
will not meet either of these UTEP expressly designated ‘objective’ heat rate criteria) (emphasis added).

51 City of New York Answer at 13, Affidavit of Thomas Simpson at PP 7-8 and Exhibit A.

 

 

15


 

 

relied on such evidence, it impermissibly departed without a reasoned explanation from its own precedent and from its own finding in the January Order that the hypothetical LMS100 plant should be used to set the NYC Demand Curve.

 

 

3. Even if There Were A Reasoned Basis for Finding That the Record

Was Unclear, the January Order Should Have Explored Other Options for Resolving any Uncertainties

Even if there were a basis to conclude that the record was unclear as to whether the NYC
Demand Curve peaking plant would be eligible under the UTEP for property tax abatement, the
Commission should not have simply rejected the November Filing’s proposal and taken an
opposite position, i.e., compelling the NYISO to assume zero abatement.  The January Order
does not, and given the record, could not reasonably, hold that the protestors had established that
the peaking plant would not be eligible for abatement.  If the Commission had a view that the
record was not clear, the most that it could have reasonably concluded was that neither the
NYISO’s nor the protestors’ position had been established.  When facing similar circumstances
with respect to excess Capacity levels,52 the Commission directed the NYISO to make a
compliance filing providing support for a reasonable level of excess Capacity.  The Commission
should have made a similar ruling regarding the peaking plant’s eligibility.
Even if there was a reasoned basis to conclude that the peaking plant would receive an abatement lower than 100 percent, and that the reasonably anticipated percentage could not be discerned from the record, the January Order’s resolution of the issue was unreasonable.  At a minimum, the Commission should have provided an opportunity for the NYISO to further justify the November Filing’s full tax abatement assumption for the reasons specified above.  If the

 

52 The NYISO is seeking rehearing of the Commission’s determinations concerning the

November Filing’s excess Capacity level proposals for the reasons specified in Section IV.A below.

 

 

16


 

 

 

 

 

evidence proffered in the record left questions unanswered, it was unreasonable for the

Commission not to seek additional input on tax abatement questions.  To the extent that the

 

Commission believed that a genuine dispute over an issue of material fact existed, it should

have53 set the matter for a paper hearing, convened a technical conference, or taken some other
step to resolve the factual dispute.  None of these potential alternative approaches would have
delayed establishing new Demand Curves beyond the period contemplated by the January Order.

Finally, by requiring the NYISO to simply assume zero abatements, based on doubts over
eligibility and a purportedly unclear record, the Commission will impose disproportionate
financial impacts on consumers and unreasonably disrupt the balance between Capacity sellers
and consumers that the ICAP Demand Curves should reflect.  Moreover, the desired balance
between “under compensating” and “overcompensating” suppliers will be skewed in a manner
that is likely to perpetuate a NYC Capacity market with an inefficient level of excess supply.

 

 

4. A Finding of Zero Abatement Is Not Supported by the Record, and

Will Result in Rates That Are Not Just and Reasonable

 

Contrary to the Commission’s conclusion, even the New York City Suppliers

acknowledged54 that it would be reasonable for the ICAP Demand Curves to assume that at least
some percentage of abatements would be granted.  It is significant that even they do not view the
abatement issue as an “all-or-nothing” proposition.  Indeed, the New York City Suppliers’

 

53 See, e.g., Cajun Electric Power Co-op v. FERC, 28 F.3d 173, 180 (D.C. Cir. 1994) (remanding a decision because the Commission failed to conduct an evidentiary hearing where a genuine issue of material fact existed); Louisiana Public Service Commission v. FERC, 184 F.3d 892, 895 (D.C. Cir 1999) (stating that “[i]n general, the Commission must hold an evidentiary hearing whenever a complainant raises a genuine issue of fact that is material to the justness and reasonableness of a rate and cannot be resolved upon the written record”); El Paso Electric Co. v. FERC, 201 F.3d 667, 672 (5th Cir. 2000)
(finding that where evidence was raised that could “create a genuine issue of material fact” the
Commission should engage in more than “summary proceedings”).

54 New York City Suppliers Protest at 50-53; New York City Suppliers Answer at 7-8.

 

 

17


 

 

demonstrated that the record of industrial development agencies in other parts of New York State
provided an evidentiary basis to “include a percentage of [property tax] costs reflective of the
likelihood that abatement will be granted.”55 They stated that the information they provided

“equates to an assumed property tax abatement approximately 89-94 percent.”56  Accordingly, if the Commission is uncertain regarding what would be an appropriate level of abatement and is unable to determine an appropriate percentage, the evidentiary record supports a range of
abatement of 89 to 100 percent.

As with the myriad of other uncertainties that can affect the profitability of investments,
one must determine an “expected value” associated with the uncertain factor that takes into
account the probabilities of the different outcomes.  Because the evidence in this case supports a
high probability of abatement, the abatement assumption can only be reasonable if it likewise
assumes a high probability of abatement as there is no credible information in the record
supporting a zero probability of abatement.  Even utilizing the NYC Suppliers’ proposed level
of abatement57 would be more reasonable and fairer to consumers than assuming zero abatement.

 

 

5.  The January Order Unlawfully Required the NYISO to Prove With
Absolute Certainty That Abatements Would Be Granted When the
Federal Power Act Only Requires a Showing That it Was Just and
Reasonable to Expect They Would Be Granted

Finally, the January Order effectively imposed an unlawfully high burden of proof on the
NYISO.  Commission and judicial precedents are clear that proposed rates need only be “just and

 

 

 

 

55 Id. At 51-52.

56 New York City Suppliers Answer at 7-8.

57 See New York City Suppliers at Protest at 46-47, 51-52; New York City Suppliers Answer at 7-

8 .

 

 

18


 

 

reasonable.”58               The November Filing made a reasonable assumption that the NYCIDA would
grant tax abatements in accordance with the NYCIDA’s own representations and its statutory
mandate, which was consistent with the City’s stated larger economic interests.  The
Commission rejected the NYISO’s assumption because it did not prove with absolute certainty
that 100 percent of the abatements would always be granted.  That standard is more than the “just
and reasonable” showing required under the FPA and thus does not reflect reasoned decision-
making.

 

 

B. The November Filing’s Proposed Levels of Excess Capacity Were Fully

Supported, Would Have Resulted in Just and Reasonable Rates, and Should Have Been Accepted by the Commission

In setting the ICAP Demand Curves, the NYISO must avoid the extremes of under-

compensating or over-compensating suppliers.  Finding the balance between over- and under-

compensation will send appropriate economic price signals.  It also will strike a balance between Capacity suppliers and consumers.  ICAP revenues must be adequate to attract and retain
sufficient Capacity to satisfy statewide and local reliability requirements, while imposing a just and reasonable cost on consumers. Both the NYISO’s and the MMU’s proposed levels of excess Capacity reasonably avoided these extremes and are thus consistent with Commission precedent. Much higher levels of excess Capacity would impose an undue financial burden on buyers and perpetuate a Capacity market with an inefficient level of excess supply.  Alternatively, the
MMU’s proposal provides a reasonable middle ground.

 

 

58 Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984) (finding that “[t]he Federal

Power Act requires that all rates charged by public utilities be ‘just and reasonable.’  In the past FERC has interpreted is authority to review rates under this provision of the Act as limited to an inquiry into whether the rates proposed by a utility are reasonable - and not to extend to determining whether a proposed rate schedule is more or less reasonable than alternative rate designs”).

 

 

19


 

 

Continuing the assumption of 400 MW excess in the current NYC Demand Curve would
perpetuate a market that is already long and also would not strike a balance between suppliers
and consumer because it would impose excessive costs on consumers.  Moreover, it would
constrain the NYISO to continue its prior assumptions despite changed economic conditions.
The January Order mistakenly found that the NYISO’s “proposed excess capacity
adjustments are unsupported, and therefore cannot be found to be just and reasonable.”59  At the
same time, it rejected as unsupported variations on the November Filing’s proposal that were
proffered by the MMU.  The Commission directed the NYISO to either adopt the levels of
excess Capacity that were used in the last reset proceeding or “propose to use a new level of
excess capacity” in its compliance filing based on what the Commission deems to be adequate
support.

The NYISO welcomes the opportunity to provide additional support for excess Capacity levels that avoid the extremes of under- and over-compensation. The NYISO will include that support in its compliance filing.  Nevertheless, the Commission should  have accepted the
November Filing’s proposal on this issue as filed.  Alternatively, the MMU’s proposal provides a reasonable middle ground and should be adopted.

 

 

1.  The NYISO’s and the MMU’s Proposed Excess Capacity Levels Were
Based on Reasoned Judgments and Were Consistent with the Services
Tariff

To establish the ICAP Demand Curves, the peaking plant’s cost of new entry is offset by
Energy and Ancillary Services revenues.60  A component in determining those revenues is the

 

 

59 January Order at P 114.

60 As discussed in Section IV.A. below, for the three-year period covered by this Demand Curve update, the NYISO used as it has in previous resets, a Capacity level of 100.5 percent of the target

 

20


 

 

assumed level of average excess Capacity.  The assumed level of excess Capacity reflects the
expectation that Capacity levels in the NYCA will not be allowed to fall below the minimum
required amount and thus that there will always be some level of excess.61  The excess Capacity
level affects both projected Energy and Ancillary Services revenues and the projected Capacity
revenues realizable in the ICAP Spot market.  Assuming a higher level of average excess
Capacity will result in a higher net CONE, since it will decrease the revenues that offset the cost
of entry.  Conversely, assuming a lower level of excess Capacity would result in a lower net
CONE.  Setting the excess Capacity level at an unreasonably low or unreasonably high level
would therefore contravene the Commission’s policy that Capacity markets should neither
under- nor over-compensate suppliers.

As the Commission stated, the Services Tariff instructs that the NYISO’s  periodic

review of the ICAP Demand Curves include an assessment of its excess Capacity assumption, so
that the CONE is adjusted “in recognition that likely actual capacity revenues will be below
those modeled at equilibrium due to expected excess capacity in the New York market.”62  The
Commission has previously affirmed that the Services Tariff dictates that the excess Capacity
level should be calculated as if Capacity were at, or slightly above, equilibrium (i.e., the Installed
Reserve Margin).  The Services Tariff specifies that the Capacity level should “equal or slightly
exceed the minimum Installed Capacity requirement.”63  The relevant language of the Services

 

 

 

Installed Capacity level for computing Energy and Ancillary Services revenues.  That level comports with the Services Tariff, which states that Energy and Ancillary Services are to be determined “under
conditions in which the available Capacity would equal or slightly exceed the minimum Installed
Capacity requirement.”  Services Tariff Section 5.14.1.2.

61 See November Filing at Affidavit of Dr. David B. Patton at PP 25-26 (“Patton Affidavit”).

62 January Order at P 115.

63 Services Tariff Section 5.14.1.2.

 

 

21


 

 

Tariff has not changed since the Commission made that ruling. The NYISO has satisfied that requirement.64

By requiring a review of the level of excess as part of the Demand Curve reset, the

Services Tariff expressly contemplates that the NYISO’s excess Capacity assumptions may be revised from one triennial review to another. Therefore, the assertion by some parties65 that revising the level of excess is a “regulatory surprise” is, quite simply, a canard.

The January Order recognized that setting a reasonable excess Capacity level necessarily
involves judgment.66  The reasoned judgment of the NYISO and the MMU was that excess
Capacity levels should be determined based on the size of the respective peaking plants.  The
NYISO’s best judgment was that the levels for this triennial reset should equal one-half the size
of the peaking plant: 98 MW for NYC and Long Island and 207 MW for the NYCA.67

 

 

2.  The NYISO’s Proposed Excess Capacity Levels Were Fully Supported

The January Order held that the NYISO had “not adequately supported the use of a

hypothetical peaking unit, rather than the use of a combined cycle unit, or the use of forecasted
actual capacity additions, in computing the average excess capacity adjustment in this reset.”68

 

 

64 See Second DCR Order at P 31 (“The Commission agrees that some small level of expected

capacity over the minimum requirement is appropriate.”) and n. 21 (“In an April 21, 2005 order accepting NYISO’s previous ICAP Demand Curve parameters, the Commission accepted NYISO’s proposal to determine the parameters based on energy and ancillary service revenue estimates that would arise when supply conditions are near, but slightly higher than, the minimum capacity requirement.  The reason was to create incentives for capacity investment not to fall below the minimum requirement”).

65 See New York Independent System Operator, Inc., Motion to Intervene and Protest of

Independent Power Producers of New York, Inc. at 25, Docket No. ER11-2224-000 (filed December 21, 2010) (“IPPNY Protest”)

66 January Order at P 119.

67 November Filing, at NYISO Final Report at 13.

68 Id. at P 121.

 

 

22


 

 

The Commission allowed that “it may be true that a peaking unit would be the efficient addition
to maintain reliability, and that the use of a peaking unit to compute average excess capacity
would appear consistent with the proxy unit specified in the tariff for determining the net CONE
. . . .”69 Nevertheless, the Commission declined to accept the proposed use of the peaking plant.
Among other things, the Commission expressed concern that “[i]nstead of accounting for the
consistent reliability signals in New York State and the lumpy nature of capacity additions, as
NYISO did in the previous reset,  NYISO assumes that the timing of entry could reasonably
coincide with the time at which excess capacity is anticipated to fall to zero.” 70 The January

Order acknowledged that the NYISO offered a coherent rationale for proposing to use the

peaking plant to determine excess Capacity levels; namely, that it would be more consistent with other parameters used to establish the ICAP Demand Curves.71  This reasoning was supported by a number of parties, including the New York Transmission Owners (“NYTOs”).72

The NYISO fully justified using the peaking plant rather than a larger combined cycle
unit. The NYISO proposed using the respective peaking plants based on its judgment that they
appropriately reflected the size of an efficient addition to maintain reliability. This judgment
was consistent with the MMU’s reasoning. The Commission’s concern that the NYISO did not
properly account for the consistency of reliability signals or the “lumpiness” of Capacity
additions is misplaced.  Using a combined cycle unit would have introduced more lumpiness

 

 

69 Id.

70 January Order at P 120 (internal citations omitted).

71 January Answer at 26.

72 The New York Transmission Owners are Central Hudson Gas & Electric Corporation,

Consolidated Company of New York, Inc., Long Island Power Authority, New York Power Authority, New York State Electric & Gas Corporation, Niagara Mohawk Power Corporation d/b/a National Gird, Orange and Rockland Utilities, Inc., and Rochester Gas and Electric Corporation; see NYTOs Answer at 9-12; City of New York Answer at 22-27.

 

 

23


 

 

than was warranted because such a unit would be larger than the most efficient addition.  Using the peaking plant instead of a combined cycle plant was also consistent with the reality that there is now and is expected to continue to be a significant Capacity surplus in New York State.  It was reasonable for the NYISO to consider that the higher excess Capacity levels used in the previous ICAP Demand Curve73 reset may have contributed to that excess.

The Commission cannot reasonably ignore that correlation in its own analysis and erred when it characterized the NYISO’s consideration of that possibility as an unjustified
“abandonment” of prior assumptions. A higher excess capacity assumption will increase the
incentive to invest in new resources and can move the market away from a long-run equilibrium that is slightly in excess of the minimum requirement.  The fact is that the ICAP Demand Curves may violate the Commission’s principles if they produce revenues that over-compensate
suppliers, and also a substantial capacity surplus will be created or exacerbated by excess
investment.  Accordingly, it is very important to determine whether the excess Capacity
assumption is too high and may, therefore, perpetuate a Capacity surplus that generates
unnecessary costs for consumers.  It seems from the January Order that the Commission ignored that possibility which is not reasoned decision-making.

Even if the potential rationale for basing excess Capacity levels in this ICAP Demand

 

Curve reset on a combined cycle unit had been as strong (which it was not) as the NYISO’s

rationale for basing it on the peaking plants, the NYISO’s approach was more consistent with the
Commission’s mandate that the ICAP Demand Curves not inefficiently over-compensate
suppliers.  In contrast, the Commission’s proposal to continue using the current level of excess

 

 

 

73 New York Independent System Operator, Inc., 122 FERC ¶ 61,064 at PP 31-34 (2008)) (“Second DCR Order”).

 

 

24


 

 

may cause new Capacity to enter solely because the ICAP Demand Curves are set too high, rather than based upon a need for new Capacity.

Parties may argue, and have asserted during the reset process, that a combined cycle unit
may enter because it might have lower costs than other technologies, or that an LMS100 peaking
unit may enter because it can be sited more quickly.  The NYISO’s Interconnection Queue
demonstrates that diverse technologies have entered, and are proposed to enter the market during
a period of downward pressure on load forecasts and continued high levels of excess Capacity.
The November Filing and the supporting Lawrence Affidavit provide a reasoned basis for the NYISO’s proposal regarding the timing of entry.  The resulting proposed levels comport with the requirements of the Services Tariff: the levels equal or slightly exceeds the minimum
Installed Capacity requirement.74 At a minimum, the Commission should recognize that it was

just and reasonable to use the peaking units to determine the level of excess, for the reasons offered by the NYISO and the MMU.

The NYISO also explained that its proposal was feasible and not “unrealistic”.  The

NYISO assumed that signals for new entry would be provided before the level of excess dropped
to the equilibrium point; but that the timing of that entry could coincide with the time at which
the excess was anticipated to fall to zero.75 The addition of the new entry peaking unit would

bring the level of excess equal to the MW of the peaking plant; i.e., 195 MW for NYC and Long Island.  The NYISO also used the peaking plant to establish the proposed level of excess for the NYCA.  The NYCA peaking plant, a 7FA is 413 MW; and applying the same rationale would result in 207 MW or a level of excess of 0.6 percent.

 

 

 

74 See November Filing at 17-19 and Affidavit of David Lawrence at PP 8-11.

75 Id. at Initial Lawrence Affidavit at PP 3-4 and NYISO Final Report at 13.

 

 

25


 

 

The NYISO explained that it “was unrealistic to assume that, over time, an average level
of excess below 1% is reasonable. Therefore, the NYISO recommend[ed] that the level of
excess in NYCA be modeled at 1%.”76  As the excess is absorbed by load growth, the cycle
would repeat, resulting in an average level of excess of 0.5 multiplied by the size of the relevant
peaking plant.  The possibility that these conditions might not occur in the market is not pertinent
because the Services Tariff requires only that the ICAP Demand Curves incorporate a level of
excess Capacity that would “equal or slightly exceed” the minimum Installed Capacity
requirement.  Objections on the ground that the NYISO erroneously assumed “that the timing of
entry could reasonably coincide with the time at which excess capacity is anticipated to fall to
zero” thus misapprehend the nature of the excess Capacity level setting exercise.
The Commission unreasonably gave short shrift to the NYISO’s reasoning and simply declared that “adequate support” had not been provided.  The Commission did not offer a
reasoned explanation of why the level of support provided in the November Filing was deficient.
Yet the support provided in the November Filing was comparable to what the NYISO provided
in the prior reset to support the Commission-approved level of excess Capacity.77
As the NYISO explained,78 its 2007 proposal had also used assumptions that differed from the Consultant’s and were justified principally based on sensitivity analyses.  The
supportive information in the 2007 filing was similar to that included in the November Filing.

 

 

 

76 Id.

77 See New York Independent System Operator, Inc., Tariff Revisions to Implement Revised

ICAP Demand Curves for Capability Years 2008/2009, 2009/2010 and 2010/2011 at 12-16, Docket No. ER08-283-000 (filed November 30, 2007) and at Affidavit of David Lawrence at PP 6-10.

78 See January Answer at 5 and n. 18 (citing Second DCR Order at  PP 26, 31, 60-61 (2008)

(accepting NYISO modifications to excess Capacity level estimates recommended by NERA based on an analysis by Mr. David Lawrence and accepting the NYISO’s judgment not to include an additional risk factor that NERA had recommended).

 

 

26


 

 

Specifically, the following table, which was included in the November Filing,79 illustrates the impact of different excess Capacity assumptions.

Table 2 - Sensitivity Analysis, Levels of Excess Capacity Modeled


 

 

 

Current Demand Curve (2011$)

1.5*MW peaking unit

1.0*MW peaking unit
NYISO recommendation*
@100.5% of equilibrium


Summer Reference Point ($/kW-mo)2011 Est. Capacity Revenue ($/kW-yr)

NYCANYCLINYCA    NYCLI

$10.67$17.24$9.37$26.14$  117.23$26.14

$9.38$20.35$11.08$22.98$  138.38$23.19

$8.86$18.43$8.36$21.71$  125.32$21.71

$8.86$16.91$6.31$ 21.71$  114.99$ 21.71
$ 8.39 $ 15.99 $ 4.88 $ 20.56 $  108.73 $ 21.71


*NYISO recommended excess: NYCA: 1%; NYC: 1.1%; Long Island: 2.1%
Current Demand Curve excess: NYCA: 1.5%; NYC: 4%; Long Island: 4%

 

In addition, the January Order did not explain why it was imposing a higher burden of

proof and requiring considerably more support for the expected level of Capacity estimate in this
ICAP Demand Curve reset than it did in the 2008 Demand Curve reset order.  Despite a
sufficient level of support in the record, the Commission erroneously concluded that the NYISO
had simply stated its “beliefs.”80 The Commission’s decision on this issue simply does not

reflect reasoned decision-making.  On rehearing, the Commission should accept the NYISO’s proposed level of excess.

 

 

3.  The January Order Applied an Impermissibly Stringent Burden of Proof
to the NYISO’s Excess Capacity Level Proposals

Commission precedent is clear that multiple alternative proposals can simultaneously be
just and reasonable without diminishing the justness and reasonableness of others.81 The January

 

 

79 November Filing at NYISO Final Report at 14.

80 January Order at P 122.

81  PJM Interconnection, LLC, 119 FERC ¶ 61,063 at P 41 (2007) (stating that “on the same set of facts there can be ‘multiple just and reasonable rate designs’”); California Independent System Operator Corporation, 119 FERC ¶ 61,076 at P 14 (2007) (stating that “there can be more than just and reasonable proposal, and the proposal under consideration will be selected unless it is found unjust and

 

27


 

 

 

 

 

Order, however, stated that “[i]n the instant reset, NYISO abandons positions it held in the

previous reset without support for its new positions.”  It also held that the NYISO had not shown
why the peaking unit “would more likely cause excess capacity conditions than either a
combined cycle unit or a combination of generation that is expected to enter the market.”82
Such showings are not required by the terms of the tariff.  The NYISO must only
demonstrate that its proposal is just and reasonable.  The January Order thus impermissibly holds
the NYISO to a higher standard than that in the Federal Power Act (“FPA”).  The NYISO need
only show that its proposed excess Capacity level is just and reasonable.  The Commission,
however, required the NYISO to prove that its proposal was superior to what was accepted in
earlier orders.

Nothing in the Services Tariff supports this departure from the burden of proof required under the FPA.  The Services Tariff does not require a special showing to justify changing the assumptions used in prior ICAP Demand Curve resets.  To the contrary, the periodic review requirement, along with multiple Commission holdings (including in the January Order itself) allowing the NYISO to adjust Demand Curve parameters, belie the notion that assumptions should not be altered in the triennial review process.

The Commission’s suggestion that the NYISO’s proposed level of excess for each

 

Demand Curve is unsupported because the NYISO “abandoned” past positions without a special

 

 

 

unreasonable”); Midwest Independent Transmission System Operator, Inc., 117 FERC ¶ 61,241 at P 62 (2006) (stating that “[u]nder the FPA, if we find that the Midwest ISO has successfully supported the
justness and reasonableness of its proposal, we must approve it even if there are other just and reasonable ways…”); Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (D.C. Cir. 1984) (finding that “[t]he Federal Power Act requires that all rates charged by public utilities be ‘just and reasonable.’  In the past FERC has interpreted is authority to review rates under this provision of the Act as limited to an inquiry into whether the rates proposed by a utility are reasonable - and not to extend to determining whether a proposed rate schedule is more or less reasonable than alternative rate designs”).

82 January Order at P 121.

 

 

28


 

 

explanation is thus both unreasonable and unlawful.  The Commission’s inquiry should be limited to whether the NYISO’s current proposal is “just and reasonable.”

 

 

4.  If the Commission Refuses to Accept the NYISO’s Proposal on

Rehearing, it Should Accept the MMU’s Proposal as it is Adequately Supported

The January Order attempts to distinguish the NYISO’s 2007 ICAP Demand Curve reset
proposal from the November Filing on the ground that in the 2007 filing, the NYISO and MMU
both supported the same excess Capacity level proposals.83  In this proceeding, however, the
NYISO and the MMU were in complete agreement with respect to the NYCA excess Capacity
assumption.  The NYISO and the MMU also were in conceptual agreement regarding the use of
the peaking plant to establish the level of excess.  The sole difference between the NYISO’s
proposal and the MMU’s variation of it was that the MMU favored setting the level of excess
Capacity for the NYC and Long Island Localities equal to the size of the peaking plant rather
than at 0.5 times its size.

To the extent that the January Order’s determination was influenced by the disagreement between the NYISO and the MMU on that point, the NYISO wishes to clarify that it does not believe that the MMU’s recommendations for NYC or Long Island were unjust, unreasonable, or inadequately supported.  It has argued that the MMU was overly focused on actual market
conditions and that the November Filing’s proposed levels of excess for NYC and Long Island were feasible.  Nevertheless, if the Commission does not adopt the November Filing’s proposals on rehearing, the Commission should instead approve the MMU’s variation.

 

 

 

 

83 Id. at P 122.

 

 

29


 

 

 

 

 

The MMU’s proposals for NYC and Long Island are adequately supported by the

NYISO’s and MMU’s evidence in the record.  Insofar as the January Order’s decision on those
excess Capacity levels was based on a concern regarding the NYISO’s assumptions on the
timing of entry, the MMU’s variation was developed to address that very issue.  Like the
November Filing’s proposal, the MMU’s more closely conforms the calculation of excess
Capacity levels to other ICAP Demand Curve parameters.  It is also more consistent with the
Services Tariff’s requirements than the alternatives favored by supply-side protestors.84 Finally,

setting the excess Capacity assumption for the NYC and Long Island Demand Curves based on 195 MW, instead of 400 MW as under the currently effective ICAP Demand Curves, would be less likely to result in over-compensating or under-compensating suppliers.  It would thus send more accurate price signals for the amount of Capacity needed to maintain reliability. The MMU’s proposal is thus superior to the proposed supply-side alternatives.

 

 

 

5.  The January Order Misinterpreted the Services Tariff’s Provisions
Governing the Determination of Excess Capacity Levels

The January Order wrongly suggests, that excess Capacity levels should reflect “current
conditions,”85 “historical experience,” “future projections,” the “lumpiness” of actual Capacity
additions,86 or “forecasted actual capacity additions.”87 It does not appear that the Commission

is requiring the NYISO to consider these factors but it would be a fundamental legal error if it

were to do so.  As explained above, the Services Tariff does not provide for the level of excess to
be based on “observed” levels of Capacity. It instead requires that the NYISO make a reasoned

 

84 See IPPNY Protest at P 16; New York City Suppliers Protest at 16, 26.

85 Id. at P 117.

86 Id. at 120.

87 Id. at P 121.

 

 

30


 

 

judgment that sets excess Capacity levels at or slightly above, equilibrium (i.e., the Installed Reserve Margin).

Relying on “observed levels” of Capacity to set estimated excess Capacity levels is
circular and could inadvertently perpetuate Capacity surpluses or deficiencies that happen to
exist at the time when ICAP Demand Curves are reset.  For example, the January Order stated
that there is a “current state of significant capacity surplus in the NYCA.... 88 Incorporating

the current surplus into the excess Capacity calculation would tend to maintain the existing

significant surplus without recognizing the economic inefficiency and the negative consequences
to the market and consumers of doing so.  An “observed level” approach also could have the
opposite effect of keeping Capacity levels too low if it were applied at a time when no surplus
existed.  Both alternatives are undesirable because each would be contrary to the purpose of the
ICAP Demand Curves, i.e., to “improve system and resource reliability and incent new entry.”89

 

 

 

6.  There Is No Evidentiary Support for Using the Currently Effective
Excess Capacity Levels for the Next Three Capability Years

 

The Commission erred when it ruled, without any evidentiary support, that the level of

excess incorporated in the NYISO’s currently effective ICAP Demand Curves would result in an
acceptable level of excess for Capability Years 2011/2012 and beyond.90  Although the
Commission properly determined that those levels were appropriate when it set the current ICAP
Demand Curves, they were never considered for use after May 1, 2011.  The NYISO is not
challenging their use for a brief additional period, such as the portion of the suspension period

88 Id. at P 117.

89 Second DCR Order at P 2 (stating that the ICAP Demand Curves "are intended to improve system and resource reliability by valuing the ICAP resources available above the system's required levels, and providing more effective economic signals for new investment.").

90 January Order at P 114.

 

 

31


 

 

that falls after May 1, 2011.  However, extending the excess Capacity levels used in the May
2008 through April 2011 Demand Curves for the three Capability Years of this reset, based on
the record in this proceeding, would be inconsistent with reasoned decision-making.  If the
Commission does not accept the November Filing’s proposal on rehearing or alternatively, the
MMU’s proposal, it should accept the proposal that will be included in the NYISO’s compliance filing and not consider using the level of excess Capacity used in the May 2008 through April
2011 Demand Curves.  To use the level in the current curves constitutes error as it is not
supported by the evidence in the case.91

 

 

C. The Commission Erred When it Found That the NYISO Must Include

System Deliverability Upgrade Costs in the ICAP Demand Curves

The January Order found that System Deliverability Upgrade (“SDU”) costs “are a

 

required cost of investment for interconnection customers in order to participate in the New

York capacity market and be ‘economically viable’” and such costs “are among the ‘current

localized levelized embedded cost of a peaking unit” that must be included in the ICAP Demand
Curves pursuant to the Services Tariff.92  The January Order also found that including SDU costs
in the ICAP Demand Curves does not reduce the incentive for developers to locate their projects
in areas where they would be deliverable93 and rejected arguments that including such costs will
create a situation in which Capacity buyers are subsidizing developers.94  The Commission held

 

 

91 The current Demand Curves have a level of excess of 4 NYC, 4 Long Island, and 1 NYCA. For the reasons stated in the record and described herein, utilizing the level of excess in the current
demand curves risks perpetuating significant levels of surplus Capacity. It also would not result in just and reasonable rates.

92 January Order at P 53.

93 Id. at P 59.

94 Id. at P 60.

 

 

32


 

 

that excluding SDU costs would “not accurately reflect developer’s costs and thus, may discourage investment.”95 The Commission erred in several respects.

The January Order failed to consider the impacts to consumers that will result from

including SDU costs in the peaking unit’s cost of new entry, in contravention of its consumer
protection responsibility under the FPA.96 It is unjust and unreasonable for consumers to pay

Capacity prices that include the costs of SDUs, especially when the Commission97 and other

parties, including the NYISO’s independent MMU, acknowledged that SDU costs are more

appropriately addressed by developing criteria for and, where appropriate, creating new Capacity
zones. The Commission’s ongoing proceeding examining such criteria and potential new
Capacity zones98 provides the appropriate forum for the parties and the Commission, to evaluate
the economically efficient price signals to locate needed Capacity. By contrast, including SDU
costs in the CONE will only serve to mute efficient price signals by increasing the probability
that developers who locate in areas where they incur significant SDU costs will be significantly
insulated from the true economic consequences of their location decision. Other than concluding
that the inclusion of SDU costs will not create a subsidy and that no windfall exists because

 

95 Id.

96 See, e.g., Pennsylvania Water & Power Co. v. FPC, 343 U.S. 414, 418 (1952) (stating that “[a] major purpose of the . . . [FPA] is to protect power consumers against excessive prices”); NAACP v. FPC, 425 U.S. 662, 669-70 (1976) (finding that the “principal purpose [behind passage of the Federal Power
Act] was to encourage the orderly development of plentiful supplies of electricity . . . at reasonable
prices”); Williams Pipeline Co., 21 FERC ¶61,260 at p. 61,583 (1982) (explaining that the Commission’s “essential mission” is “to protect consumers against exploitation” and that “[c]onsumer protection is what we are here for.  Of course, that function must be performed with scrupulous regard for the legitimate
claims of those we regulate.  Nevertheless, it is the consumer’s interest that is paramount. The statutes on which we spend most of our time and energy were carefully designed to close gaps in the protective fabric that the states had previously fashioned for the consumer’s benefit. That is so clear that even lawyers
have been unable to dispute it. Thus history gives us a good light by which to steer when we deal with
electric power and with the transportation of natural gas”).

97 January Order at P 64 (stating that “we agree with NYISO and the MMU that the creation of a new capacity zone could provide better locational signals”).

98 New York Independent System Operator, Inc., Docket No. ER04-449-023.

 

 

33


 

 

including such costs would simply reflect the “actual costs of new entry,”99 the January Order did not address the “resultant outcomes”100 of including SDU costs in the CONE.  The January Order should have (i) considered the financial impact on consumers and (ii) provided a reasoned explanation of why the price signals and investment signals intended for developers would not be muted by including SDUs in the cost of new entry.

The NYISO’s proposal reasonably excluded SDU costs from the peaking unit’s CONE.
Inclusion of SDU costs will result in unjust and unreasonable rates because it will either
discourage development in areas where units would be deliverable or eliminate the financial
disincentives for locating in areas that require significant system upgrades.
The November Filing explained that prior to the instant ICAP Demand Curve reset, SDU costs were not a factor to be considered in a peaking plant’s cost of new entry, as they did not yet exist in the NYISO market.101  The NYISO showed that, contrary to protestors’ assertions, SDUs were not previously identified, and past determinations of SUF costs were irrelevant to the issue of whether SDU costs are properly included in the ICAP Demand Curves.102  The January Order is incorrect in its finding that “the same rationale used to include System Upgrade Facilities in CONE also leads to the conclusion that System Deliverability Upgrades should not be
excluded.”103

The January Order does not refute the NYISO’s statement that the Deliverability tariff
provisions were “designed to give interconnection customers an economic incentive to locate in

 

99 Id. at P 60.

100 Id. at P 119.

101 Id. at P 56 (acknowledging that “System Upgrade Facilities were the only type of identified interconnection upgrade required previously because, prior to the current demand curve reset, NYISO offered only one type of interconnection service—Minimum Interconnection Standard.”).

102 January Answer at 18.

103 January Order at P 57.

 

 

34


 

 

areas where their capacity would be deliverable.”104  Including SDU costs in the peaking plant’s
cost of new entry clearly contravenes the purpose of the Deliverability tariff provisions.  In its
orders accepting the Deliverability tariff provisions, the Commission rejected arguments that the
cost allocation provisions unfairly allocated certain costs entirely to developers, finding that the
approach was “consistent with Commission policy and recognize[d] the competing interests of
those involved.”105  In those orders, the Commission found that it was reasonable and consistent
with a “beneficiary-pays” approach to require developers to be primarily responsible for paying
for those transmission system upgrades necessary to achieve deliverability.106  Further, as noted
in the Affidavit of Dr. David B. Patton, “including SDU costs in the Demand Curves is not an
efficient means of providing long-term economic signals to prospective investors in new

 

resource.”107

Similarly, the January Order incorrectly found that “excluding these costs results in net
CONE that does not accurately reflect the developer’s costs and thus, may discourage
investment.”108 The NYISO and the NYTOs presented evidence that projects can be sited in
regions where deliverability constraints exist, such as NYC, without incurring SDU costs, so
such costs are not necessarily a required cost of new entry.  As shown in the January Answer,
two projects located in NYC, the Hudson Transmission Partner project in Class Year 2008 and
the Bayonne Energy Center project in Class Year 2009, did not incur SDU costs.109  Further, the

 

 

 

 

104 Id. at P 59.

105 Deliverability Order at P 46. 106 Id. at P 45.

107 November Filing at Affidavit of Dr. David B. Patton at P 18. 108 January Order at P 60.

109 January Answer at 19-20.

 

 

35


 

 

Affidavit of John Beck,110 shows that incurring SDU costs in NYC is determined by “specific
local characteristics all under the control and selection of the developer,” including the project’s
interconnection point, voltage level and size.111 The fact that certain projects are locating in a

manner that allows them to avoid SDU costs supports the view that the Deliverability process is
intended to send locational signals for economically efficient siting, and that those tariff
provisions are actually achieving their intended result.112  It also demonstrates that SDU costs are
not a required cost of entry and, therefore, it was appropriate to not include them in of the
estimate of the net CONE.  Suggestions that SDU costs may be allocated to a project are not
evidence of a cost of entry but merely indicate that a supplier made a conscious business decision
to forego locations with zero SDU costs in favor of a location that does have SDU costs.
Reflecting SDU costs in the peaking plant’s cost of new entry will mute the signals that those provisions are currently sending, likely leading to inefficient investment.  Therefore,
rehearing must be granted because the January Order erred when it found that inclusion of such
costs in the peaking plant’s net cost of new entry “does nothing to decrease this incentive
because the developer will still evaluate profitability over the life of the project in determining
where to locate”113

SDU costs are directly related to the issues being addressed in Docket No. ER04-449-
023.  The November Filing explained that the proceeding examining new Capacity zones in the
NYCA is the appropriate venue to consider the SDU costs, as it would address those costs

 

110 See New York Independent System Operator, Inc., Request for Leave to Answer and Answer
of the New York Transmission Owners at Affidavit of John Beck of Consolidated Edison Company of
New York Inc. at P 24, Docket No. ER11-2224 (“Beck Affidavit”), (filed January 10, 2011) (“NYTO
Answer”).

111 NYTO Answer at Beck Affidavit P 24. 112 Id. at P 22.

113 January Order at P 59.

 

 

36


 

 

 

 

 

without increasing Capacity payments to all resources.114               Thus, the January Order should have

accepted the NYISO’s proposal to not include SDU costs.

 

 

 

D. The January Order Should Not Have Directed the NYISO to Consider

Additional Data Regarding NYC System Upgrade Facility Costs That Was Introduced After the NYISO’s Submitted its November Filing

The January Order found that “there is merit to IPPNY’s concerns with the level of

interconnection costs used by the NYISO in determining CONE for the NYC locality” and

directed the NYISO “to address IPPNY’s arguments that the costs for System Upgrade Facilities that NYISO has used for NYC are unrealistic and provide support for the estimate it has
used.”115 It was not reasoned decision-making for the January Order to direct the NYISO to
reexamine the interconnection costs, including SUF costs, of the NYC peaking plant based on
data finalized after the Consultant’s Report and the stakeholder process had been completed.116 Further, the NYISO’s November Filing and January Answer provided sufficient support for the estimate used in the proposed ICAP Demand Curves.  The Commission did not provide a
reasoned basis for its rejection of the NYISO’s estimate beyond the assertion that there may be
“merit” to the concerns raised by IPPNY.

The November Filing used the appropriate data available to calculate the interconnection
costs, including SUF costs, in the NYC peaking unit’s CONE.  The Commission has previously

 

 

 

 

114 November Filing at 13 and Patton Affidavit at P 18 (stating that “[s]ince efficient economic
signals can be achieved by the completion of this effort and implementation of one or more new zones, it
is reasonable to exclude the interzonal SDU costs from the Demand Curves as proposed by the NYISO”).

115 January Order at P 140.

116 The January Order directs the NYISO to review its interconnection and SUF costs based on issues raised by IPPNY’s evaluation of data published by the NYISO on November 30, 2010 and
December 2, 2010.  NYISO Answer at Ungate Affidavit at P 17.

 

 

37


 

 

declined to require updates to inputs to the ICAP Demand Curves based on data available after the fact, stating that

as in a cost-of-service rate case involving test year data, at a certain point, a

decision must be made based on the information on hand, and adjustments based
on post test year data can throw off the balance between offsetting factors.117

The January Order should have followed prior precedent and not required that the

 

NYISO update interconnection costs to reflect data introduced after completion of the

Consultant’s Report and after the November Filing because that information was not yet final
prior to filing118 and as of the date of the filing of this request still has not yet been approved by
the NYISO’s Operating Committee, as required by Section 25.7.7 of Attachment S to the OATT.
The interconnection costs used in the Consultant’s Report were reasonably estimated based on
average SUF costs for historical Zone J Capacity interconnection projects, escalated to 2010
dollars.  The January Order did not find that the NYISO’s use of such data was unjust and
unreasonable.

Further, the reasonableness of the data used in the Consultant’s Report is not undermined
by the more recent project-specific data used by IPPNY.  That data only shows that the
interconnection costs of projects in NYC varies widely, depending primarily on specific project
characteristics wholly within the control of the developer, such as a project’s voltage level and
interconnection point location.  As noted the January Answer119 and in the Beck Affidavit, 120
generalization of the costs used in IPPNY’s analysis is not possible and those costs do not
support the conclusion that the Consultant’s interconnection costs are understated.  Aside from a

 

117 New York Independent System Operator, Inc., 112 FERC ¶61,283 at P 38 (2005). 118 Id. at P 37.

119 January Answer at 14.

120 NYTO Answer at Beck Affidavit P 24.

 

 

38


 

 

statement regarding a “belief” that IPPNY’s concerns have “merit,” the January Order did not
provide a reasoned basis to reject the NYISO’s proposed interconnection costs estimates.
Therefore, rehearing should be granted with respect to the directive that the NYISO reexamine
and provide additional support for the estimates utilized in the proposed ICAP Demand Curves.
In addition, the January Order did not address any of the points raised by Mr. Beck on this issue.  It thus fails to comport with the legal requirement that Commission decisions be
based on substantial record evidence and that the Commission respond to legitimate issues raised
by parties to the proceeding.  Specifically, whether the Commission engaged in reasoned
decision making under the arbitrary and capricious standard, depends on whether it “respond[s]
meaningfully to the evidence.”121 Thus “unless an agency answers objections that on their face

appear legitimate, its decision can hardly be said to be reasoned.”122               As such, directing the

NYISO to consider additional data regarding NYC SUFs, as opposed to approving the NYISO’s proposal, was arbitrary and capricious and should be reversed.

 

 

IV.REQUEST FOR CLARIFICATION OR IN THE ALTERNATIVE REHEARING

A.The Commission Should Clarify its Ruling Regarding the Consistent

Application of the Level of Excess Capacity or, in the Alternative, Grant Rehearing Before the NYISO’s Compliance Filing Deadline

The NYISO also requests clarification of Paragraph 129 and Paragraph 122 of the

January Order in which the Commission, respectively, directed that the “NYISO revise the

demand curves to use the level of excess capacity that is reflected in the curves currently in use
and to use this level of capacity consistently throughout the analyses used to develop the demand

 

 

121 KeySpan-Ravenswood v. FERC, 348 F.3d 1053, 1056 (D.C. Cir. 2003), citing Tesoro Alaska Petroleum Co. v. FERC, 234 F.3d 1286, 1294 (D.C. Cir. 2000).

122 Id.

 

 

39


 

 

curves” and found that the NYISO “does not support its proposal to use a different adjustment for the first three years as compared to the remainder of the nominal life of the hypothetical
peaking unit.” The Commission should clarify that it is not directing the NYISO to change the ICAP Demand Curves to apply that consistent level of excess in its determination of Energy and Ancillary Services revenue offsets to the net CONE and confirm that the level of excess used for years one through three to determine those offsets is just and reasonable. The NYISO also
requests that the Commission grant this clarification expeditiously, and if necessary, issue an
order on this point before it acts on other rehearing issues.  Providing guidance on this discrete issue prior to the NYISO’s compliance filing deadline would eliminate any possible uncertainty regarding the assumptions to be included in that filing.

Paragraph 136 of the January Order accepted the NYISO’s proposed Energy and

Ancillary Services revenue offsets, noting that though changes to estimation methods or data
choices could have been made to produce lower or higher results, the estimated values were
produced using “objective and reasonable statistical methods.”  Those proposed revenue offsets
were calculated using a different level of excess for years one through three, as consistent with
the NYISO’s approach in the prior Demand Curve reset.  In the 2007 Demand Curve reset, the
Consultants used 100.5 percent as the excess level of Capacity for computing Energy and
Ancillary Services revenues for the first three years123 and the NYISO did not alter its approach
for this Demand Curve reset.124 Additionally, Paragraph 136 accepted the NYISO’s proposed

 

 

123 See, New York Independent System Operator, Inc., Tariff Revisions to Implement Revised

ICAP Demand Curves for Capability Years 2008/2009, 2009/2010 and 2010/2011 at 12, Docket No.

ER08-283-000 (filed November 30, 2007) (stating that “[t]he Consultant’s modeled 100.5% as the excess
for these three years…”) and at Affidavit of David Lawrence at Exhibit A at 9 (stating that “[f]or the three
year period covered by this demand curve update, the NYISO recommends using a capacity level of 100.5
percent of the target installed capacity level for computing energy and ancillary services revenue”).

124 November Filing at 17.

 

 

40


 

 

Energy and Ancillary Services revenue offsets calculated using the different years one to three excess Capacity level assumption.  Thus, the NYISO requests clarification that the Commission did not intend for the directives in Paragraph 122 or Paragraph 129 to require the NYISO to modify the accepted Energy and Ancillary Services revenue offsets.

In the alternative, to the extent that the Commission intended to require the NYISO to

change the Energy and Ancillary Services revenues offsets, by requiring a consistent application
of the level of excess to those calculations, the January Order did not engage in reasoned
decision-making and rehearing should be granted expeditiously. The Energy and Ancillary
Services revenue offsets that the Commission accepted in Paragraph 136 were calculated
“[b]ased upon the Consultant’s energy model and the NYISO’s recommended levels of
excess,”125 and assumed a 100.5 percent level of excess Capacity for years one through three.126
No party protested the use of 100.5 percent in the Energy and Ancillary Services revenue offset
calculation. Nor did any party protest the Consultant’s or the NYISO’s application of a level of
excess Capacity in years one through three that differed from the level applied in years four
through thirty.  Paragraph 136 of the January Order accepted the Energy and Ancillary Services
revenue offsets calculated using those different assumptions for the two periods.  The
Commission accepted the Energy and Ancillary Services offset assumptions, finding them to be
produced using “objective and reasonable statistical methods.”127 Thus, should the Commission

not grant the NYISO’s request for clarification on this issue, the Paragraph 122 and Paragraph
129 requirement that the NYISO apply a consistent level of excess Capacity does not reflect
reasoned decision-making, as it contradicts the Commission’s finding in Paragraph 136.

 

125 Id. at Consultant’s Report at 73.

126 Id. at 17 and Consultant’s Report at 73.
127 Id.

 

 

41


 

 

As explained above, the NYISO’s approach did not deviate from its proposal in the 2007
Demand Curve reset, 128 which the Commission previously found to be just and reasonable in
that proceeding.129 Nothing has changed in the time since the last ICAP Demand Curve reset

proceeding that would affect or alter the rationale for the NYISO’s approach and the January Order did not identify any changed circumstances that would make the approach unjust and unreasonable.

Also alternatively, instead of rejecting the NYISO’s proposal, if the Commission

concluded that the record was unclear regarding the NYISO’s application of a different level of
excess for years one through three, the January Order should have, consistent with the other
directives on the level of excess Capacity, provided the NYISO with an opportunity to submit
further justification of its proposal.  Therefore rehearing should be granted, because the
Commission failed to articulate any changed circumstances which would form a basis for
denying what had been previously found to be just and reasonable, requiring the NYISO to
change the Energy and Ancillary Services revenue offsets would make the January Order
internally inconsistent, and, to the extent the record was unclear, the Commission should have
provided the NYISO an opportunity to supplement the record consistent with the other directives
on the level of excess Capacity.

 

 

B.The Commission Should Clarify its Ruling Regarding the NYISO’s Accepted

Winter/Summer Adjustment Methodology or, In the Alternative, Grant

Rehearing

 

 

128 See New York Independent System Operator, Inc., Tariff Revisions to Implement Revised

ICAP Demand Curves for Capability Years 2008/2009, 2009/2010 and 2010/2011 at NERA/S&L report at 61, Docket No. ER08-283-000 (filed November 30, 2007).

129 Second DCR Order at PP 43-47 (accepting the NYISO’s proposed revenue offsets for energy and ancillary services).

 

 

42


 

 

The NYISO respectfully requests clarification regarding the January Order’s directive that it “revise the winter/summer adjustment to reflect the assumption for the level of excess capacity” in order “to be consistent with other aspects of the demand curve reset analysis.”130 The January Order accepted the NYISO’s proposed winter/summer adjustment methodology as “just and reasonable and consistent with the requirements of the Services Tariff with respect to the issue of quantities of capacity available versus quantities sold.”131

It does not appear that the January Order could reasonably be construed as requiring the
NYISO to modify its methodology to include the revised level of excess Capacity in its
calculation of the winter/summer adjustment.  The Commission appears to have accepted the
NYISO’s proposed winter/summer adjustment methodology which is based on the amount of
Capacity available (i.e., the amount of Capacity that could be offered into the ICAP Spot Market
Auctions).  Excess Capacity levels should therefore not be a factor in the calculation of the
winter/summer adjustment because the amount of available Capacity is determined using
historical levels obtained from data published by the NYISO in its annual Load and Capacity
Reports.132

Nevertheless, because the winter/summer adjustment was challenged by a party133 and
because the Commission’s intent is not entirely clear, the NYISO respectfully requests
clarification that it is not required to change its winter/summer adjustment methodology.  The
Commission should instead clarify that Paragraph 161 only requires that the NYISO apply its
accepted winter/summer adjustment methodology when establishing revised ICAP Demand

 

130 January Order at P 161.

131 Id.

132 November Filing at Consultant’s Report at 18.

133 New York Independent System Operator, Inc., Motion to Intervene and Protest of the New York Transmission Owners at 15-17 (filed December 21, 2010).

 

 

43


 

 

 

 

 

Curves that reflect the January Order’s directives regarding excess Capacity levels.  Those

revised ICAP Demand Curves will incorporate a Commission-approved level of excess, but the
level of excess should not be an input into the winter/summer adjustment methodology.
In the alternative, the NYISO respectfully requests rehearing.  As explained above, the level of excess is not an input in the NYISO’s winter/summer adjustment methodology.  If the Commission intended that excess Capacity levels be used as an input, then its ruling would be inconsistent with the January Order’s seeming acceptance of the NYISO’s proposed calculation methodology.  Any such ruling would not constitute reasoned decision-making and should be overturned.  At a minimum, if the Commission did intend for the NYISO to revise its
winter/summer adjustment methodology it should more clearly explain exactly what it expects
the NYISO to do, so that the NYISO may fulfill its compliance obligations.

 

 

V. THE COMMISSION SHOULD CONSIDER THE CUMULATIVE IMPACT OF

ITS DECISIONS WHEN IT CONSIDERS THE REQUESTS FOR REHEARING AND CLARIFICATION IN THIS PROCEEDING

The NYISO is required to administer Capacity markets that “provide a level of

 

compensation that will attract and retain needed infrastructure and thus promote long-term

reliability while neither over-compensating nor under-compensating generators.”134  The

proposals that were advanced in the November Filing were developed with this requirement in mind.  Ultimately, the ICAP Demand Curves must be set at a level that avoids both under- and over-compensation.  Otherwise, the efficiency of the Capacity markets, and the balance between consumer and supplier interests could be seriously  disrupted.

 

 

 

 

134 New York Independent. System Operator, Inc., 118 FERC ¶ 61,182 at P 17 (2007).

 

 

44


 

 

 

 

 

The MMU has observed,135 and the Commission has acknowledged,136 that there is

currently significant surplus Capacity in each of New York’s three Capacity zones.  It is clear

from the NYISO’s Interconnection Queue and its 2010 Load and Capacity Data Report, that new
Capacity has continued to enter the market, and more is expected in the near future. There is no
sign that new entry has been discouraged by the levels of revenue provided under the currently
effective ICAP Demand Curves or would be discouraged by the levels proposed in the
November Filing.

Thus, at a minimum, there should be little cause for concern that the Capacity price

increases proposed by the November Filing would result in Capacity prices that were

 

inefficiently low.  The four determinations addressed in Section III of this rehearing request,

however, give rise to a genuine danger that Capacity prices, especially in New York City, would
be inefficiently high.  In each instance, the Commission has adopted unreasonable
interpretations, or reached unsupported conclusions, that will increase Capacity prices
substantially beyond the levels proposed in the November Filing137
Inefficient over-compensation would distort the Capacity market, particularly in New York City, by encouraging inefficient new entry and by perpetuating the current high level of excess Capacity.  It would also contravene the Commission’ statutory obligation to protect
consumers against excessive rates.  Given the level of rates approved in the January Order, it
appears that the Commission has failed to demonstrate the attention to consumer interests that

 

 

 

135 See Patton Affidavit at 7, citing Potomac Economics, 2009 State of the Market Report New York ISO at iii, iv, xii, and 19 (September 2010), available at

<http://www.nyiso.com/public/webdocs/documents/market_advisor_reports/2009/NYISO_2009_SOM_F
inal.pdf> (noting that “significant surpluses” exist in the three Capacity zones).

136 January Order at P 117.

137 January Answer at Lawrence Affidavit at Exhibit 1.

 

 

45


 

 

Order No. 719 requires.138  It was not reasoned decision-making for the Commission to fail to
account for, or seemingly to even consider, these implications.  A Commission ruling that
substantially increases Capacity prices at a time of significant surplus and significant planned
new Capacity entry also has the potential to undermine consumer and public confidence in
ISO/RTO-administered markets in general, and the NYISO’s ICAP Demand Curve construct in
particular.

 

 

VI.STATEMENT OF ISSUES

In accordance with Rule 713(c), 18 C.F.R. § 385.713(c), the NYISO submits the following statement of issues:

1.  The Commission’s decision finding that no property tax abatement should be assumed in the
peaking plant’s cost of new entry is arbitrary and capricious, is  unlawful, does not reflect
reasoned decision making, and is not reasonably explained because:  (a) the record in this
proceeding clearly supports the conclusion that the peaking plant would be eligible for, and
would receive, a full property tax abatement under the New York City Industrial
Development Agency’s Third Amended and Restated Uniform Tax Exemption Policy and the
Commission failed to consider the price impact of the property tax abatement ruling on NYC
consumers, in contravention of its statutory consumer obligation purpose (see, e.g.,
Pennsylvania Water & Power Co. v. FPC, 343 U.S. 414, 418 (1952); NAACP v. FPC, 495
U.S. 662, 669-70 (1976)); (b)  the Commission disregarded the arguments showing that it
would be irrational to assume that the New York City Industrial Development Agency would
exercise its discretion in a way that would harm economic development and contravene its
stated public policy goals; ( (c) the Commission failed to accord sufficient weight to the
evidence showing that the peaking plant would qualify for tax abatements; (d) the
Commission should have followed its precedent regarding deference to state and local
regulatory agencies (see, e.g., City of Vernon, California, 111 FERC ¶ 61,092 (2005);
Entergy Services, Inc., 120 FERC ¶ 61,020 (2007)) and found that the statements by New
York City Industrial Development Agency regarding its application of the Third Amendment
and Restated Uniform Tax Exemption Policy indicated that it was reasonably likely, and thus

 

138  In Order No. 719, the Commission directed ISOs/RTOs to pursue governance and market

reforms to ensure that they were responsive to stakeholders, and, more generally, that ISO/RTO-

administered markets work for the benefit of consumers. See Wholesale Competition in Regions with
Organized Electric Markets, Order No. 719, FERC Stats. & Regs. ¶ 31,281 at PP 1-2 (2008),
order on reh’g, Order No. 719-A, 74 Fed. Reg. 37,776 (July 29, 2009), FERC Stats. & Regs. ¶
31,292 (2009).

 

 

46


 

 

 

 

 

reasonable to conclude that the peaking plant would receive full property tax abatement; (e) even if it was reasonable to conclude that an assumption of full tax abatement was not
supported, it was not reasoned decision-making to direct that no tax abatement be assumed
(see, e.g., Panhandle Eastern Pipeline Co. v. FERC, 881 F.2d 1101, 1118 (D.C. Cir. 1989)); instead, the Commission should have directed the NYISO to provide additional support for
its proposal, or assume some partial level of property tax abatement, or initiate paper hearing or technical conference proceedings to resolve any remaining factual uncertainties; (f) the
Commission’s conclusion of zero abatement is not supported by the evidence in the record, which supports a high probability of abatement, and will result in unjust and unreasonable
rates; and (g) the January Order imposed an unlawfully high burden of proof on the NYISO, instead of the “just and reasonable” showing required under the Federal Power Act (see, e.g., Cities of Bethany v. FERC, 727 F.2d 1131, 1136 (1984)).

 

2. The Commission’s rejection of the NYISO’s proposed levels of excess Capacity is arbitrary

and capricious, is not lawful, does not reflect reasoned decision making, and is not

reasonably explained because: (a) the NYISO’s proposals were based on reasoned judgments
and were consistent with the requirements of the NYISO’s Services Tariff (see NYISO
Services Tariff Section 5.14.1.2); (b) the NYISO’s proposal provided full support for its
proposed excess Capacity levels, the support provided was comparable to what was provided
for the same proposal in the last ICAP Demand Curve reset, the Commission failed to
explain why it was requiring a greater level of support than it had in the past, and the
evidence showed that the NYISO’s proposed excess Capacity levels would have resulted in
just and reasonable rates; (c) the Commission erred because it applied to the NYISO an
impermissibly stringent burden of proof (see, e.g., Cities of Bethany v. FERC, 727 F.2d 1131,
1136 (1984)); (d) in the event that the Commission refused to accept the NYISO’s proposal
on rehearing, it should have found, in the alternative, that the MMU’s variation on that
proposal was adequately supported and accepted it; (e) the Services Tariff requires that the
NYISO calculate excess Capacity as if Capacity was, at or slightly above, the Installed
Reserve Margin (see NYISO Services Tariff Section 5.14.1.2) and the Commission erred to
the extent it incorrectly directed the NYISO to base its proposed level of excess Capacity on
“observed levels”; and (f) there is no evidentiary support for using the currently effective
level of excess Capacity for the next three Capability Years.

3. The Commission’s finding that the NYISO’s proposal to exclude SDU costs from the

peaking plant’s cost of new entry is arbitrary and capricious, does not reflect reasoned

decision making, and is not reasonably explained because:  (a) the Commission failed to

consider the impact that inclusion of SDU costs in the peaking plant’s cost of new entry

would have on consumers (see, e.g., Pennsylvania Water & Power Co. v. FPC, 343 U.S. 414,
418 (1952); NAACP v. FPC, 495 U.S. 662, 669-70 (1976)); (b) the Commission failed to
consider the evidence presented that indicated that SDU costs were not a factor to be
considered in prior Demand Curve reset proceedings; (c) the Commission erred when it
found that including SDU costs in the peaking plant’s cost of new entry did not mute the
signals that the deliverability tariff provisions were intended to send and are currently
sending (see New York Independent System Operator, Inc., 126 FERC ¶61,046 at PP 45-46
(2009)); and (d) the Commission failed to consider the evidence presented which showed that

 

 

 

47


 

 

 

 

 

projects can be sited in areas where deliverability constraints exist without incurring SDU costs, so such costs are not necessarily a required cost of new entry.

 

4. The Commission’s directive that the NYISO reexamine interconnection costs, including SUF

costs, of the NYC peaking plant, is arbitrary and capricious, does not reflect reasoned

decision making, and is not reasonably explained because:  (a) it would require the NYISO to reexamine those costs based on data available after the Demand Curve Reset process had been concluded and that to date has not yet been approved by the NYISO’s stakeholder
Operating Committee as required by the OATT (see, e.g., New York Independent System
Operator, Inc., 112 FERC ¶ 61,283 at P 38 (2005)); and (b) the NYISO provided sufficient support for its interconnection costs estimates.

5. If the Commission denies clarification that the NYISO does not need to apply a consistent

level of excess in its determination of Energy and Ancillary Services revenue offsets to the
net CONE and that the proposed level of excess used for years one through three to
determine those offsets was just and reasonable, the Commission’s decision is arbitrary and
capricious, does not reflect reasoned decision making, and is not reasonably explained
because:  (a) interpreting the January Order to require the NYISO to change its Energy and
Ancillary Services revenue offsets makes the January Order internally inconsistent, and thus
does not reflect reasoned decision-making; (b) the January Order did not provide a reasoned
basis to reject a proposal previously found to be just and reasonable (see New York
Independent System Operator, Inc., 122 FERC ¶ 61,064 at PP 43-47 (2008)); and (c) if the
record was unclear, the Commission should have provided the NYISO an opportunity to
submit further justification of its proposal.

6. If the Commission denies clarification that it did not intend for the NYISO to modify its

winter/summer adjustment methodology to include the revised level of excess Capacity, the
Commission’s decision is arbitrary and capricious, does not reflect reasoned decision
making, and is not reasonably explained because the January Order accepted the NYISO’s
proposed winter/summer adjustment methodology which is based on the amount of available
Capacity and is not properly calculated using the excess Capacity level as a factor.

7. The Commission’s failure to consider or address the danger that the cumulative impact of the

decisions referenced in Paragraphs one through six would be to set Capacity prices

inefficiently high, especially in New York City, and thereby distort the Capacity markets by encouraging inefficient new entry, perpetuate the current high level of excess Capacity, and expose consumers to excess rates was is arbitrary and capricious, does not reflect reasoned decision making, and is not reasonably explained.

 

 

 

 

 

 

 

 

 

 

 

48


 

 

 

 

 

 

 

VII.   CONCLUSION

WHEREFORE, for the foregoing reasons, the New York Independent System Operator, Inc. respectfully requests that the Commission grant rehearing, or in the alternative, clarification, of the January Order for the reasons specified above.

 

 

Respectfully Submitted,

 

/s/Ted J. Murphy

Ted J. Murphy
Counsel to the

New York Independent System Operator, Inc.

 

 

February 28, 2011

cc:Michael McLaughlin

Anna Cochrane
Connie Caldwell
Michael Bardee
Kathleen Nieman
Lance Hinrichs
Rachel Spiker

Gregory Berson
Jeffrey Honeycutt
Daniel Nowak
Jignasa Gadani

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

49


 

 

 

 

 

CERTIFICATE OF SERVICE

I hereby certify that I have this day caused the foregoing document to be served on the official service list compiled by the Secretary in this proceeding.
Dated at Washington, DC, this 28th day of February, 2011.

 

 

/s/Ted J. Murphy

Hunton & Williams LLP
1900 K Street, NW
Washington, DC 20426
(202) 955-1500

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

50