UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
New York Independent System Operator, Inc.)Docket Nos. ER19-467-000
ER19-467-001
ER19-467-002
REQUEST FOR REHEARING OF
NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.
Pursuant to Section 313(a) of the Federal Power Act1 and Rule 713 of the Rules of
Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),2 the
New York Independent System Operator, Inc. (“NYISO”) requests rehearing of the
Commission’s December 20, 2019, Order on Compliance Filing in the above-captioned
proceedings (“December 2019 Order”).3 The December 2019 Order accepted in large part the
NYISO’s compliance filing in response to Order No. 841,4 but rejected certain elements of the
NYISO’s proposal and directed the NYISO to submit a further compliance filing.5
As discussed below, the NYISO respectfully requests rehearing of the December 2019 Order’s determinations that the NYISO is required to: (i) assess transmission charges to Energy Storage Resources participating in its markets when such resources are charging for later
injection to the grid but are not being dispatched by the NYISO to provide a service in its
1 16 U.S.C. § 8251(a).
2 18 C.F.R. § 385.713.
3 New York Independent System Operator, Inc., Order on Compliance Filing, 169 FERC ¶ 61,225 (2019) (“December 2019 Order”).
4 Electric Storage Participation in Markets Operated by Regional Transmission Organizations and
Independent System Operators, Order No. 841, 162 FERC ¶ 61,127 (Feb. 15, 2018), 83 Fed. Reg. 9580 (Mar. 6,
2018), Errata Notice (Feb. 28, 2018) (“Order No. 841”), order on reh’g, Order No. 841-A, 167 FERC ¶ 61,154
(2019). All citations to Order No. 841 in this compliance filing are to the revised order included with the February 28, 2018, errata notice.
5 Capitalized terms that are not defined in this request for rehearing shall have the meaning set forth in the NYISO’s Open Access Transmission Tariff (“OATT”) or its Market Administration and Control Area Services Tariff (“Services Tariff”).
markets, and (ii) propose an effective date for its Order No. 841 compliant tariff revisions that is
no later than May 1, 2020.6 As described below, these two determinations do not constitute
reasoned decision-making. The Commission should, therefore, grant rehearing, accept the
NYISO’s proposed approach for transmission charges, and confirm that the NYISO may justify a
later effective date.
I.COMMUNICATIONS
Communications and correspondence regarding this pleading should be directed to:7
Robert E. Fernandez, Executive Vice President & General Counsel
Karen Georgenson Gach, Deputy General Counsel
Raymond Stalter, Director, Regulatory Affairs
* Alex M. Schnell, Assistant General Counsel/ Registered Corporate Counsel * Gregory J. Campbell, Attorney
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-6000
Fax: (518) 356-4702
rfernandez@nyiso.com
kgach@nyiso.com
rstalter@nyiso.com
aschnell@nyiso.com
gcampbell@nyiso.com
* -- Persons designated for service.
6 December 2019 Order at PP 186-189, 223.
* Ted J. Murphy
Hunton Andrews Kurth LLP 2200 Pennsylvania Avenue, NW Washington, D.C. 20037
Tel: (202) 955-1500
Fax: (202) 778-2201
tmurphy@huntonak.com
* Michael J. Messonnier Jr. Hunton Andrews Kurth LLP 951 East Byrd Street
Richmond, VA 23219
Tel: (804) 788-8200
Fax: (804) 344-7999
mmessonnier@huntonak.com
7 The NYISO respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) (2014) to permit service on counsel in multiple locations.
2
II.SPECIFICATION OF ERRORS/STATEMENT OF ISSUES
In accordance with Rule 713(c),8 the NYISO submits the following specifications of
error and statement of the issues on which it seeks rehearing of the December 2019 Order:
• The December 2019 Order’s directive that the NYISO assess transmission charges to
Energy Storage Resources that are charging for later injection to the grid does not
constitute reasoned decision-making9 because the NYISO’s proposed approach in its
compliance filing aligns with its existing rate structure for transmission charges assessed
to resources in the New York Control Area (“NYCA”) that withdraw energy at a node for
later injection in the grid, and because the directive is inconsistent with the approach
accepted by the Commission for the California Independent System Operator (“CAISO”).
There is thus no reasoned basis for the directive, and the Commission has not supplied a
reasoned explanation for its decision.
• The December 2019 Order’s directive that the NYISO must propose an effective date for
its Order No. 841 compliant tariff revisions that is no later than May 1, 2020 does not
constitute reasoned decision-making10 to the extent that it is intended to prevent the
NYISO from demonstrating that a later effective date is justified. A “no later than May
1, 2020” deadline is unreasonable because it is based on an assumption that is not
supported by record evidence and no reasoned explanation has been supplied for it. The
unsupported assumption in the December 2019 Order should not preclude the NYISO
from seeking and justifying an extension in a later filing.
III.BACKGROUND
On December 3, 2018, the NYISO submitted its compliance filing in response to Order
No. 841 (“December 2018 Filing”).11 Specifically, the NYISO proposed tariff revisions to
establish a new participation model for Energy Storage Resources that recognizes their physical
and operational characteristics, and facilitates their participation in the NYISO-administered
8 18 C.F.R. § 385.713(c).
9 See, e.g., Motor Vehicle Mfr. Ass 'n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 at 43 (1983); National Fuel Gas Supply Corp. v. FERC, 468 F.3d 831 at 839 (D.C. Cir. 2006); NorAM Gas Transmission Co. v. FERC, 148 F.3d 1158, 1165 (D.C. Cir. 1998); citing K N Energy, Inc. v. FERC, 968 F.2d 1295, 1303 (D.C. Cir. 1992); PPL Wallingford Energy LLC v. FERC, 419 F.3d 1194, 1198 (D.C.Cir.2005).
10 Id.
11 New York Independent System Operator, Inc., Compliance Filing and Request for Extension of Time of Effective Date, Docket No. ER19-467-000 (December 3, 2018) (“December 2018 Filing”).
3
Energy, Ancillary Services, and Installed Capacity markets. The NYISO subsequently submitted further information in response to the Commission’s request for additional information
concerning the December 2018 Filing12 and submitted amendments to its initial filing.13
On December 20, 2019, the Commission accepted the NYISO’s compliance filing in
large part, but rejected certain elements of the NYISO’s proposal. This filing seeks rehearing of two of the December 2019 Order’s determinations.
IV.REQUEST FOR REHEARING
A.The Commission Should Grant Rehearing of the December 2019 Order’s
Determination that the NYISO Is Required to Assess Transmission Charges to
Energy Storage Resources that Are Charging for Later Injection to the Grid
In the December 2018 Filing, the NYISO proposed not to assess transmission charges to
any Energy Storage Resource participating in the NYISO-administered markets when that
resource is charging for later injection to the grid.14 The December 2019 Order held that the
NYISO’s proposal did not comply with the requirements in Order Nos. 841 and 841-A.15
Specifically, the Commission concluded that the NYISO had not shown that its proposal is
reasonable given how it assesses transmission charges to wholesale load under its existing rate
structure.16
12 New York Independent System Operator, Inc., Response to April 1, 2019 Letter and Notification of
Implementation Issues that Necessitate Additional Limited Compliance Tariff Revisions, Docket No. ER19-467-001 (May 1, 2019).
13 The NYISO submitted minor amendments to the material in its December 2018 Filing to address two implementation issues concerning the ability of electric storage facilities to participate in the NYISO-administered markets as Generators that are Energy Limited Resources. New York Independent System Operator, Inc., Order No. 841 Compliance Filing, Docket No. ER19-467-002 (May 31, 2019); see December 2019 Order at PP 43-48
(accepting NYISO’s new participation model for Energy Storage Resources as complying with Order No. 841 and not requiring changes to the NYISO’s Energy Limited Resource participation model).
14 December 2018 Filing at p 22 n. 52; see also New York Independent System Operator, Inc., Response to April 1, 2019 Letter and Notification of Implementation Issues that Necessitate Additional Limited Compliance Tariff Revisions in Docket No. ER19-467-000, Docket No. ER19-467-001 at pp 31-32 (May 1, 2019).
15 December 2019 Order at PP 186-189.
16 Id. at P 189.
4
The Commission did not engage in reasoned decision-making when it rejected the
NYISO’s proposal. As the NYISO’s compliance filing explained, and as is reiterated here, the
NYISO’s proposal is aligned with its existing rate structure for transmission charges to resources in the NYCA that withdraw energy at a node for later injection to the grid. In addition, the
December 2019 Order’s determination is inconsistent with the Commission’s acceptance of
CAISO’s proposed treatment of transmission charges. Like the NYISO, CAISO presented its
existing rate structure for electric storage resources that withdraw energy for later injection to the grid as justification for not assessing transmission charges to energy storage resources that
withdraw energy at a node for later injection to the grid. As explained below, there is no
reasoned basis for overlooking the fact that the NYISO’s proposal is consistent with its existing practice or for treating the NYISO and CAISO differently. The Commission has likewise not
provided a reasoned explanation for its decision.
1. Order Nos. 841 and 841-A Transmission Charge Requirements
In Order No. 841, the Commission determined that the transmission charges that apply to
load should apply to electric storage resources, except when the resource is dispatched by the
RTO/ISO to provide a service in the RTO/ISO markets.17 However, the Commission recognized
that different transmission charges may apply to a load resource located at a single node that is
paying a nodal price for energy (e.g., a pump storage resource) versus the charges that apply to
load resources that are located across multiple nodes that are paying a zonal price of energy (e.g.,
load serving entities).18 The Commission instructed that if the load resource located at a single
node was paying different transmission charges than load resources across multiple nodes, then
17 Order No. 841 at PP 297-298; Order No 841-A at P 108.
18 Order No. 841 at P 297.
5
the RTO/ISO is required to apply the transmission charges applicable to the single node resources to electric storage resources.19
In addition, in Order No. 841-A the Commission clarified the meaning of the term
“applicable transmission charges” for the charges to be assessed to electric storage resources that
are not being dispatched by the ISO/RTO to provide a service in its markets.20 Specifically, the
Commission indicated that (1) an RTO/ISO may propose to apply its existing rate structure for
transmission charges to an electric storage resource that is charging at wholesale; (2) an electric
storage resource that is charging for participation in an RTO/ISO market should be assessed
charges consistent with how the RTO/ISO assesses transmission charges to wholesale load under
its existing rate structure; and (3) if an RTO/ISO proposes not to apply transmission charges to
an electric storage resource that is charging at wholesale, the RTO/ISO must demonstrate that
exempting such a resource from these charges is reasonable given its existing rate structure for
transmission charges.21
2. The NYISO’s Proposed Approach Concerning the Assessment of Transmission
Charges Aligns with Its Existing Rate Structure
Consistent with the Commission’s directives in Order Nos. 841 and 841-A, the NYISO
proposed in its December 2018 Filing that it would not “assess transmission charges to Energy
Storage Resources, consistent with the treatment of other Resources in the New York Control
Area.”22 As this filing reiterates, the NYISO’s proposed approach concerning transmission
charges for Energy Storage Resources is consistent with its existing approach concerning the
19 Id. (“[T]o the extent that load resources located at a single node pay different transmission charges than load resources located across multiple nodes, then we require each RTO/ISO to apply those transmission charges for single-node resources to electric storage resources that are located at a single pricing node….”).
20 Order No. 841-A at P 121.
21 Id.
22 December 2018 Filing at p 22 n. 52.
6
assessment of transmission charges to resources in the NYCA that withdraw energy for later
injection to the grid and complies with the Commission’s instructions in Order Nos. 841 and
841-A.
As described below, the NYISO and the Transmission Owners assess three transmission
charges to customers located in the NYCA based on their energy withdrawals to serve Load.
The Transmission Usage Charge (“TUC”) is the congestion and loss components of the Locational Based Marginal Price (“LBMP”) that the NYISO develops. The TUC is also
assessed to customers that purchase transmission service from the NYISO, but supply their own
Energy in a bilateral transaction. The TUC is assessed in both the Day-Ahead Market and the
Real-Time Market.
Each Transmission Owner assesses a Transmission Service Charge (“TSC”) based on a
customer’s Energy withdrawals in the Real-Time Market, which charge provides for the
Transmission Owner’s recovery of the costs of its transmission facilities.
Finally, the NYISO assesses, on behalf of the New York Power Authority (“NYPA”), a NYPA Transmission Adjustment Charge (“NTAC”) based on a customer’s Energy withdrawals in the Real-Time Market, which charge provides for NYPA’s recovery of its transmission service revenue requirement.
However, since it commenced operations two decades ago, the NYISO has assessed
transmission charges differently to an electric storage resource that withdraws energy for later
injection to the grid. Specifically, the NYISO has applied a separate rate structure for
transmission charges applicable to the pumped storage resource operating in the NYCA. The
Blenheim-Gilboa Pumped Storage Power Project (“Gilboa”) is a pump storage facility located at
a single Generator bus (or node) that pays the nodal LBMP to withdraw Energy as a “negative
7
injection”23 for later injection back to the grid (when it is paid the nodal LBMP). The facility is currently the only storage resource in the NYCA that is optimized in the NYISO’s dispatch.24
Since 1999, the NYISO has treated pumped storage bids to withdraw Energy for later injection to the grid as negative injections at the Resource’s bus, rather than as withdrawals to serve zonal Load. The NYISO assesses the congestion and loss component of the LBMP to a pumped storage resource based on its negative injections at its bus. Because pumped storage has always been scheduled and dispatched as a Generator, the NYISO calculates the LBMP
(including the congestion and losses component of the LBMP) in a manner that incorporates the facility’s positive or negative injections at its bus in the Day-Ahead Market and Real-Time
Market, rather than as Load withdrawals at the zonal level.
Pumped storage is not assessed the TSC or NTAC for its negative generation in the Real-
Time Market. TSC and NTAC are only assessed to customers based on their Energy
withdrawals in the Real-Time Market to serve Load. Negative injections at the Generator bus
have never been treated as Load for dispatch or settlement purposes. Instead, pumped storage is
assessed the NYISO’s annual budgeted costs and annual FERC fees set forth in Rate Schedule 1
of the NYISO OATT. The NYISO’s annual budgeted costs and FERC fees are the two charges
the NYISO assesses to Generators based on their nodal injections. In the case of Gilboa, the
injections used to determine the NYISO’s annual budgeted costs and FERC fees include both its
positive Energy injections and the absolute value of its negative injections to withdraw energy
23 A “negative injection” is a withdrawal, rather than an injection, of Energy at a bus (node) by a Generator
for later injection back to the grid. See the definition of Injection Billing Unit in Section 1.9 of the OATT and the
discussion below. It is distinguished from Station Power by the NYISO’s Tariffs. See Section 2.19 of the Services
Tariff.
24 As the NYISO explained in its May 31, 2019 filing in this docket, Gilboa is an Energy Limited Resource
that submits offers to withdraw Energy as negative injections. New York Independent System Operator, Inc., Order
No. 841 Compliance Filing, Docket No. ER19-467-002 at 6-8 (May 31, 2019). Gilboa is not an Energy Storage
Resource.
8
for later injection back to the grid.25 The NYISO’s annual budgeted costs and annual FERC fees
are not transmission charges; they are assessed to all Generators based on their Energy
injections.
The NYISO proposed to apply to new Energy Storage Resources the same transmission charge requirements that it has applied since start-up to the existing electric storage facility that withdraws energy at its discrete Generator bus for later injection back to the grid. As with
pumped storage, the NYISO proposed to treat an Energy Storage Resource’s withdrawal of
Energy at its node for later injection back to the grid as negative generation scheduled at the
Energy Storage Resource’s bus.
Consistent with the transmission charges that are assessed to pumped storage under the
NYISO’s existing rate structure, an Energy Storage Resource will be responsible for paying the TUC for its negative injections. The TUC calculation incorporates each Energy Storage
Resource’s negative injections at its Generator bus in the Day-Ahead Market or in the Real-Time Market, as applicable.26
Consistent with how negative injections by pumped storage at a node are treated under
the NYISO’s existing rate structure for transmission service charges, the NYISO proposed that
25 The term Injection Billing Unit is defined in Section 1.9 of the OATT as “A Transmission Customer’s
Actual Energy Injections (for all internal injections) or Scheduled Energy Injections (for all Import Energy
injections) in the New York Control Area, including injections for Wheels Through. For purposes of Rate Schedule
1 and Rate Schedule 11 of this ISO OATT, (i) a Limited Energy Storage Resource shall be responsible for charges
or eligible for payments on the basis only of its Actual Energy Injections and (ii) a Day-Ahead Demand Reduction
Provider’s Demand Reduction shall be included as Injection Billing Units. For purposes of recovering the ISO
annual budgeted costs and the annual FERC fee pursuant to Rate Schedule 1 of this ISO OATT, Injection
Billing Units shall include the absolute value of negative injections by pump storage facilities.” Emphasis
added.
26 The TUC is the only transmission charge assessed in the Day-Ahead Market.
9
an Energy Storage Resource not be required to pay the TSC and NTAC, which are only assessed to customers withdrawing energy to serve zonal Load in real-time.27
The NYISO’s proposed approach complies with the requirements in Order No. 841-A
that permit an RTO/ISO to assess transmission charges to electric storage facilities consistent
with its existing rate structure for such charges. Specifically, the NYISO has proposed to apply the same, existing rate structure for transmission charges that it currently uses for the only energy storage resource historically (and currently) included in its dispatch to all Energy Storage
Resources. This approach is reasonable as a pump storage resource that pays the LBMP at its transmission node and withdraws energy for later injection to the grid more accurately reflects the characteristics and expected impact of Energy Storage Resources than entities that withdraw energy on a non-price-sensitive, zonal basis to serve Load.
3. The NYISO’s Proposed Approach Also Aligns with How NYISO Currently
Assesses Transmission Charges to Energy Storage Resources that Pay a
Nodal Price for Energy
The NYISO’s proposed approach also complies with the requirement in Order No. 841
that an RTO/ISO apply the transmission charges applicable for single node resources (e.g., pump
storage resources) to electric storage resources that are located at a single pricing node.28
Consistent with the Commission’s instruction, the NYISO proposes to price all Energy Storage
Resources at a single node and to apply the same transmission charge requirements that it has
27 An Energy Storage Resource, as with all other Generators, will be responsible for the NYISO’s annual budgeted costs and annual FERC fees based on its Energy injections, including the absolute value of its negative injections, like pumped storage is under the NYISO’s existing rate structure.
28 Order No. 841 at P 297.
10
applied for more than twenty years to the existing, nodal energy storage resource in New York (the Gilboa facility) to all nodal Energy Storage Resources in the NYCA.
4. Requiring the NYISO to Diverge from Its Existing Rate Structure for
Transmission Charges Will Produce Unjust and Unreasonable Results
Requiring the NYISO (or Transmission Owners) to assess Load-side transmission
charges (i.e., the TSC and NTAC) to Energy Storage Resources would be inconsistent with the
NYISO’s existing rate structure for transmission charges and could lead to inefficiencies that
produce unjust and unreasonable results. Assessing TSC and NTAC to Energy Storage
Resources while they are withdrawing Energy can result in double charging the TSC and NTAC
to Loads. If the NYISO is required to assess TSC and NTAC to an Energy Storage Resource
when it is withdrawing Energy for later injection to the grid, but not simultaneously providing a
service to the NYISO’s markets, then the NYISO expects that the Energy Storage Resource
would include the TSC and NTAC costs in its Energy Bids in order to recover the additional
costs imposed on its Energy withdrawals.29 When an Energy Storage Resource that incorporates
TSC and NTAC costs into its Bid is marginal, Loads in the NYCA will effectively be paying the
TSC and NTAC twice - once as part of the “energy” component of LBMP and again when the
NYISO and the relevant Transmission Owner assess the TSC and NTAC to the Loads. It is not
clear to the NYISO that this will produce a just and reasonable result under the NYISO’s existing
rate structure.
For all of the above-stated reasons, the NYISO’s proposed approach for assessing
transmission charges to Energy Storage Resources complies with the requirements in Order Nos.
841 and 841-A. The Commission should grant rehearing and accept the NYISO’s proposal.
29 The additional transmission costs incurred by the Energy Storage Resource would be included in
NYISO’s reference levels for the resource, if requested, because the TSC and NTAC would be an actual cost that the Energy Storage Resource is required to pay.
11
5. The NYISO’s Proposal Is Consistent with the CAISO’s Approach Accepted by
the Commission
The Commission should also grant rehearing and accept the NYISO’s proposed treatment of transmission charges for Energy Storage Resources because the NYISO’s proposed approach is consistent with CAISO’s approach for such charges, which the Commission has accepted as complying with Order No. 841.
CAISO also proposed to use an existing rate structure to satisfy the requirements in Order No. 841.30 Specifically, CAISO proposed to use its current non-generation resource (“NGR”) model for electric storage facilities, by which CAISO treats electric storage facilities charging as “negative generation,” rather than as load or demand, and bills the resource at the wholesale
nodal locational marginal price.31 Consistent with this structure, CAISO proposed that it would not assess transmission access charges to electric storage resources.32
The Commission accepted CAISO’s proposed approach.33 It noted that “CAISO’s
existing rate structure accounts for NGR charging as negative generation” and, “[a]s a result,
CAISO does not assess transmission access charges, which only apply to load, to NGR charging, regardless of the reason for the NGR’s negative generation.”34
As with CAISO, the NYISO has proposed to apply an existing rate structure for
transmission charges to Energy Storage Resources that are charging for later injection to the grid.
As explained above, the NYISO’s existing rate structure for its only electric storage resource
30 California Independent System Operator Corporation, 169 FERC ¶ 61,126 at PP 124-126 (2019) (“California 841 Order”).
31 Id. at P 124.
32 Id. at P 126.
33 Id. at PP 136-138.
34 Id. at P 137.
12
accounts for charging as negative injection,35 just as CAISO’s NGR approach does. In addition, as with CAISO, the NYISO does not assess transmission charges, other than the congestion and loss components of LBMP,36 to its existing electric storage resource when the resource is
charging for later injection back to the grid.
The Commission went further in its CAISO order and permitted CAISO to change its
existing rate structure for pump storage resources, which were previously assessed transmission access charges, so that pumped storage resources are now treated in the same manner as electric storage facilities under the NGR model, and are no longer assessed transmission charges.37 The NYISO did not propose to change its existing approach for transmission charges assessed to
resources that are eligible to withdraw energy for later injection. Rather, the NYISO proposes to apply its existing rules that apply to a pump storage resource to all Energy Storage Resources.
The NYISO’s proposed approach for assessing transmission charges to Energy Storage Resources complies with the requirements in Order Nos. 841 and 841-A and is consistent with the rules the CAISO proposed and the Commission accepted for filing. The Commission should grant rehearing and accept the NYISO’s proposal.
B. The Commission Should Grant Rehearing of the December 2019 Order’s
Determination Regarding the Effective Date of the NYISO’s Order No. 841-
Compliant Tariff Provisions to the Extent that It Is Intended to Prevent the NYISO from Demonstrating that a Later Effective Date is Justified
The December 2019 Order rejected the NYISO’s request for a flexible effective date that would be no earlier than May 1, 2020. It expressed concern that the NYISO’s proposal
35 CAISO’s “negative generation” is directly comparable to a “negative injection” in the NYCA.
36 California also assesses the congestion and loss components of LMP to NGRs when they withdraw
Energy.
37 California 841 Order at PP 126, 138.
13
“inappropriately creates uncertainty for existing and prospective market participants........”38 The
Commission also stated that “[n]early a full year has elapsed since NYISO proposed this
effective date in its compliance filing” and that “we expect that NYISO has made sufficient progress to implement its software upgrade.”39 Accordingly, Paragraph 223 of the December 2019 Order directed the NYISO to propose an effective date for its Order No. 841 compliance revisions “that is no later than May 1, 2020.”40
The December 2018 Filing explained that it would not be possible for the NYISO to
implement necessary software upgrades before May 1, 2020, due to a years-long effort to
upgrade its Energy Management System (“EMS”) and Business Management System (“BMS”)
platforms, which comprise the hardware and software that run the NYISO’s wholesale Energy
markets and monitor and maintain the reliability of the bulk electricity grid. The EMS is used by
NYISO’s system operators to monitor the reliable operation of the grid and for situational
awareness, and includes applications that monitor load flows and perform contingency analyses,
such as outage monitoring and automatic generation control. The BMS is a suite of applications
that comprise the Security Constrained Unit Commitment, Real-Time Commitment, and Real-
Time Dispatch software used to develop schedules and prices for the NYISO’s Energy and
Ancillary Services markets. The NYISO’s upgrade to these platforms is nearing completion, and
is expected to be deployed in March 2020, or, if conditions permit, February.
In the thirteen months since the December 2018 Filing, the NYISO has worked diligently along with its contractors and has recently completed the software development necessary to
38 December 2019 Order at P 223.
39 Id.
40 Id.
14
effectuate the proposed Energy Storage Resource participation model.41 However, substantial
software testing and staff training remains to be done. Software testing will include simulated
operations by multiple units throughout the state, and the NYISO will be reviewing how changes
to various bid parameters and market conditions impact the performance of the NYISO’s EMS
and the BMS. The NYISO will also conduct integrated testing across the impacted NYISO
systems to confirm that the software operates in a manner that is consistent with the tariff
revisions submitted in this docket in compliance with Order Nos. 841 and 841-A. Along with
this required testing, the NYISO will conduct system operator training to educate operators on
the new system capabilities and conduct market trials to provide Market Participants with the
opportunity to test the new software.
Although the NYISO is expeditiously completing Energy Storage Resource participation
model development, it has determined that these testing and training activities cannot practicably
be completed by May 1, 2020. As described in the December 2018 Filing and in the NYISO’s
December 20, 2019 Informational Filing in this Docket,42 much of the testing and training cannot
commence until the completion of the ongoing upgrade to EMS and BMS.43 Therefore, the
NYISO expects to advance the required testing and training in the first quarter of 2020. Once the
applicable testing and training is completed the NYISO will be in a position to deploy the
software, and make the compliance revisions effective. The NYISO’s current best estimate is
that it will be in a position to make its compliance revisions effective by September 30, 2020.
41 The completed software applications were developed to implement the rules and requirements submitted in the NYISO’s December 2018 Filing. Additional software, and adjustments to software that has already been developed, will be required to address the directives contained in the December 2019 Order.
42 New York Independent System Operator, Inc., Informational Filing, Docket No. ER19-467 (Dec. 20,
2019).
43 The software necessary to implement the Energy Storage Resource participation model was developed to
integrate with the upgraded EMS/BMS platform, and therefore cannot be tested on the currently operating systems.
15
Consequently, the NYISO intends to make a filing in the near future to request an
extension of the May 1, 2020 deadline under Rule 2008 of the Commission’s Rules of Practice
and Procedure. The NYISO is still finalizing its implementation plans, and that filing will
explain the need for additional time in more detail. The NYISO believes that it already has the
authority to make such a filing and that nothing in the December 2019 Order restricts its right to
do so.
Nevertheless, out of an abundance of caution, the NYISO is requesting rehearing to the
extent that the December 2019 Order was intended to prevent it from making a filing
demonstrating the need to extend the May 1, 2020 deadline. If the December 2019 Order was
meant to preclude subsequent extensions requests, that determination is not based on reasoned
decision-making. The December 2019 Order imposed the May 1, 2020 deadline based on an
assumption that the NYISO had made substantial progress on software upgrades in the year since
the December 2018 Filing. As noted above, the Commission’s assumption is correct as far as it
goes but overlooks the need for extensive performance testing. It would not be reasoned
decision-making for the Commission to disregard a NYISO demonstration that the need for
testing will not permit implementation by May 1, 2020, or to insist that the NYISO deploy
software without finishing testing and training. The December 2019 Order does not explain how
such a holding could be reasonable. Moreover, the Commission’s concern about an uncertain
effective date will be fully addressed by the forthcoming extension filing. The Commission
should therefore grant rehearing, to the extent necessary, to permit the NYISO to make an
extension filing.
16
VI.CONCLUSION
WHEREFORE, for the foregoing reasons, the New York Independent System Operator,
Inc., respectfully requests that the Commission grant rehearing of the December 2019 Order.
Respectfully submitted,
/s/ Gregory J. Campbell
Alex M. Schnell
Gregory J. Campbell
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Counsel for the New York Independent System Operator, Inc.
Ted J. Murphy
Hunton Andrews Kurth LLP
2200 Pennsylvania Avenue, NW Washington, D.C. 20037
Michael J. Messonnier Jr.
Hunton Andrews Kurth LLP 951 East Byrd Street
Richmond, VA 23219
Counsel for the New York Independent System Operator, Inc.
January 21, 2020
cc:Anna Cochrane
James Danly
Jignasa Gadani
Jette Gebhart
Kurt Longo
John C. Miller
David Morenoff
Daniel Nowak
Larry Parkinson
Douglas Roe
Frank Swigonski
Gary Will
17
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person
designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. §385.2010.
Dated at Rensselaer, NY this 21st day of January 2020.
/s/ Joy A. Zimberlin
Joy A. Zimberlin
New York Independent System Operator, Inc.
10 Krey Blvd.
Rensselaer, NY 12144 (518) 356-6207