Christopher J. Novak

Senior Counsel

 

 

January 17, 2020

 

 

The Honorable Kimberly D. Bose Secretary

Federal Energy Regulatory Commission 888 First Street, NE

Washington, DC 20426

 

Re:    Niagara Mohawk Power Corporation
Docket No. ER20-____-000

 

Filing of Small Generator Interconnection Agreement with LaChute Hydro Company, LLC

 

Dear Secretary Bose:

Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and Part 35 of the Federal Energy Regulatory Commission’s (“Commission”) regulations,2 Niagara
Mohawk Power Corporation d/b/a National Grid (“Niagara Mohawk”) submits for filing a Small Generator Interconnection Agreement (“Agreement”) between Niagara Mohawk and LaChute Hydro Company, LLC (“LaChute Hydro”), designated as Service
Agreement No. 2511 under the New York Independent System Operator, Inc.’s
(“NYISO”) Open Access Transmission Tariff (“OATT”).3  Niagara Mohawk requests that the Commission accept the Agreement effective as of the date agreed to by the
parties and set forth in the Agreement, December 19, 2019.


 

 

 

 

 

 

 

 

1

 

2

 

3


 

 

 

 

16 U.S.C. § 824d.

18 C.F.R. Part 35.
The Agreement is captioned as a Small Generator Interconnection Agreement (“SGIA”) because


its terms and conditions are based upon the terms and conditions of the Commission-approved pro forma
SGIA that was set forth in Appendix 7 of Attachment Z to the NYISO OATT at the time the Agreement
was finalized.  Niagara Mohawk uses this “modified SGIA” to document the interconnection of generators
when Commission jurisdiction does not attach or the NYISO is not required to be a party to the
interconnection agreement.  Interconnection pursuant to the Agreement is not subject to the NYISO’s Small
Generator Interconnection Procedures (Attachment Z to the NYISO OATT).  The Agreement does not
involve a new interconnection request, and thus the Agreement does not need to be a three-party agreement
that also includes the NYISO as a party and tracks the NYISO pro forma SGIA.  See New Eng. Power Co.,
109 FERC ¶ 61,364, at PP 12-13 (2004).  Differences between the NYISO pro forma SGIA and the
“modified SGIA” include the fact that the former is a three-party agreement including NYISO, while the
latter is written to be bilateral between Niagara Mohawk and the generator.

 

40 Sylvan Road, Waltham, MA  02451

T: 781-907-2112F: 781-907-5701Chris.Novak@nationalgrid.com
www.nationalgrid.com


 

 

The Honorable Kimberly D. Bose January 17, 2020

Page 2

 

I.Background

Niagara Mohawk is a public utility subject to the Commission’s jurisdiction that owns transmission facilities located in New York which have been placed under the
operational control of the NYISO.  LaChute Hydro, a subsidiary of Enel Green Power
North America, Inc., is a limited liability company organized and existing under the laws of the State of Delaware.

 

LaChute Hydro owns and operates two hydroelectric generating facilities with a
combined total capacity of approximately 9 MW that are located in Ticonderoga, New
York (the “Plants”).  Each Plant began operating in 1988 and is a Qualifying Facility
(“QF”).4

 

Niagara Mohawk and LaChute Hydro are parties to a power purchase agreement (“PPA”) for the full output of the Plants.  The PPA was first executed between Niagara Mohawk and International Paper Company in 1986 and was later assigned to LaChute Hydro.  The PPA has since been amended, most recently on December 19, 2019.
Pursuant to that last amendment, the term of the PPA extends through December 31, 2020 and provides for the PPA to be terminated upon 30 days’ notice.

 

II.Filing Obligation

Section 205 of the FPA authorizes the Commission to require utilities to file all
rates and charges that are “for or in connection with,” and all agreements that “affect or
relate to,” jurisdictional transmission or sales of electric energy.5  The Commission has
provided guidance regarding some of the specific agreements that must be filed under
this authority.  The Commission has found that “[i]nterconnection agreements between
utilities come within section 205 of the FPA.”6  The Commission has also explained that
its jurisdiction over an agreement “is limited to the provisions of the agreement that

facilitate the exchange of energy between the parties, i.e., the sale of electric energy at wholesale in interstate commerce.”7  As the activities covered by the provisions of the Agreement described above all relate to activities needed to facilitate the delivery of the Plants’ energy to the grid for sales at wholesale in interstate commerce, Niagara Mohawk believes that these provisions bring the Agreement within the Commission’s jurisdiction and make it subject to the Commission’s filing requirements.


 

 

 

 

 

 

4


 

 

 

See LaChute Hydro Co., Inc., et al., 42 FERC ¶ 62,214 (1988); LaChute Hydro Co., Inc., et al., 42


FERC ¶ 62,215 (1988).


 

5

 

6


16 U.S.C. §§ 824d(a), -(c).
Prior Notice and Filing Requirements Under Section II of the Federal Power Act, 64 FERC ¶


61,139, at 61,991 (1993).


 

7


PSI Energy, Inc., 56 FERC ¶ 61,237, at 61,908 n.4 (1991).


 

 

The Honorable Kimberly D. Bose January 17, 2020

Page 3

 

Pursuant to Commission policy, “[w]hen an electric utility . . . purchases the QF’s
total output, the state has authority over the interconnection and the allocation of
interconnection costs.  But when an electric utility interconnecting with a QF does not
purchase all of the QF’s output and instead transmits the QF’s power in interstate
commerce, the Commission exercises jurisdiction over the rates, terms, and conditions
affecting or related to such service, such as interconnections.”8  Further, where the
interconnected utility is on notice that a QF plans to make wholesale sales of its output to
a third party, either by way of contractual provisions or otherwise, the Commission has
exclusive jurisdiction over the interconnection between the QF and the interconnected
utility from the date the utility receives this notice, even where the QF has not engaged in
third-party sales or where the interconnected utility is still purchasing the full output of
the QF.9

 

As described above, LaChute Hydro currently sells the full output of the Plants to Niagara Mohawk pursuant to the PPA.  As such, any interconnection provisions in the PPA were not subject to Commission filing requirements.  LaChute Hydro is in the
process of taking the necessary steps with the NYISO to transition to a new power
purchase agreement with Green Mountain Power Corporation (“GMP”).  The new power purchase agreement will take effect upon the NYISO’s approval for the Plants to sell
their output into the wholesale market.  At that future time, the PPA between Niagara
Mohawk and LaChute Hydro will be terminated.

III. The Charges Authorized Under the Agreement Are Just and Reasonable

 

The Agreement states that Niagara Mohawk will bill LaChute Hydro for the

design, engineering, construction, and procurement costs of interconnection facilities and upgrades contemplated by the Agreement.10  The Agreement also states that LaChute Hydro is responsible for its share of all reasonable expenses, including overheads,
associated with operating, maintaining, repairing, and replacing the Niagara Mohawk interconnection facilities defined in the Agreement.11


 

 

 

 

 

 

8


 

 

 

Standardization of Small Generator Interconnection Agreement and Procedures, Order No. 2006,


FERC Stats. & Regs. ¶ 31,180, at P 516 (citation omitted) (2005) (“Order No. 2006”).


 

9


In Order No. 2006, the Commission explained that:

This Final Rule applies when the owner of the QF seeks interconnection with a facility subject to the OATT to sell any of the output of the QF to a third party.  This applies to a new QF that plans to sell any of its output to a third party and to an existing QF

interconnected with an electric utility or on-site customer that decides in the future to sell any of its output to a third party.


Id. at P 517.  See also Florida Power & Light Co., 133 FERC ¶ 61,121, at P 22 (2010).


 

10

 

11


Agreement, Article 6.1.1.
Agreement, Article 4.1.2.


 

 

The Honorable Kimberly D. Bose January 17, 2020

Page 4

 

IV.Effective Date

Niagara Mohawk requests that the Commission accept the Agreement effective as of the date agreed to by the parties and set forth in the Agreement, December 19, 2019. The Commission’s regulations require service agreements to be filed not more than 30 days after service under such an agreement has commenced.12  Niagara Mohawk is filing the Agreement within 30 days of the requested effective date.

 

V.Attachments

In addition to this transmittal letter, this filing includes the following attachments:

 

Attachment AThe Agreement between Niagara Mohawk and LaChute

Hydro; and

 

Attachment BA red-lined document showing differences between the

Agreement and the NYISO pro forma SGIA.

 

With the minor variations as depicted in Attachment B to this filing, the

Agreement follows the NYISO pro forma SGIA.  Therefore, the Commission should accept the Agreement as a two-party agreement.


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

18 C.F.R. § 35.3(a)(2).


 

 

The Honorable Kimberly D. Bose January 17, 2020

Page 5

 

VI.Communications

Communications and correspondence regarding this filing should be addressed to

the following individuals:


Christopher J. Novak Senior Counsel

National Grid USA
Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451-1120 (781) 907-2112

Chris.Novak@nationalgrid.com

 

Joseph Murphy

Acting Director, Commercial Services National Grid

40 Sylvan Road

Waltham, MA 02451 (781) 907-2007

Joseph.Murphy3@nationalgrid.com

 

VII.   Service


Sean Atkins

Bradley R. Miliauskas Alston & Bird LLP The Atlantic Building 950 F Street, NW

Washington, DC 20004 (202) 239-3300

sean.atkins@alston.com
bradley.miliauskas@alston.com


 

Copies of this filing have been served on LaChute Hydro, the NYISO, and the New York Public Service Commission.

 

VIII.   Conclusion

 

For the reasons stated herein, National Grid respectfully requests that the Commission accept the Agreement effective as of December 19, 2019.

 

Respectfully submitted,

 

/s/ Christopher J. Novak

Christopher J. Novak Senior Counsel

National Grid USA

Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451

 

Counsel for Niagara Mohawk Power Corporation