Christopher J. Novak

Senior Counsel

 

December 6, 2019

 

 

The Honorable Kimberly D. Bose Secretary

Federal Energy Regulatory Commission 888 First Street, NE

Washington, DC 20426

Re:    Niagara Mohawk Power Corporation
Docket No. ER20-____-000

Filing of Small Generator Interconnection Agreement with GR Catalyst Two LLC

Dear Secretary Bose:

 

Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and Part 35 of the
Federal Energy Regulatory Commission’s (“Commission”) regulations,2 Niagara
Mohawk Power Corporation d/b/a National Grid (“Niagara Mohawk”) submits for filing
a Small Generator Interconnection Agreement (“Agreement”) between Niagara Mohawk
and GR Catalyst Two LLC (“GR Catalyst Two”), designated as Service Agreement No.
2498 under the New York Independent System Operator, Inc.’s (“NYISO”) Open Access
Transmission Tariff (“OATT”).3  Niagara Mohawk requests that the Commission accept
the Agreement effective as of the date agreed to by the parties and set forth in the
Agreement, November 26, 2019.

 

I.Background

Niagara Mohawk is a public utility subject to the Commission’s jurisdiction that

owns transmission facilities located in New York which have been placed under the


 

 

1

 

2

 

3


16 U.S.C. § 824d.

18 C.F.R. Part 35.
The Agreement is captioned as a Small Generator Interconnection Agreement (“SGIA”) because


its terms and conditions are based upon the terms and conditions of the Commission-approved pro forma
SGIA that was set forth in Appendix 7 of Attachment Z to the NYISO OATT at the time the Agreement
was finalized.  Niagara Mohawk uses this “modified SGIA” to document the interconnection of generators
when Commission jurisdiction does not attach or the NYISO is not required to be a party to the
interconnection agreement.  Differences between the pro forma SGIA and the “modified SGIA” include the
fact that the former is a three-party agreement including NYISO, while the latter is written to be bilateral
between Niagara Mohawk and the generator.  Niagara Mohawk and GR Catalyst Two are executing this
two-party Agreement because NYISO notified Niagara Mohawk and GR Catalyst Two that the proposed
interconnection is not subject to NYISO’s Small Generator Interconnection Procedures (Attachment Z to
the NYISO OATT).

 

40 Sylvan Road, Waltham, MA  02451

T: 781-907-2112F: 781-907-5701Chris.Novak@nationalgrid.com
www.nationalgrid.com


 

 

The Honorable Kimberly D. Bose December 6, 2019

Page 2

 

operational control of the NYISO.  GR Catalyst Two is a limited liability company organized and existing under the laws of the State of New York.

 

GR Catalyst Two owns and operates a 12.265 MW small generating facility

located in Greenwich, New York (the “Plant”) that began commercial operation in 1987.4 The Plant is a Qualifying Facility (“QF”).

On January 22, 1987, Niagara Mohawk entered into a power purchase agreement
(“PPA”) with Stevens & Thompson Paper Company (“Stevens & Thompson”, the
previous owner of the Plant), pursuant to which Stevens & Thompson agreed to sell and
deliver, and Niagara Mohawk agreed to purchase and accept, all of the electric output
produced by the Plant.  The PPA expired on December 31, 2016.  The interconnection
and power purchase arrangements between Niagara Mohawk and GR Catalyst Two were
then set forth in a Letter of Agreement (the “First LOA”) between Niagara Mohawk and
Stevens & Thompson, executed by Niagara Mohawk on December 12, 2016 and by
Stevens & Thompson on December 2, 2016.  The First LOA was extended by a Letter of
Agreement (the “Second LOA”) between Niagara Mohawk and Stevens & Thompson,
executed by Niagara Mohawk on December 19, 2017 and by Stevens & Thompson on
December 15, 2017.  The Second LOA was extended by a Letter of Agreement (the
“Third LOA”) between Niagara Mohawk and Stevens & Thompson, executed by Niagara
Mohawk on November 5, 2018 and by Stevens & Thompson on November 7, 2018.  A
Consent to Assignment of Letter of Agreement was executed by Niagara Mohawk on
April 2, 2019 and by Stevens & Thompson and GR Catalyst Two LLC on March 28,
2019.  Following the fulfillment of Niagara Mohawk and GR Catalyst Two obligations
under the Agreement, including but not limited to the installation of certain
interconnection equipment, GR Catalyst Two can begin selling the output of the Plant to
entities other than Niagara Mohawk at wholesale in interstate commerce.

II.Filing Obligation

Section 205 of the FPA authorizes the Commission to require utilities to file all
rates and charges that are “for or in connection with,” and all agreements that “affect or
relate to,” jurisdictional transmission or sales of electric energy.5  The Commission has
provided guidance regarding some of the specific agreements that must be filed under
this authority.  The Commission has found that “[i]nterconnection agreements between
utilities come within section 205 of the FPA.”6  The Commission has also explained that
its jurisdiction over an agreement “is limited to the provisions of the agreement that

facilitate the exchange of energy between the parties, i.e., the sale of electric energy at


 

 

4


The Plant was formerly owned and operated by Stevens & Thompson Paper Company, Inc.


(“Stevens & Thompson”).  See Stevens & Thompson Paper Co., Inc. and GR Catalyst Two, LLC, 167


FERC ¶ 62,071 (2019) (order approving transfer of license for the Plant to GR Catalyst Two).


 

5

 

6


16 U.S.C. §§ 824d(a), -(c).
Prior Notice and Filing Requirements Under Section II of the Federal Power Act, 64 FERC ¶


61,139, at 61,991 (1993).


 

 

The Honorable Kimberly D. Bose December 6, 2019

Page 3

 

wholesale in interstate commerce.”7  As the activities covered by the provisions of the Agreement described above all relate to activities needed to facilitate the delivery of the Plant’s energy to the grid for sales at wholesale in interstate commerce, Niagara Mohawk believes that these provisions bring the Agreement within the Commission’s jurisdiction and make it subject to the Commission’s filing requirements.

Pursuant to Commission policy, “[w]hen an electric utility . . . purchases the QF’s
total output, the state has authority over the interconnection and the allocation of
interconnection costs.  But when an electric utility interconnecting with a QF does not
purchase all of the QF’s output and instead transmits the QF’s power in interstate
commerce, the Commission exercises jurisdiction over the rates, terms, and conditions
affecting or related to such service, such as interconnections.”8  Further, where the
interconnected utility is on notice that a QF plans to make wholesale sales of its output to
a third party, either by way of contractual provisions or otherwise, the Commission has
exclusive jurisdiction over the interconnection between the QF and the interconnected
utility from the date the utility receives this notice, even where the QF has not engaged in
third-party sales or where the interconnected utility is still purchasing the full output of
the QF.9

 

GR Catalyst Two has notified Niagara Mohawk that it intends to terminate the Third LOA upon the Commission’s acceptance of the Agreement and following the
fulfillment of Niagara Mohawk and GR Catalyst Two obligations under the Agreement, including but not limited to the installation of certain interconnection equipment required to facilitate GR Catalyst Two’s participation in NYISO wholesale markets.

 

III. The Charges Authorized Under the Agreement Are Just and Reasonable

The Agreement states that Niagara Mohawk will bill GR Catalyst Two for the

design, engineering, construction, and procurement costs of interconnection facilities and upgrades contemplated by the Agreement.10  The Agreement also states that GR Catalyst Two is responsible for its share of all reasonable expenses, including overheads,


 

 

 

 

7

 

8


PSI Energy, Inc., 56 FERC ¶ 61,237, at 61,908 n.4 (1991).
Standardization of Small Generator Interconnection Agreement and Procedures, Order No. 2006,


FERC Stats. & Regs. ¶ 31,180, at P 516 (citation omitted) (2005) (“Order No. 2006”).


 

9


In Order No. 2006, the Commission explained that:

This Final Rule applies when the owner of the QF seeks interconnection with a facility subject to the OATT to sell any of the output of the QF to a third party.  This applies to a new QF that plans to sell any of its output to a third party and to an existing QF

interconnected with an electric utility or on-site customer that decides in the future to sell any of its output to a third party.


Id. at P 517.  See also Florida Power & Light Co., 133 FERC ¶ 61,121, at P 22 (2010).


 

10


Agreement, Article 6 (first paragraph).


 

 

The Honorable Kimberly D. Bose December 6, 2019

Page 4

 

associated with operating, maintaining, repairing, and replacing the Niagara Mohawk interconnection facilities defined in the Agreement.11

 

IV.Effective Date

Niagara Mohawk requests that the Commission accept the Agreement effective as of the date agreed to by the parties and set forth in the Agreement, November 26, 2019. The Commission’s regulations require service agreements to be filed not more than 30 days after service under such an agreement has commenced.12  Niagara Mohawk is filing the Agreement within 30 days of the requested effective date.

 

V.Attachments

In addition to this transmittal letter, this filing includes the following attachments:

 

Attachment AAgreement between Niagara Mohawk and GR Catalyst

Two LLC dated November 26, 2019.

 

Attachment BRed-lined document showing differences between

Agreement between (1) Niagara Mohawk and GR Catalyst Two LLC dated November 26, 2019 and (2) NYISO pro forma SGIA.

 

With the minor variations as depicted in Attachment B to this filing, the

Agreement follows the NYISO pro forma SGIA.  Therefore, the Commission should accept the Agreement as a two-party agreement.


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

11

 

12


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Agreement, Article 4 (second paragraph).

18 C.F.R. § 35.3(a)(2).


 

 

The Honorable Kimberly D. Bose December 6, 2019

Page 5

 

VI.Communications

Communications and correspondence regarding this filing should be addressed to

the following individuals:


Christopher J. Novak Senior Counsel

National Grid USA Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451-1120 (781) 907-2112

Chris.Novak@nationalgrid.com

 

 

Kathryn Cox-Arslan

Director, Commercial Services

National Grid USA Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451-1120 (781) 907-2406

Kathryn.Cox@nationalgrid.com

 

VII.   Service


Sean Atkins

Bradley R. Miliauskas Alston & Bird LLP The Atlantic Building 950 F Street, NW

Washington, DC 20004 (202) 239-3300

sean.atkins@alston.com
bradley.miliauskas@alston.com


 

Copies of this filing have been served on GR Catalyst Two, the NYISO, and the New York Public Service Commission.

 

VIII.   Conclusion

 

For the reasons stated herein, National Grid respectfully requests that the Commission accept the Agreement effective as of November 26, 2019.

 

Respectfully submitted,

 

/s/ Christopher J. Novak

Christopher J. Novak Senior Counsel

National Grid USA Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451

Counsel for National Grid USA