COUCH WHITE, LLP

counselors and attorneys at law

 

October 9, 2019

 

The Honorable Kimberly D. Bose Secretary

Federal Energy Regulatory Commission 888 First Street, N.E.

Washington, DC  20426

 

Re:    Rochester Gas and Electric Corporation

Interconnection Agreement with RED-Rochester, LLC ER20-______-000

Request for Expedited Comment Period and Waiver of 60-day Prior Notice Period

Dear Secretary Bose:

Pursuant to Section 205 of the Federal Power Act, 16 U.S.C. § 824d and Section 35 of
the Federal Energy Regulatory Commission’s (“Commission”)  regulations, Rochester Gas and
Electric Corporation  (“RGE”) and RED-Rochester LLC (“RED”) jointly submit an Amended
and Restated Interconnection Agreement (“IA”) between RGE and RED.  For the reasons
discussed below, RGE and RED jointly request a shortened comment period on this filing and
waiver of the 60-day prior notice period with expedited Commission action to permit the IA to
become effective as of September 16, 2019. The IA is labeled as Service Agreement No. 2484
under the New York Independent System Operator, Inc.’s (“NYISO”) Open Access
Transmission Tariff.

I.DESCRIPTION OF PARTIES

 

RGE is public utility subject to the Commission’s jurisdiction that owns transmission facilities under the operational control of the NYISO. RGE serves residential, commercial, and industrial retail electric customers in its service territory in and near Rochester, New York, which territory contains a population of approximately 900,000.

RED is a private company owned by Ironclad Energy Ventures LLC, a joint venture of
Ironclad Energy Partners and Stonepeak Infrastructure Partners.  RED owns and operates the
former Eastman Kodak industrial complex in Rochester, New York, now known as the Eastman
Business Park (“Park”).  RED also owns and operates a series of generating units located within
the Park that provide electricity, steam, and refrigeration to the businesses operating within the
Park.


 

 

 

 

COUCH WHITE, LLP

counselors and attorneys at law

II. BACKGROUND AND OVERVIEW OF THE FILING

 

The generation facilities within the Park were initially constructed to support Kodak’s

manufacturing operations.  In total, the generating capacity is approximately 117 MW.  The Park is also connected to RGE’s electric distribution system.

The electric generation facilities have been considered Qualifying Facilities under the Public Utility Regulatory Policies Act and Section 2 of the New York Public Service Law. For many years, the entire output from the generation facilities was utilized by the manufacturing operations.  As the on-site demand declined, some of the excess power was sold to RGE in accordance with applicable law and a bilateral agreement between the parties.

Because a portion of the output of the electric generation facilities always has been

needed to serve the Park’s businesses, there has been no reason to install interconnection

facilities with RGE equal to the total output from the on-site generation.  Because of the limited
capacity of those facilities, the ability to export power from the Park onto RGE’s electric system
was and is limited to approximately 41 MW.  At this time, there are no plans to modify the
interconnection facilities or otherwise add equipment to increase the power flows into or out of
the Park.

A few years ago, the NYISO undertook a project to establish market and operational

rules to allow facilities such as the Park (collectively known as “Behind-the-Meter Net

Generators”) to participate in NYISO’s markets as suppliers. The rule changes were approved by the Commission in 2016.1  RED qualifies as a Behind-the-Meter Net Generator and is desirous of becoming a participant in the NYISO’s wholesale markets as such.  It is now in the process of registering as a market participant with NYISO.

As part of the governance of the relationship between RGE and RED, the parties entered
into an interconnection agreement that was subject to the oversight of the New York Public
Service Commission and consistent with New York policies and procedures.  During the
registration process, NYISO informed RGE and RED that their interconnection agreement would
need to be revised to be subject to the Commission’s oversight and jurisdiction.  However,
NYISO indicated that because the agreement was preexisting and would remain a two-party
agreement, the use of NYISO’s pro forma large generator interconnection agreement (“LGIA”)
would not be required.

The original interconnection agreement had been rigorously negotiated, and the parties

agreed that they preferred to continue those terms to the maximum extent possible.  Accordingly,
they agreed to amend their agreement to conform to the LGIA to the extent possible without
substantively changing their respective obligations and commitments.  The IA that is the subject

 

 

1 New York Indep. Sys. Op., 155 FERC ¶ 61,166 (2016).


 

 

 

 

COUCH WHITE, LLP

counselors and attorneys at law

of this matter, and which is attached to this transmittal letter, is the product of the parties’ efforts.
Although NYISO is not a signatory to the IA, NYISO has reviewed the document and provided
advice and guidance to the parties regarding its provisions.  The parties modified the IA based on
that advice and guidance, and NYISO authorized RGE to report that NYISO has no objections to
the IA.

RED would like to begin participating in NYISO’s markets as expeditiously as possible. As part of the requirements to do so, it needs to have a Commission-jurisdictional
interconnection agreement in place.  Most other registration steps have been completed, and
RED anticipates being able to commence selling energy by November 2019, with capacity sales commencing shortly thereafter. RED’s ability to do so is contingent, in part, on this IA being
filed with the Commission.  In the event that RED is able to commence selling energy before the Commission takes action on this filing, RED’s participation will be conditional until it receives Commission approval or acceptance of the IA.

The Parties respectfully request a shortened comment period, expedited Commission
action and an effective date of September 16, 2019 for the IA.  That effective date will help
ensure that RED is fully able to participate in NYISO’s markets as soon as possible, and that there will be no question or dispute regarding RED’s legal ability to do so.  Further, until such time as RED commences participation in NYISO’s markets, the existing interconnection
agreement between the parties will remain in effect.  Setting the effective date for the IA as the date of execution of the IA will ensure that there is certainty and clarity between the parties
regarding when the new terms take effect and that there will not be any gaps in coverage
between the existing and new agreements.  That is, the IA provides that the termination date of the existing interconnection agreement will be the date of execution of the IA.  If the effective date of the IA is some date after the execution date, there will be a period of time when neither agreement is in effect - a possibility that neither party wants.

III.DESCRIPTION OF IA

 

The rates, terms, and conditions of the IA were agreed to by RGE and RED and are generally consistent with the Pro Forma LGIA. Key differences include:

  Because of the nature and configuration of RED’s generation facilities and the Park’s
connection to RGE’s distribution system, some provisions from the Parties’ initial
interconnection agreement, including a requirement that RED bear all costs
associated with any changes required to RGE’s electric system to accommodate
RED’s present and future needs, were deemed to be more comprehensive and provide
more clarity than the similar terms of the pro forma LGIA;

  The LGIA provisions generally make reference to a single interconnection point

between a generating facility and a transmission owner’s transmission system.  Here,
however, the interconnection is with RGE’s distribution system, and there are
multiple generating units connected to RGE’s distribution system at three discrete


 

 

 

 

COUCH WHITE, LLP

counselors and attorneys at law

locations.  The parties’ initial interconnection agreement better reflected this unique arrangement than the terms of the pro forma LGIA;

Other provisions of the pro forma LGIA are relevant only to new interconnections,

but no new interconnections or equipment are required for RED to commence

participation in NYISO’s markets, and no additional work or incurrence of

interconnection-related costs is contemplated.  RGE and RED respectfully submit
that, in total, the differences between the IA and pro forma LGIA satisfy the
Commission’s “consistent with or superior to” standard for deviations from the pro
forma LGIA;2

The pro forma LGIA includes NYISO as a party.  As noted above and below, NYISO

is not a party to the IA.  However, the provisions of the pro forma LGIA that give

certain rights to NYISO are included in the IA such that it essentially is the equivalent of the LGIA from NYISO’s perspective.  This approach is consistent with the other pre-existing PURPA-type interconnection agreements that were converted, inter alia, from New York Public Service Commission to Commission-jurisdictional
documents.  As in the prior cases, the IA here does not involve a proposed increase in capacity or material modifications to any existing facilities;3

Additional differences agreed upon by RGE and RED to reflect the unique

circumstance of the interconnection.

The Parties respectfully request that the Commission accept the IA for filing as executed as submitted with this letter.

IV.REQUEST FOR CEII TREATMENT

Pursuant to the Commission’s regulations at 18 C.F.R. §388.112 and 18 C.F.R. §

388.113, the Parties request that the one-line diagrams included as part of Appendix D to the

Agreement  be protected from disclosure as Critical Energy Infrastructure Information (“CEII”).
The one-line diagrams contain one-line schematics of the electric substation which, if disclosed,
could pose a threat to the security and the reliability of the New York State bulk power
system.  These diagrams provide more than simply the general location of critical infrastructure.
Unlike publicly available maps of power transmission lines and generation and substation
facilities, these diagrams provide the exact nature, specific location, and additional potentially

 

 

2 Standardization of Generator Interconnection Agreements and Procedure, Order No. 2003 at P 26, FERC Stats. &
Regs., ¶ 31,146 (2003), order on reh'g, Order No. 2003-A, FERC Stats. & Regs., ¶ 31,160, order on reb'g, Order
No. 2003-B, FERC Stats. & Regs., ¶ 31,171 (2004), order on reh'g, Order No. 2003-C, FERC Stats. & Regs., ¶
31,190 (2005), aff’d sub nom. Natl. Assn. of Regulatory Util. Commrs. v. FERC, 475 F.3d 1277 (D.C. Cir. 2007).

3 See, e.g., Niagara Mohawk Power Corporation d/b/a National Grid, 121 FERC ¶ 61,104 at P 22 (2007).


 

 

 

 

COUCH WHITE, LLP

counselors and attorneys at law

harmful information of facilities and transmission lines used to maintain the reliability of the

New York State bulk power system.  They reveal critical information related to the facilities and transmission lines depicted therein that, if disclosed, could be useful to a person seeking to
disable the power grid.

Therefore, the disclosure of these CEII diagrams would pose a threat to the reliability of
the New York State bulk power system and to the health and safety of New York
residents.  Moreover, the information revealed in these diagrams reveals CEII that FERC has
determined to be exempt from mandatory disclosure under 5 U.S.C. § 552(b)(7)(F).  These
diagrams have been omitted from the Public version of the Interconnection Agreement included
in this filing. The diagrams are included only in the CEII version of the Interconnection
Agreement in the filing.

 

V.REQUEST FOR SHORTENED COMMENT PERIOD AND PROPOSED

EFFECTIVE DATE

The Parties respectfully request that the Commission grant waiver of the 60-day notice
requirement and accept the IA effective September 16, 2019.  The Commission’s regulations
specify that tariff filings will normally become effective after a 60-day notice period and that 21
days will normally be allowed for interested parties to submit protests.4  The Commission has
discretion, however, to shorten both periods for good cause.  As the Commission noted in
Central Hudson Gas & Electric Corp.,5 waiver of the 60-day prior notice requirement is
appropriate where the customer and the utility agree and where there is no rate impact:

[W]aiver of the notice requirement will generally be appropriate

when an uncontested filing has no rate impact or when a filing reduces rates or charges, or when a rate increase and its effective date are prescribed by a contract on file with the Commission or by a settlement agreement accepted by the Commission.6

In this case, there is good cause for the Commission to grant this waiver because waiver
of the notice will not have a rate impact and both RGE and RED support the instant filing and
the requested effective date. .  The Commission previously has granted waiver of the 60-day
prior notice requirement where an agreement was filed within 30 days of the commencement of
service.7

 

 

 

 

4 See 18 C.F.R. §§ 35.3 and 35.8.

5 Central Hudson Gas & Electric Corp., 60 FERC ¶ 61,089 (1992).

6 Id., slip op at 2.

7 See, e.g., Ameren Illinois Co., Docket No. ER15-370-000 (Dec. 15, 2014) (unpublished letter order); S. Cal.

Edison Co., Docket No. ER15-76-000 (Nov. 17, 2014) (unpublished letter order); MidAmerican Energy Co., Docket No. ER13-2399-000 (Nov. 6, 2013) (unpublished letter order).


 

 

 

 

COUCH WHITE, LLP

counselors and attorneys at law

The Parties respectfully request a waiver of any Commission requirements not

specifically addressed herein necessary to allow the IA to become effective as of September 16,
2019.

VI.COMMUNICATIONS

The individuals indicated below are designated for service under Rule 2010 of FERC’s

Rules of Practice and Procedure.  Please direct all correspondence and communications

regarding this filing to:8


 

Justin Atkins Counsel

Avangrid Service Company One City Center 5th Floor Portland, ME 04101

207.629.1293

Justin.atkins@avangrid.com

 

Kevin M. Lang, Esq.
Couch White, LLP

Counsel for RED-Rochester, LLC 540 Broadway

P.O. Box 22222

Albany, NY  12201-2222 518-320-3421

klang@couchwhite.com

 

VII.   CONTENTS OF FILING


Timothy J. Lynch

Director - Electric Transmission Services
New York State Electric & Gas Corporation

18 Link Drive, PO Box 5224

Binghamton, NY 13902 585.484.6352

tjlynch@nyseg.com


 

In accordance with the Commission’s eTariff regulations and other filing requirements,9 in addition to this transmittal letter this filing consists of:

  the CEII Version of the IA; and

  the Public Version of the IA.

Copies of this filing have been served upon the New York Public Service Commission and NYISO.

 

 

 

 

8 The Parties respectfully request waiver of 18 C.F.R. § 385.203(b)(3) to allow more than two persons to be added to the service list in this proceeding.

9 18 C.F.R. § 35.3(a)(2).


 

 

 

 

COUCH WHITE, LLP

counselors and attorneys at law

Please feel free to contact the undersigned with any questions concerning the instant filing.  Thank you for your assistance in this matter.

 

Respectfully submitted,

 

 

/s/ Justin Atkins/s/ Kevin M. Lang

Justin AtkinsKevin M. Lang

Counsel for Rochester Gas and ElectricCounsel for RED-Rochester, LLC

Corporation