UNITED STATES OF
AMERICA BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
New York Independent System)Docket No. ER18--000
Operator, Inc.)
PETITION FOR TEMPORARY TARIFF WAIVERS, REQUEST FOR SHORTENED
NOTICE AND COMMENT PERIOD, AND
REQUEST FOR EXPEDITED COMMISSION ACTION BY JANUARY 10, 2018
The New York Independent System Operator, Inc. (“NYISO”) respectfully submits this
“Petition” pursuant to Rule 2071 of the Commission’s Rules of Practice and Procedure for
temporary waivers of Sections 21.4 and 21.5.1 of its Market Administration and Control Area
Services Tariff (“Services Tariff”). Granting these requested waivers will temporarily enable the
NYISO to consider Incremental Energy and Minimum Generation2 offers that exceed
$1000/MWh and compensate Generators that are able to demonstrate that they actually incurred
variable costs in excess of $1000/MWh to provide Incremental Energy or Minimum Generation.
As discussed below, extreme winter weather and extreme natural gas market conditions have driven certain gas-fired Generators’ fuel costs to levels that could exceed $1000/MWh. The requested waivers are therefore necessary to ensure the reliable operation of the New York State Power System and that Generators are made whole for their costs of producing Energy. The waivers are consistent with Commission precedent3 because they are needed to remedy a concrete problem, are narrowly drawn, and will not have adverse consequences.
1 18 CFR § 385.207 (2017).
2 Capitalized terms that are not defined in this Petition have the meaning ascribed to them in Section 2 of the NYISO’s Market Administration and Control Area Services Tariff (“Services Tariff”).
3 See, e.g., New York Independent System Operator, Inc., 146 FERC ¶ 61,061 (2014) (granting petition seeking waiver to allow NYISO pay demonstrated actual costs of offers that exceeded $1,000/MWh).
The NYISO requests that these temporary waivers be made effective immediately in the Real-Time Market, i.e., starting today, January 4, 2018, and remain in effect through February
28, 2018, i.e., for the remainder of the coldest portion of the winter season, and in the Day-
Ahead Market from January 5, 2018 through February 28, 2018. The NYISO also respectfully
asks that the Commission grant any other waivers, or authorize any other actions, that it deems
necessary to enable the NYISO to preserve reliability and ensure that Generators are made whole for their costs during this period.
The NYISO respectfully requests that the Commission act expeditiously, and either
waive or abbreviate to the maximum extent possible any notice and comment procedures, so that it may issue an order granting the requested waivers by January 10, 2018.4
I.THE NEED FOR EMERGENCY ACTION
The extreme cold weather that New York (and much of the Eastern United States) is
experiencing has caused a significant spike in natural gas prices. These extreme natural gas
prices are, in turn, significantly increasing the cost of producing electric Energy in New York. The purpose of this waiver filing is to protect the reliability of the New York State Power System by providing New York Control Area (“NYCA”) Generators that must operate on natural gas the opportunity to recover the actual costs that they incur to operate should those costs exceed the $1,000/MWh Bid Restriction5 that limits the NYISO’s authority to consider Incremental Energy Bids and Minimum Generation Bids that exceed this amount.
4 The NYISO’s external Market Monitoring Unit, Potomac Economics, has indicated that it supports this filing.
5 See NYISO Market Services Tarff Section 21.4.
2
Commission Order No. 8316 instructed the NYISO to increase its offer cap to
$2,000/MWh to address circumstances similar to those addressed in this petition. In the
NYISO’s compliance filings, including the pending submittal filed December 8, 2017, the
NYISO committed to implement software necessary to support its Order No. 831 obligations by the end of 2018.7
II.DESCRIPTION OF REQUEST FOR WAIVERS
A.Background—Extremely Cold Weather and High Natural Gas Prices
Are Increasing the Cost of Producing Electricity in New York
New York is in the throes of a cold snap that began on December 25, 2017. It is not
expected to end until January 8, 2018, or later. Daily low temperatures in New York City during
this cold snap are expected to range from 3 degrees to 30 degrees Fahrenheit. This is
approximately 24 degrees below average for New York City at this time of year.
The natural gas prices that the NYCA is experiencing during this cold snap could cause some NYCA Generators’ costs to exceed the $1,000/MWh Bid Restriction. The January 5, 2018 day-ahead index price for natural gas at the Transco Z6 NY8 hub was more than $48.99/MMBtu. $48.99/MMBtu is more than double the highest price posted for that hub in 2016 and 2017. The January 5, 2018 day-ahead index price is six times higher than the $6.96/MMBtu average price at the Transco Z6 NY hub in December 2017. During January and February 2017, the average
Transco Z6 NY natural gas prices were $3.62/MMBtu and $2.89/MMBtu respectively. During
6 See Order No. 831, Offer Caps in Markets Operated by Regional Transmission Organizations and Independent System Operators, 157 FERC ¶ 61,115 (2016); on reh’g, Order No. 831-A, 161 FERC ¶ 61,156 (2017); New York Independent System Operator, Inc., 161 FERC ¶ 61,151 (2017).
7 See NYISO’s May 8, 2017 compliance filing in Docket No. ER17-1561 at 16-17; New York Independent System Operator, Inc., 161 FERC ¶ 61,151 at Ordering Paragraph (C).
8 Transco Z6 NY is the natural gas pipeline index price that determines the natural gas price incurred by Generators in and around New York City.
3
the cold weather in winter 2016 - 2017 the Transco Z6 NY natural gas price ranged from
approximately $2.04/MMBtu to $7.62/MMBtu, with only one day higher at $17.78/MMBtu. The
average Transco Z6 NY price for the entire 2016 - 2017 winter was $3.52/MMBtu. The
January 5, 2018 day-ahead index price of $48.99/MMBtu is more than five times the highest
price seen at the Transco Z6 NY hub in January or February of 2017 ($7.62/MMBtu).
Natural gas trades at prices greater than $100/MMBtu for Transco Z6 NY have already been observed for the January 6, 2018 gas day. Natural gas trades at prices greater than
$90/MMBtu have already been observed for other trading hubs that are used by New York
generators on that day.
B.The NYISO Proposes to Permit Generators to Submit and Recover
Actual Costs they Incur to Provide Incremental Energy and Minimum
Generation
If the Commission grants the NYISO’s waiver request, the NYISO will reimburse affected
generation resources for their demonstrated, actual costs of producing Incremental Energy and/or
Minimum Generation that exceed the $1,000/MWh Bid Restriction, via a Bid Production Cost
Guarantee. The supplemental payment will be available for both Day-Ahead and Real-Time
Market commitments. Additional costs incurred to commit Generators that are needed for
reliability will be recovered in accordance with the rules set forth in Rate Schedule 1 of the
NYISO’s Open Access Transmission Tariff.9 Until it implements its Order No. 831 compliance
obligations (by the end of 2018) the NYISO is not able to permit, and is not seeking authority to
permit Incremental Energy offers in excess of $1,000/MWh to set prices in its Day-Ahead or
Real-Time Markets.
9 See Section 4.1.8 of the Services Tariff.
4
The NYISO proposes to require Generators that will incur variable costs in excess of
$1,000/MWh to provide Incremental Energy or Minimum Generation to the NYISO to comply with the requirements set forth below in order to be eligible to recover their actual, demonstrated costs in excess of the Bid Restriction:
1. The Market Party responsible for offering the Generator must submit a Bid of
$1,000/MWh for the (portion of the) Minimum Generation and Incremental Energy MWs that it expects to incur an incremental cost of greater than $1,000/MWh to provide; and
2. The Market Party responsible for offering a Generator that expects to incur
incremental costs in excess of $1,000/MWh to provide Minimum Generation or Incremental Energy must submit an e-mail to the NYISO’s Stakeholder
Services Department at Stakeholder_Services@NYISO.com specifying the fuel cost it expects to incur10; and
3. When it obtains documents substantiating the fuel costs incurred, the Market
Party responsible for offering a Generator must e-mail supporting
documentation to the NYISO’s Stakeholder Services Department at the address provided above. The Market Party must submit documents evidencing the actual fuel costs it incurred.
Eligibility to recover costs in excess of the $1,000/MWh cap will be determined after-the-
fact and will be limited to demonstrated, actual production costs incurred. Generators will be
expected to offer into the NYISO’s markets based on the lowest cost fuel available. The NYISO
will notify Market Parties responsible for offering generation into its markets of their obligations
10 The NYISO requests that e-mail notice also be provided to the responsible Market Participant’s stakeholder services representative, but this additional notice is not mandatory.
5
to comply with the Commission’s Market Behavior Rules (18 C.F.R. § 35.41) and the
requirements of the Market Mitigation Measures that are set forth in Attachment H to the NYISO’s Services Tariff.
C. The NYISO Requests a Temporary, Limited Waiver of the Requirement
that it Reject All Incremental Energy and Minimum Generation Bids that Exceed that +/-$1,000/MWh Limit
The NYISO requests a temporary, limited waiver of the provisions of Sections 21.4 and
21.5.1 of Attachment F to its Services Tariff that require it to summarily reject Day-Ahead and
Real-Time Market Incremental Energy Bids and Minimum Generation Bids that exceed the
+/-$1,000/MWh Bid Restriction. Granting the requested waiver will enable the NYISO to
compensate Market Parties for the actual costs they incur to produce Incremental Energy and
Minimum Generation from their Generators at times when natural gas prices are extremely high.
Granting the NYISO’s requested waiver is appropriate because it will provide assurance to NYCA generation owners that they will have a reasonable opportunity to recover the costs they incur to provide Incremental Energy and/or Minimum Generation. Failure to implement
measures to permit generation owners to recover the costs they incur to supply Incremental
Energy and/or Minimum Generation could reduce participation in the markets that the NYISO
administers. Such a result could be detrimental to reliability.
Accordingly, the NYISO respectfully requests the Commission waive the identified
Services Tariff requirements for a period commencing January 4, 2018 and concluding at the
end of the day on February 28, 2018 for the Real-Time Market, and commencing January 5,
2018 and concluding at the end of the day on February 28, 2018 for the Day-Ahead Market.
6
III.COMPLIANCE WITH THE COMMISSION’S WAIVER PRECEDENT
The Commission has traditionally granted tariff waiver requests when: (i) the underlying error (if any) was made in good faith; (ii) the waiver request is limited in scope; (iii) a concrete problem needed, or needs, to be remedied, and (iv) the request did not have undesirable
consequences such as harming third parties.11
All of these criteria are satisfied in this proceeding. The requested waivers address
weather and market conditions that threaten the reliability of the New York State Power System. There can be no question that the NYISO is acting in good faith by taking prompt action to
ensure that Generators are given the opportunity to recover demonstrated, actual costs of
producing Incremental Energy and Minimum Generation. When initially implemented, the Bid Restrictions that the NYISO is seeking to waive did not contemplate the extreme natural gas
prices that are currently driving up the cost of producing electric Energy. The NYISO has
committed to implement its FERC Order No. 831 compliance revisions to address the concern
raised in this petition by the end of 2018.
The requested waivers are limited in scope to the minimum necessary to address the issues
facing the NYCA. As described above, the requested waivers include safeguards against over-
compensating Generators and are limited in duration. The NYISO’s proposal relies on existing
tariff mechanisms, such as the existing Bid Production Cost Guarantee rules, as much as possible.
The requested waivers address a “concrete problem.” Absent the requested waivers,
certain Generators might be required to provide service needed to support reliability without
11 See, e.g., New York Independent System Operator, Inc., 144 FERC ¶ 61,147 at P 8 (2013); New York Independent System Operator, Inc., 139 FERC ¶ 61,108 at P 14 (2012); PJM Interconnection, L.L.C., 137 FERC ¶ 61,184 at P 13 (2011); ISO New England, Inc., 134 FERC ¶ 61,182 at P 8 (2011); California Independent System Operator Corp., 132 FERC ¶ 61,004 at P 10 (2010); accord ISO New England Inc. -EnerNOC, Inc., 122 FERC ¶ 61,297 (2008);
Central Vermont Public Service Corp., 121 FERC ¶ 61,225 (2007); Waterbury Generation LLC, 120 FERC ¶ 61,007 (2007); Acushnet Co., 122 FERC ¶ 61,045 (2008).
7
being able to recoup a portion of the incremental operating costs that they incur. This would present Generators with an undesirable financial incentive not to offer to provide service at a time when the Generator is needed.
Finally, the requested waivers will not have undesirable consequences, such as harming the legitimate interests of third parties. Increasing payments to Generators so that they are made whole for the actual costs they incur to provide Minimum Generation and Incremental Energy that the NYISO schedules will increase the costs ultimately paid by Loads. However, such increased costs should not be viewed as “harming” Loads because they are necessary to ensure continued, reliable electric service during extreme weather conditions, as explained above.
IV.REQUEST FOR EXPEDITED COMMISSION ACTION BY JANUARY 10, 2018
AND FOR PROCEDURAL WAIVERS
The NYISO respectfully requests that the Commission act expeditiously and issue an order granting the requested waivers by January 10, 2018. The NYISO also requests that the Commission either waive or shorten to the maximum extent possible any notice and comment periods that would otherwise apply to this petition, so that it may issue an order by that date and make the temporary waivers effective on the dates specified above. Commission action within that time frame will permit Generators to recover their actual, demonstrated costs through the NYISO-administered markets and ameliorate a threat to reliability. It would also be consistent with other Commission orders granting independent system operators expedited waivers to
address unexpected winter-related natural gas market issues.12
12 See, e.g., PJM Interconnection, L.L.C., 146 FERC ¶ 61,003 (2014) (Accepting requested waivers to facilitate gaselectric communications and coordination in the face of “extreme” winter weather conditions three days after the waiver request was filed).
8
Similarly, there is ample justification to allow the temporary waivers for the Real-Time
and Day-Ahead Markets to take effect on January 4 and January 5, respectively. As discussed
above, severe weather conditions and extreme natural gas prices could prevent Generators that
must operate on natural gas from having an opportunity to recover their actual costs. This
market issue will be addressed by the end of 2018 when the NYISO completes its
implementation of Order No. 831’s requirements. Making the requested temporary waivers
effective on the NYISO’s proposed effective dates will address this issue on an interim basis
while also supporting reliability.
V.COMMUNICATIONS
All communications and service in this proceeding should be directed to:
Robert E. Fernandez, General Counsel
*Raymond Stalter, Director, Regulatory Affairs *Alex M. Schnell, Assistant General Counsel/
Registered Corporate Counsel
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-6000
rstalter@nyiso.com
aschnell@nyiso.com
*Persons designated for receipt of service.
VI.SERVICE
This filing will be posted on the NYISO’s website at www.nyiso.com. In addition, the
NYISO will e-mail an electronic link to this filing to each of its customers, to each participant on its stakeholder committees, to the New York Public Service Commission, and to the New Jersey Board of Public Utilities.
9
VII.CONCLUSION
For the reasons specified above, the New York Independent System Operator, Inc.
respectfully petitions the Commission to expeditiously issue an order granting the temporary waivers requested herein by January 10, 2018.
Respectfully submitted,
/s/ Alex M. Schnell
Alex M. Schnell, Assistant General Counsel/ Registered Corporate Counsel
New York Independent System Operator, Inc.
Dated: January 4, 2018
cc:Michael Bardee
Anna Cochrane
James Danly
Jette Gebhart
Kurt Longo
David Morenoff
Daniel Nowak
Larry Parkinson
J. Arnold Quinn
Douglas Roe
Kathleen Schnorf Gary Will
10
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person
designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. §385.2010.
Dated at Rensselaer, NY this 4th day of January, 2018.
/s/ Joy A. Zimberlin
Joy A. Zimberlin
New York Independent System Operator, Inc.
10 Krey Blvd.
Rensselaer, NY 12144 (518) 356-6207