UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Bayonne Energy Center, LLC)Docket No. ER17-1652-000
MOTION TO INTERVENE AND COMMENTS OF
THE NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.
In accordance with the Commission’s May 23, 2017 Combined Notice of Filings and with
Rules 212 and 213 of the Commission’s Rules of Practice and Procedure,1 the New York
Independent System Operator, Inc. (“NYISO”) moves to intervene and submit comments in the
above-captioned proceeding. The NYISO requests that the Commission consider these
comments in its evaluation of whether to grant Bayonne Energy Center, LLC’s (“BEC”) request
for a one-time, limited waiver of the deadline set forth in Section 23.4.5.7.9.3.2 of Attachment H
of the NYISO’s Market Administration and Control Area Services Tariff (“Services Tariff”).
The requested waiver would allow the NYISO to act on BEC’s request for a Competitive Entry
Exemption (“CEE”) under the NYISO’s “buyer-side” capacity market power mitigation rules
(the “BSM Rules”). As discussed below, the NYISO does not oppose BEC’s request but joins
BEC in urging the Commission to act on the request no later than August 1, 2017. A
determination by that date would avoid potential disruptions to the NYISO’s Class Year
Interconnection Facilities Study2 (“Class Year Study”) and BSM processes.3 The NYISO also
requests that if the Commission grants BEC’s requested waiver, it also briefly extend the
1 See 18 C.F.R. §§385.212 and 213 (2016).
2 Capitalized terms not defined herein have the meaning set forth in the Services Tariff, which in accordance with Section 23.4.4 of the Services Tariff, includes the meaning set forth in the NYISO’s Open Access Transmission Tariff.
3 The Class Year Study processes are set forth in Section 25 of the Open Access Transmission Tariff, and the BSM Rules are set forth in Section 23.4.5.7, et seq.
deadline for CEE exemption requests (accompanied by the executed Certification and
Acknowledgement)4 to similarly situated proposed new Examined Facilities in a Mitigated Capacity Zone that are members of Class Year 2017, as discussed below.
I.Motion to Intervene
The NYISO is the independent body responsible for providing open access transmission
service, maintaining reliability, and administering competitive wholesale markets for electricity,
capacity and ancillary services in New York State. Of particular relevance, the NYISO
administers the BSM Rules, including the rules for obtaining exemptions from mitigation, and
the closely related Class Year interconnection process. The NYISO’s administration of both the
BSM rules and Class Year rules will be directly impacted by the Commission’s ruling in this
proceeding. The NYISO, therefore, has a unique interest that cannot be adequately represented
by any other entity and, therefore, should be permitted to intervene with all rights of a party.
II.Comments
The Services Tariff’s deadline for submitting a CEE request is critical to the orderly
administration of both the BSM Rules and the Class Year Study procedures. The tariff deadline
allows the NYISO to perform the due diligence requisite to the evaluation of exemption requests
and make determinations thereon concurrent with its consideration of those same facilities and
all other facilities in the Class Year pursuant to the two economic entry tests5 in the BSM Rules.
Because the BSM Rules and Class Year Study process are so closely integrated, extending a
deadline generally has the potential to cause delays and disruption to both. Thus, deadlines
4 See Services Tariff Section 23.4.5.7.9.2.4 providing that the CEE Certification and
Acknowledgment “shall be submitted concurrent with the request for a Competitive Entry Exemption”.
5 The BSM Rules contain two tests to determine economic exemptions and Offer Floors
(commonly referred to as the “Part A Test” and the “Part B Test”). See Services Tariff Section
23.4.5.7.2(a) and (b).
2
should not be altered lightly and it is important that the Commission reinforce their importance. Adherence to the tariff-specified deadline will be even more imperative in the future if the
Commission accepts the proposed deadlines for submitting renewable and self-supply exemption requests which are pending in Docket Nos. ER16-1404, et. al.6 At that point the deadlines for
seeking various exemptions from mitigation will be the same - so that no developer has more
information than another developer when it makes a decision on whether to request a
Competitive Entry Exemption, renewable exemption, or a self-supply exemption, and the
potential disruptions from extending one deadline would be magnified.7 However, given the
specific circumstances in this case, granting BEC’s requested waiver of the deadline for it to
have submitted a CEE request and Certification and Acknowledgment would not practically
cause delays or disruptions - with the caveats noted below.
Based upon: (i) the NYISO’s review of BEC’s waiver request, (ii) the facts known to the NYISO at this time, (iii) the low potential for adverse market impacts, and (iv) the Commission’s guidance in earlier waiver orders, the NYISO does not oppose BEC’s waiver request. The
NYISO defers to the Commission on the question of whether BEC has met its burden of proof under the four-part waiver analysis.8
6 See New York Public Service Commission, et al. v. New York Independent System Operator,
Inc., Compliance Filing and Request for Commission Action within Sixty Days, Docket Nos. EL15-64-
000, ER16-1404-000, at proposed Sections 23.4.5.7.13.1.1 and 23.4.5.7.14.1.1(a) (providing that “its
request is received no later than the deadline by which a facility must notify the ISO of its election to
enter the Class Year, such date as set forth in Section 25.5.9 OATT Attachment S, or (iii) an expected
recipient of transferred CRIS rights at the same location and the ISO has been notified, by the transferor or the transferee, of a transfer pursuant to OATT Attachment S Section 25.9.4 that will be effective on a date within the Mitigation Study Period for the Class Year, provided that the request is received no later than the Class Year Start Date for such Class Year”) and proposed revisions to the CEE provisions [“[a] Generator or UDR project that requests a Competitive Entry Exemption in a Class Year may not also
request a Renewable Exemption or Self Supply Exemption”).
7 Id.
8 The NYISO also notes that although BEC’s petition describes the ongoing stakeholder process
related to comprehensive interconnection queue reform, and corresponding adjustments to the BSM
3
As noted above, the NYISO supports the request that the Commission act on BEC’s
waiver request no later than August 1, 2017.9 If the Commission were to grant a waiver after
that date, the NYISO’s anticipates that its ability to administer the BSM Rules and Class Year
Study process for 2017 Class Year projects could be impacted.10 The NYISO would use its best
efforts to complete both processes in a timely manner and in good order but, the further beyond
August 1 that Commission action is delayed, the greater the potential that exemption and Offer
Floor determinations and the overall Class Year Study process would be delayed.
In addition, if the Commission grants BEC’s waiver request it should issue a ruling that would provide a brief extension of the deadline, to a single specified date, for other eligible
proposed new Generators and UDR projects that are members of Class Year 2017 to request a
CEE and concurrently provide11 the required executed Certification and Acknowledgment.12
The tariff-established deadline for requesting a CEE is the same as the deadline for notifying the
NYISO of intent to join a Class Year. For Class Year 2017, as BEC’s petition notes, that date
Rules, it is not seeking any Commission action with respect to those still evolving rules. The NYISO likewise is not seeking, and would not support, any Commission action pertaining to any of those proposals at this time.
9 BEC has authorized the NYISO to state that BEC submitted its executed Certification and
Acknowledgment shortly after it filed its petition in this proceeding. See Petition of Bayonne Energy
Center, LLC for Limited Waiver and Request for Commission Action by August 1, 2017 (“BEC Petition”), Docket No. ER17-1652-000, at 5.
10 If the Commission’s ruling is to deny the waiver request, an order by August 1, 2017 would add certainty for all members of Class Year 2017 and Market Participants.
11 See supra at n. 4.
12 The date of the first certification and acknowledgement by a Developer of an Examined
Facility in Class Year 2017 is March 8, 2017. In addition to that requirement, the Services Tariff
specifies that the NYISO “may request additional information and updated certifications at any time prior to a Generator’s or UDR project’s Entry Date. A Generator or UDR project that is granted an exemption pursuant to this Section 23.4.5.7.9, shall be required to submit an executed Certification and
Acknowledgement form set forth in Section 23.4.5.7.9.2 of the Services Tariff, updated as appropriate, upon its Entry Date.” See Services Tariff Section 23.4.5.7.9.3.1.
4
was March 8, 2017.13 If the Commission were to waive that deadline for BEC, other new
entrants might be encouraged to seek deadline waivers of their own. But if such waivers were sought, and then granted after August 1, 2017, it would be as potentially disruptive and likely to cause an even greater delay to the NYISO’s work under the BSM Rules and Class Year Study process as acting on BEC’s request after that date would. The NYISO’s evaluation of a request for a CEE actually increases the amount of work it must perform to determine eligibility because it also must perform the balance of the due diligence under the BSM Rules.
Therefore, if the Commission grants BEC’s request for a waiver of the deadline by which
a proposed new Generator or UDR project was to have submitted, for NYISO’s receipt, a request
and Certification and Acknowledgment, it should also rule that any additional requests for a CEE
accompanied by the required Certification and Acknowledgment by other, similarly-situated
proposed new Examined Facilities must be received before the later of: (i) six calendar days after
the issuance of the order granting the waiver; or (ii) August 1, 2017, i.e., BEC’s requested
August 1, 2017 action date. The Commission has previously made similar rulings in other
proceedings involving requests for waivers of NYISO tariff provisions in order to avoid potential
undue discrimination.14 It should do the same here in order to treat all parties fairly and to
preserve the NYISO’s ability to administer the BSM Rules and Class Year process in a timely
and orderly fashion.
13 BEC Petition at 5.
14 See, e.g., New York Power Authority, 139 FERC ¶61,157 at P 27 (2012) (“Further, for the
reasons for which we grant NYPA’s waiver request as outlined below, we find that this waiver applies
equally to all other similarly situated responsible interface parties. We find that it would be unduly
discriminatory to limit the applicability of this waiver to only certain affected responsible interface
parties, as some of the commenters and the protestor contend. Therefore, we grant waiver to all similarly
situated responsible interface parties, as described above, to permit the deadline for submission of the
required data to be extended to and including four calendar days from the date of this order”).
5
The NYISO also respectfully requests that if the Commission grants that limited
extension for other proposed new Examined Facilities that are members of Class Year 2017, it
make clear that it is not altering any requirement other than the deadline by which they are to
submit the request and required documentation for the NYISO’s receipt. Therefore, the
Developer as of March 8, 2017 should submit the request for a CEE and the Certification and
Acknowledgment based on the facts as of March 8, 2017, and the Developer should also submit
an updated Certification and Acknowledgement based on the facts as of the date of the
submission of the request.15
If the Commission grants the NYISO’s request for a limited extension for such other
similarly situated members of Class Year 2017, the NYISO would promptly post on its website a list of each such Generator or UDR project that requests a CEE and provides to the NYISO the required Certification and Acknowledgment and updated Certification and Acknowledgment.16 III. Communications and Correspondence
All communications and service with regard to this filing should be directed to:
Robert E. Fernandez, General Counsel
Raymond Stalter, Director, Regulatory Affairs *Gloria Kavanah, Senior Attorney
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-6103
Fax: (518) 356-8825
rfernandez@nyiso.com
rstalter@nyiso.com
gkavanah@nyiso.com
* Person designated for receipt of service.
15 The Developer’s provision of the updated certification is contemplated by and consistent with Section 23.4.5.7.9.3.1 of the Services Tariff.
16 See Section 23.4.5.7.9.4.1 of the Services Tariff.
6
IV.Conclusion
WHEREFORE, for the foregoing reasons, the NYISO respectfully requests that the Commission (i) grant this motion to intervene, (ii) consider these comments in making its decision on BEC’s request; and (iii) if it decides to grant the requested waiver, issue a ruling allowing other similarly-situated proposed new Examined Facilities a brief extension of the deadline to also submit a request for a CEE, to the NYISO, accompanied by the required Certification and Acknowledgment, for the reasons set forth above.
Respectfully submitted,
/s/ Gloria Kavanah
Gloria Kavanah
Counsel to the New York Independent System Operator, Inc.
10 Krey Blvd.
Rensselaer, New York 12144 (518) 356-6103
gkavanah@nyiso.com
cc:Michael Bardee
Nicole Buell
Anna Cochrane
Kurt Longo
David Morenoff
Daniel Nowak
Larry Parkinson
J. Arnold Quinn
Douglas Roe
Kathleen Schnorf
Jamie Simler
Gary Will
7
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person
designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. §385.2010.
Dated at Rensselaer, NY this 12th day of June 2017.
/s/ Joy A. Zimberlin
Joy A. Zimberlin
New York Independent System Operator, Inc.
10 Krey Blvd.
Rensselaer, NY 12144 (518) 356-6207