Public Service Commission

Gregg C. Sayre

Interim Chairman and

Interim Chief Executive Officer

Diane X. Burman

Commissioner

Thomas Congdon

Deputy Chair and
Executive Deputy

Paul Agresta

General Counsel

Kathleen H. Burgess


Three Empire State Plaza, Albany, NY 12223-1350 www.dps.ny.gov

 

March 27, 2017

SUBMITTED VIA E-TARIFF FILING

Kimberly D. Bose, Secretary

Federal Energy Regulatory Commission 888 First Street, N.E.

Washington, DC 20426

 

Re:   New York Independent System Operator, Inc.
Docket No. ER17-___-000

 

Dear Secretary Bose:

For filing, attached please find proposed revisions to the Open Access Transmission Tariff (OATT) of the New York Independent System Operator, Inc. (NYISO).  Pursuant to Section 31.5.5.4.1 of the NYISO’s OATT, any methodology for allocating the costs of


Secretary


transmission facilities, which is prescribed in connection with a Public Policy Requirement (also referred to as a Public Policy Transmission Need), shall be filed pursuant to Section 205 of the Federal Power Act for approval by the Federal Energy Regulatory Commission (Commission).1 Consistent with the NYISO’s Public Policy Transmission Planning Process, the New York
Public Service Commission (NYPSC) identified a Public Policy Requirement and cost allocation approach with respect to relieving the persistent transmission congestion across certain electrical interfaces, referred to as Central East and Upstate New York/Southeast New York
(UPNY/SENY).  The OATT revisions proposed herein provide the NYPSC’s cost allocation
methodology associated with addressing this AC Transmission Public Policy Transmission
Need.2  In addition, the NYPSC identifies its preferred approach for cost containment that was adopted in connection with the cost allocation methodology.


 

 

 

1

 

2


 

16 U.S.C. § 824d (2012).

The NYISO advises that, upon acceptance by the Commission, the tariff revisions proposed herein will become part of the NYISO OATT under Section 31.8 of Attachment Y.

Accordingly, the NYISO is submitting this filing in FERC’s e-Tariff system on behalf of the NYPSC solely in its role as the Tariff Administrator.  The burden of demonstrating that the proposed tariff amendments are just and reasonable resides with the NYPSC—the sponsoring party.  The NYISO takes no position on any substantive aspect of the filing at this time.


 

 

 

 

 

The NYPSC respectfully submits that the proposed amendments for allocating costs
under the NYISO OATT, as demonstrated by this transmittal letter and the attached affidavits
and appendices, are just and reasonable, and should be accepted without suspension or hearing.3 The NYPSC requests an effective date of May 26, 2017 for the cost allocation methodology and related tariff changes.  Alternatively, the NYPSC requests that the Commission limit the issues set for hearing and impose a nominal suspension period.  In addition, the Commission should
direct that any developer selected to construct the transmission facilities shall apply the cost
containment provisions identified herein.

 

I.BACKGROUND

A. Description of the NYPSC

 

The NYPSC is a regulatory body established under the laws of the State of New York
with jurisdiction, in part, to regulate rates and charges for the sale of electric energy to
consumers within the State, as well as the siting of major electric transmission facilities.
Accordingly, the NYPSC is a State Commission as defined in section 3(15) of the Federal Power
Act.

 

B. NYISO’s Public Policy Transmission Planning and Cost Allocation Process

The NYISO’s Public Policy Transmission Planning Process was developed to comply
with the Commission’s Order No. 1000, which required, in part, the development of a planning
process for the consideration of public policy-driven transmission needs.4  The NYISO’s process
consists of four main steps, which include:  (1) the NYPSC’s identification of any Public Policy
Requirements/Public Policy Transmission Needs; (2) the NYISO’s solicitation of proposed
solutions to any identified Public Policy Transmission Needs; (3) the NYISO’s evaluation of the
viability and sufficiency of proposed transmission and non-transmission solutions to the Public
Policy Transmission Needs; and, (4) upon the NYPSC’s confirmation of a transmission need
based on the viability and sufficiency evaluation, the NYISO’s full evaluation and selection of
the more efficient or cost-effective transmission project to satisfy the Public Policy Transmission
Need.5

 

Consistent with the Commission’s directives in Order No. 1000, the NYISO’s Public

Policy Transmission Planning Process contains a multi-step process to prescribe a cost allocation
methodology for regulated transmission solutions that are selected to satisfy needs driven by


 

 

3

 

 

 

 

4

 

 

 

 

 

5


The views expressed herein are not intended to represent those of any individual member of the NYPSC.  Pursuant to Section 12 of the New York Public Service Law, the Chair of the NYPSC is authorized to direct this filing on behalf of the NYPSC.

See, Docket No. RM10-23-000, Transmission Planning and Cost Allocation by Transmission
Owning and Operating Public Utilities, Order No. 1000 (issued July 21, 2011), reh’g denied,
Order No. 1000-A (issued May 17, 2012) reh’g denied, Order No. 1000-B (issued October
18, 2012).

NYISO Public Policy Transmission Planning Process Manual; Section 1.2 (July 2015).
-2-


 

 

 

 

 

Public Policy Requirements.6  This process was designed to provide flexibility in prescribing a methodology that would allocate the costs of a selected Public Policy Transmission Project
consistent with the Public Policy Requirement driving the identified transmission need and
roughly commensurate with the derived benefits.7  In allocating the costs of the selected Public Policy Transmission Project, the NYISO will use the methodology accepted by the Commission upon completion of this process.8

 

Section 31.5.5.4.1 of the NYISO OATT provides that where the identified Public Policy
Requirement prescribes a particular cost allocation methodology, the NYISO will use that
methodology, provided the Commission accepts it.  Therefore, as the initial step in this process,
the NYISO, on behalf of the NYPSC, will file with the Commission any cost allocation
methodology prescribed by the NYPSC in a Public Policy Requirement driving the identified
transmission need within 60 days of the NYPSC’s order setting forth such methodology.9

 

If the Public Policy Requirement does not prescribe a cost allocation methodology or the
Developer of the selected Public Policy Transmission Project wants to propose an alternative
methodology, the Developer may submit to the NYPSC for its consideration a proposed cost
allocation methodology within 30 days after the NYISO’s selection of its transmission project as
the more efficient or cost effective transmission solution to the identified Public Policy
Transmission Need.10  The NYPSC will have 150 days to review the Developer’s proposed cost
allocation methodology and to notify the Developer whether the NYPSC supports the
methodology.11  If the NYPSC supports the proposed methodology, the Developer will file it
with the Commission under Section 205 of the Federal Power Act within 30 days of the
NYPSC’s indication of its support.12

However, if the NYPSC does not support the Developer’s proposed cost allocation

methodology, the Developer will have 60 days to work with the NYPSC to develop a mutually
agreeable cost allocation methodology.13  If they agree upon a cost allocation methodology, the
Developer will file that methodology with the Commission within 30 days of the conclusion of
the 60-day discussion period.14  If they cannot agree, the Developer will file its preferred


 

 

 

6

 

7

 

 

8

 

9


 

See generally Section 31.5.5.4 of the NYISO OATT

See id.; New York Independent System Operator, Inc., et al., Compliance Filing, Docket No. ER13-102-000 (October 12, 2012), at p 46.

Section 31.5.5.4 of the NYISO OATT.
Section 31.5.5.4.1 of the NYISO OATT.


10   Section 41.5.5.4.2 of the NYISO OATT; see also New York Independent System Operator,
Inc., et al., Compliance Filing, Docket No. ER13-102-006 (September 15, 2014), at p 15.

11   Section 31.5.5.4.2.1 of the NYISO OATT.

12   Section 31.5.5.4.2.2 of the NYISO OATT.

13   Section 31.5.5.4.2.3 of the NYISO OATT.

14   Section 31.5.5.4.2.4 of the NYISO OATT.

 

-3-


 

 

 

 

 

methodology with the Commission within 30 days of the conclusion of the discussion period, which filing will also include the methodology supported by the NYPSC.15

 

In the event that this process does not result in the Commission accepting a cost

allocation methodology prescribed by the Public Policy Requirement or proposed by a

Transmission Owner or Other Developer, the NYISO will use the default ex ante methodology
based on load-ratio share to allocate the costs to all Load Zones in the New York Control Area.16

C. NYPSC Identification of the Public Policy Transmission Need and Cost
Allocation/Containment Approaches

The NYPSC initiated a proceeding in November 2012 to address the need for certain

upgrades across the Central East and Upstate New York/Southeast New York portions of the AC
transmission system (referred to as the AC Transmission Upgrades).17  Following subsequent
notice and comment procedures, the NYPSC issued a December 2014 Order,18 attached as
Appendix E, which adopted a cost allocation methodology related to the AC Transmission
Upgrades, as recommended by its Advisory Staff.  In particular, the NYPSC indicated that it:

 

supports a “beneficiaries pay” approach for allocating costs, whereby those that derive
the benefits of a project should bear the costs.  Although a precise calculation of the
projected benefits has not been completed, the cost allocation proposed in the Advisory
Staff Recommendations is roughly commensurate with the anticipated beneficiaries.  The
[NYPSC] therefore adopts an approach whereby 75% of project costs are allocated to the
economic beneficiaries of reduced congestion, while the other 25% of the costs are
allocated to all customers on a load-ratio share.  This would result in approximately 90%
of the project costs being allocated to customers in the downstate region, and about 10%
to upstate customers.  This allocation reflects that the primary benefit of the projects will
be reduced congestion into downstate load areas, but also recognizes that some benefits
accrue to upstate customers in the form of increased reliability and reduced operational
costs.

On December 17, 2015, the NYPSC issued an order, which is attached as Appendix F,
finding that the need for certain upgrades across the Central East and UPNY/SENY portions of
the AC transmission system were being driven by a Public Policy Requirement, as defined under
the NYISO OATT.19  The NYPSC indicated that upgrades to those sections of the transmission

15   Section 31.5.5.4.2.4 of the NYISO OATT.

16    Section 31.5.5.4.3 of the NYISO OATT.

17  Case 12-T-0502, AC Transmission Proceeding, Order Instituting Proceeding (issued
November 30, 2012).

18  Case 12-T-0502, et al., AC Transmission Proceedings, Order Establishing Modified

Procedures for Comparative Evaluation (issued December 16, 2014) pp. 41-42 (December 2014 Order).

19  Case 12-T-0502, Order Finding Transmission Needs driven by Public Policy Requirements
(issued December 17, 2015) (December 2015 Order).

-4-


 

 

 

 

 

system could produce various benefits for New York, including:  1) enhancing system reliability,
flexibility, and efficiency; 2) reducing environmental and health impacts; 3) increasing diversity
in supply; 4) promoting job growth and the development of new efficient generation resources
upstate; and, 5) mitigating reliability problems that may arise with expected generator
retirements.  In identifying the AC Transmission Public Policy Transmission Need, the NYPSC
affirmed its support of the cost allocation approach identified in its December 2014 Order, which
would result in approximately 90% of the project costs being allocated to customers in the
downstate region (NYISO Zones G-K), and about 10% to upstate customers (NYISO Zones A-

F).  However, the NYPSC sought the NYISO’s expertise in designing a more granular cost allocation among downstate entities.20

As directed under the OATT, the NYISO issued a solicitation on February 29, 2016,

seeking potential solutions to resolve the Public Policy Requirement identified by the NYPSC.
Subsequently, the NYISO provided the results of its Viability and Sufficiency Assessment to the
NYPSC on October 28, 2016, which included the results of the NYISO’s analysis of cost
allocation methodologies that comport with the NYPSC-identified Public Policy Requirement.

 

On January 24, 2017, the NYPSC issued an order, attached as Appendix G, which

directed the NYISO to proceed to a full evaluation and selection, as appropriate, of the more

efficient or cost-effective transmission solution to meet the AC Transmission Public Policy

Transmission Need.21  The NYPSC also adopted the cost allocation methodology outlined in the
NYISO’s analysis for allocating and recovering the costs of the transmission upgrades.  Further,
the NYPSC stated that certain incentives are appropriate to ensure accurate cost estimates,
whereby:

[i]f actual costs come in above a bid, the developer should bear 20% of the cost overruns, while ratepayers should bear 80% of those costs. If actual costs come in below a bid, then the developer should retain 20% of the savings.  Furthermore, if the developer seeks incentives from FERC above the base return-on-equity otherwise approved by FERC, then the developer should not receive any incentives above the base return-on-
equity on any cost overruns over the bid price.  The bid price would therefore cap the costs that may be proposed to FERC for incentives.22

 

 

II.SUMMARY OF REQUESTED ACTIONS

A. Cost Allocation

The NYPSC requests that the proposed amendments for allocating costs under the

NYISO OATT, as identified in clean format in Appendix A and redlined format in Appendix B,
should be accepted without suspension or hearing.  The NYPSC requests an effective date of

 

20  December 2015 Order.

21  Case 12-T-0502, et al., Order Addressing Public Policy Transmission Need for AC
Transmission Upgrades (issued January 24, 2017) (January 2017 Order).

22 December 2015 Order, p. 48.

 

-5-


 

 

 

 

 

May 26, 2017 for the cost allocation methodology and related tariff changes.  Alternatively, the NYPSC requests that the Commission limit the issues set for hearing and impose a nominal
suspension period.

B. Cost Containment

The NYPSC requests that any developer selected by the NYISO to construct the

transmission facilities for meeting the AC Transmission Public Policy Transmission Need shall be directed to apply the cost containment provisions adopted in the NYPSC’s prior orders and discussed herein.

 

III.THE REQUESTED ACTIONS ARE JUST AND REASONABLE AND

CONSISTENT WITH ORDER NO. 1000

As demonstrated in the affidavit of Jerry J. Ancona, attached as Appendix C, the

25%/75% breakdown between overall statewide benefits and more targeted congestion savings,
respectively - resulting in approximately 10% of benefits accruing upstate and 90% accruing
downstate - provides a  just and reasonable approximation to assign costs commensurate with all
anticipated benefits.  This approach appropriately recognizes that the primary benefits of the AC
Transmission Upgrades will be due to congestion relief savings, while also acknowledging that
other benefits will accrue to some portions or all of the State, such as: 1) enhanced system
reliability, flexibility, and efficiency; 2) reduced environmental and health impacts; 3) increased
diversity in supply; 4) promotion of job growth and the development of new efficient generation
resources upstate; and, 5) mitigation of reliability problems that may arise with expected
generator retirements.

As further discussed in the affidavit of Mr. Ancona, an 80%/20% (ratepayer/developer)

risk sharing mechanism provides a balanced incentive among competing interests for meeting the dual objectives of (i) reliable initial cost estimates, and (ii) well managed and cost-controlled
project completions.  The affidavit of MaryAnn Sorrentino, attached as Appendix D, illustrates a regulatory approach for effectuating this risk sharing and cost containment approach, whereby
cost overruns would be addressed by reducing the allowed return on equity on any capital cost overrun.  This approach would ensure the return on equity remains within the zone of
reasonableness and is just and reasonable.

 

IV. PROPOSED EFFECTIVE DATE

The NYPSC requests that the Commission accept the tariff amendments to be effective

60 days after this filing, on May 26, 2017, without suspension or hearing.  Alternatively, the NYPSC requests that the Commission limit the issues set for hearing and impose a nominal suspension period.

 

 

 

 

 

 

-6-


 

 

 

 

 

V.CONTENTS OF THE FILING

In addition to this transmittal letter, which provides a detailed description of the

approvals requested and the bases for those requests, this filing contains the following

components:

Appendix A:Clean Version of NYISO OATT

Appendix B:Redlined Version of NYISO OATT

Appendix C:Affidavit of Jerry J. Ancona, PE

Appendix D:Affidavit of MaryAnn Sorrentino

Appendix E:NYPSC Order issued December 16, 2014

Appendix F:NYPSC Order issued December 17, 2015

Appendix G:NYPSC Order issued January 24, 2017

 

VI.REQUESTED WAIVERS

Based on its status as a non-jurisdictional utility, the NYPSC respectfully requests that it be exempt from FERC’s filing fees and from compliance with any requirements of section 35.13 of the Commission’s regulations not otherwise satisfied by this filing.23  In the event any
additional waivers are required in connection with this filing, the NYPSC respectfully requests that the Commission grant such waivers.

 

VII.   CORRESPONDENCE AND COMMUNICATIONS

 

The following persons are authorized to receive notices and communications with respect to this Application:


 

David G. Drexler
Managing Attorney

New York State Department
of Public Service

Three Empire State Plaza
Albany, New York 12223-1350
Telephone: (518) 473-8178
David.Drexler@dps.ny.gov


William Heinrich

Manager, Policy Coordination
New York State Department

of Public Service

Three Empire State Plaza
Albany, New York 12223-1350
Telephone: (518) 473-3402
William.Heinrich@dps.ny.gov


 

23  See, 18 C.F.R. § 381.108 (indicating that “States, municipalities and anyone who is engaged
in the official business of the Federal Government are exempt from the fees required by this
part and may file a petition for exemption in lieu of the applicable fee”).

 

 

-7-


 

 

 

 

 

VIII.   CONCLUSION

For the reasons set forth herein, the NYPSC requests that the Commission accept the

OATT revisions providing for a cost allocation methodology, to be effective May 26, 2017, and direct that the cost containment provisions to be applied to the recovery of project costs.

Respectfully submitted,

 

/s/ Paul Agresta

Paul Agresta

General Counsel

New York State Public Service Commission Three Empire State Plaza

Albany, NY 12223

Telephone: (518) 474-2510

Attachments:  Appendices A-G

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

-8-