Christopher J. Novak
Senior Counsel
November 9, 2017
The Honorable Kimberly D. Bose Secretary
Federal Energy Regulatory Commission 888 First Street, NE
Washington, DC 20426
Re: Niagara Mohawk Power Corporation
Docket No. ER18-____-000
Filing of Reimbursement Agreement with
Mid-Atlantic Interstate Transmission, LLC
Dear Secretary Bose:
Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and Part 35 of the
Federal Energy Regulatory Commission’s (“Commission”) regulations,2 Niagara Mohawk
Power Corporation (“Niagara Mohawk”) submits a letter agreement (“Reimbursement
Agreement”) between Niagara Mohawk and Mid-Atlantic Interstate Transmission, LLC
(“MAIT”).3 The Reimbursement Agreement is designated as Service Agreement No.
2386 under the New York Independent System Operator, Inc.’s (“NYISO”) Open Access
Transmission Tariff.
The Reimbursement Agreement is an undisputed agreement to facilitate the
performance of certain work that Niagara Mohawk is required to do as a result of MAIT’s upgrades to its Erie East 230 kV Substation. Niagara Mohawk requests that the
Commission grant acceptance of the Reimbursement Agreement effective as of October 11, 2017, the effective date agreed to by the Parties.
I.Background
Niagara Mohawk is a public utility subject to the Commission’s jurisdiction that
owns transmission facilities located in New York which have been placed under the
operational control of the NYISO. MAIT is a public utility subject to the Commission’s
jurisdiction that owns and operates transmission facilities located in Pennsylvania which
have been placed under the functional control of PJM Interconnection, L.L.C. (“PJM”).
1
2
3
16 U.S.C. § 824d.
18 C.F.R. Part 35.
Together, Niagara Mohawk and MAIT are referred to in the Reimbursement Agreement and in this
transmittal letter as the “Parties.”
40 Sylvan Road, Waltham, MA 02451
T: 781-907-2112 F: 781-907-5701 Chris.Novak@nationalgrid.com www.nationalgrid.com
The Honorable Kimberly D. Bose November 9, 2017
Page 2
Certain system protection modifications to Niagara Mohawk’s South Ripley
Substation, at its 230 kV Line 69, are required as a result of MAIT’s upgrades to its Erie East 230 kV Substation as defined in PJM Regional Transmission Expansion Plan b2371. MAIT has requested that Niagara Mohawk perform the system protection modification work pursuant to the Reimbursement Agreement. Niagara Mohawk is willing to perform this work, subject to reimbursement by MAIT of all costs and expenses incurred by
Niagara Mohawk in connection with the work.
II. Description of the Reimbursement Agreement and Filing Requirements
Pursuant to the Reimbursement Agreement, MAIT will reimburse Niagara
Mohawk for the actual costs and expenses incurred in connection with the work described above. The Reimbursement Agreement sets forth the terms and conditions of this work
and certain related commitments by MAIT. The Reimbursement Agreement includes
provisions addressing the performance of the work, liability and indemnification, force
majeure, and various other standard provisions included in comparable utility cost
reimbursement agreements.
Section 205 of the FPA authorizes the Commission to require public utilities to file
all rates and charges that are “for or in connection with,” and all agreements that “affect or
relate to,” jurisdictional transmission service or sales of electric energy.4 In the Prior
Notice Order, the Commission stated that the types of agreements that a public utility
must file include “a jurisdictional CIAC agreement,” which is defined as an “agreement
providing for the customer payment of contributions-in-aid-of-construction” of facilities
used to provide jurisdictional service, either in a single lump sum or over a period of
time.5 Commission precedent also indicates that engineering and pre-construction
agreements related to jurisdictional facilities can be construed as CIAC agreements.6
The Reimbursement Agreement relates to Niagara Mohawk’s recovery of costs for
performing system protection modifications on transmission facilities as described in the
Reimbursement Agreement that are required due to MAIT’s upgrades to the Erie East 230
kV Substation. Niagara Mohawk recognizes that the Commission may find the
Reimbursement Agreement to be a jurisdictional CIAC agreement that must be filed. For
these reasons, Niagara Mohawk is filing the Reimbursement Agreement for Commission
acceptance.
4
5
16 U.S.C. §§ 824d(a)-(c).
Prior Notice and Filing Requirements Under Part II of the Federal Power Act, 64 FERC ¶ 61,139,
at 61,974, 61,988-91 (1993) (“Prior Notice Order”).
6
For example, in Southern California Edison Company, 98 FERC ¶ 61,304, at 62,300-01 (2002), the
Commission required the filing of seven letter agreements related to pre-interconnection activities in
anticipation of certain generator interconnections, “including procurement, engineering, and limited
construction.” See also GenPower Anderson, LLC v. Duke Energy Corp. and Duke Electric Transmission, 101 FERC ¶ 61,038 (2002) (requiring Duke Energy to file an engineering and design letter agreement that was entered into pending execution of an interconnection and operating agreement).
The Honorable Kimberly D. Bose November 9, 2017
Page 3
The price of the services to be performed pursuant to the Reimbursement
Agreement will be just and reasonable because Niagara Mohawk will perform these
services at actual cost. The Commission should therefore accept the Reimbursement
Agreement.
III.Effective Date
The Commission’s regulations require service agreements to be filed not more
than 30 days after service under the agreements has commenced.7 As discussed above,
the Parties intend the Reimbursement Agreement to go into effect as of October 11, 2017,
i.e., fewer than 30 days before the date the Reimbursement Agreement is being filed.8
IV.Attachment
In addition to this transmittal letter, this filing includes the Reimbursement
Agreement that is provided in Attachment A hereto.
V.Communications and Service
Communications regarding this filing should be addressed to the following
individuals, whose names should be entered on the official service list maintained by the
Secretary for this proceeding:
Christopher J. NovakSean Atkins
Senior CounselBradley R. Miliauskas
National Grid USAAlston & Bird LLP
Service Company, Inc.The Atlantic Building
40 Sylvan Road950 F Street, NW
Waltham, MA 02451Washington, DC 20004
(781) 907-2112(202) 239-3300
Chris.Novak@nationalgrid.comsean.atkins@alston.com
Kathryn Cox-Arslan
Director, Commercial Services National Grid USA
40 Sylvan Road
Waltham, MA 02451 (781) 907-2406
kathryn.cox-arslan@nationalgrid.com
Copies of this filing have been served on MAIT, the NYISO, and PJM.
7
8
18 C.F.R. § 35.3.
Section 1 of the miscellaneous provisions in the Reimbursement Agreement states that the
agreement will become effective as of the date of the agreement, which is October 11, 2017.
The Honorable Kimberly D. Bose November 9, 2017
Page 4
VI.Conclusion
For the reasons stated herein, Niagara Mohawk respectfully requests that the
Commission accept the Reimbursement Agreement effective as of October 11, 2017.
Respectfully submitted,
/s/ Christopher J. Novak
Christopher J. Novak Senior Counsel
National Grid USA
Service Company, Inc.
40 Sylvan Road
Waltham, MA 02451
Attorney for Niagara Mohawk Power Corporation