UNITED STATES OF AMERICA
BEFORE THE

FEDERAL ENERGY REGULATORY COMMISSION


 

New York Public Service Commission, New York Power Authority, and

New York State Energy Research and Development Authority

 

v.

 

New York Independent System Operator, Inc.


)
)
)
)
)

)Docket No. EL15-64-000
)

)
)


 

MOTION FOR EXTENSION OF TIME OF

NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.

 

In accordance with Rules 212 and 2008 of the Commission’s Rules of Practice and

Procedure,1 the New York Independent System Operator, Inc. (“NYISO”) respectfully requests that the Commission grant an additional 21 day extension of the compliance filing deadline in this proceeding.  The compliance filing is currently due on February 22, 2016, in accordance with the December 16, 2015 Notice of Extension of Time.  If the requested additional extension is granted it would be due on March 14, 2016.

The Commission’s October 9, 2015 order (“October Order”)2 directed the NYISO to

make a compliance filing to revise its buyer-side capacity market power mitigation rules (“BSM
Rules”) to exempt certain narrowly defined renewable and self-supply resources from Offer
Floor3 mitigation.  The NYISO has made substantial progress on its compliance proposal and is
working diligently to finalize it.  The NYISO has determined, however, that allowing a few extra

 

1 18 C.F.R. §§ 385.212 and 2008 (2015).

2 New York Pub. Serv. Comm’n et al. v. New York Indep. Sys. Operator, Inc., 153 FERC ¶ 61,022

(2015).

3 Capitalized terms not otherwise defined herein shall have the meaning set forth in the NYISO’s Market Administration and Control Area Services Tariff.


 

 

weeks for additional stakeholder review and discussion would be likely to improve the proposal without materially delaying its implementation.  As noted below, the complainants and other parties in this proceeding support the requested additional extension, numerous other parties do not oppose it, and the NYISO is not aware of any opposition.  There is thus “good cause” for granting the requested 21 day additional extension.

The NYISO respectfully requests that the Commission adopt the standard five day notice period for extension requests4 and act expeditiously to grant the extension no later than February 18, 2016 so that the NYISO and stakeholders will know with certainty when the compliance
filing will be due.

 

I. The Development of the NYISO’s BSM Compliance Proposal to Date

The October Order directed the NYISO to file “a compliance filing, within 90 days of the
date of this order, to revise its buyer-side market power mitigation rules to exempt a narrowly
defined set of renewable and self-supply resources that have limited or no incentive and ability to
exercise buyer-side market power to artificially suppress ICAP market prices.”5  Specifically, the
NYISO was directed to revise the BSM rules to exempt renewable resources “that are both
purely intermittent and that have relatively low capacity factors and high development costs
because these resources have limited or no incentive and ability to artificially suppress capacity
prices,”6 and self-supply resources “whose ICAP portfolios are consistent with reasonably

 

 

 

 

 

 

 

4 18 C.F.R. § 385.213(d)(1)(i).

5 October Order P 10.

6 October Order P 51.

 

 

2


 

 

 

 

 

anticipated levels of their future ICAP obligations.”7  The Commission also stated that it

 

“expect[s] NYISO to work with its stakeholders in developing this compliance filing.”8

The NYISO commenced work on a compliance proposal promptly after the issuance of the October Order.  When it became apparent that additional time was needed the NYISO timely sought and obtained a 45 day extension.  In the months since the October Order the NYISO has worked diligently to craft renewable and self-supply exemptions that would satisfy the
Commission’s requirements and to incorporate stakeholder input.  The NYISO has held five
stakeholder meetings to discuss the NYISO’s proposal, and obtain stakeholder input as it has
evolved.  Since the last meeting with stakeholders, on January 26, meeting with stakeholders,
further details of the proposal have been developed and the NYISO is has is continuing to draft compliance tariff language.  The NYISO would like to discuss the details and review the draft
tariff provisions with stakeholders.  The NYISO believes that review with stakeholders will be beneficial to all parties and will result in a clearer proposal.

II. Request for Extension of Compliance Filing Deadline

 

The NYISO understands the importance that the Commission places on timely

compliance with its orders.  The requested additional extension is brief (21 days) but necessary
given the potential impacts of the compliance filing.  Taking a little more time to finalize the
filing will allow stakeholders the opportunity to review a near final version of the NYISO’s
compliance draft language and give the NYISO an opportunity to consider it and to make any
necessary revisions.  Allowing an opportunity for additional pre-filing review would complete
the stakeholder process and is likely to improve the compliance proposal.  Granting a brief

 

 

 

7 October Order P 62.

8 October Order at P 10.

 

 

3


 

 

additional extension also will not materially delay the implementation of renewable and selfsupply exemptions in the NYISO-administered capacity markets.

The complainants in this proceeding―the New York Public Service Commission, the

New York Power Authority, and the New York State Energy Research and Development

Authority―have authorized the NYISO to state that they are appreciative of the dialogue thus far
in the stakeholder process and support the requested extension so that there is time for additional
stakeholder meetings in which the relevant tariff language will be refined.  Other parties in this
proceeding, specifically, the Independent Power Producers of New York, Inc., the City of New
York, Multiple Intervenors, Entergy Nuclear Power Marketing, LLC, the New York Association
of Public Power, Consolidated Edison Company of New York, Inc. and Central Hudson Gas and
Electric Corporation, have informed the NYISO that they do not object to the requested

extension.

Rule 2008 authorizes the Commission to extend any deadline, including one imposed by a compliance directive, before it expires if a requesting party demonstrates that there is “good cause” to do so.  For the reasons set forth above, the NYISO respectfully submits that there is good cause to grant the additional 21 day extension of time that it has requested.

III.Conclusion

WHEREFORE, for the foregoing reasons, the NYISO respectfully requests that the

Commission grant an additional 21 day extension to the compliance filing deadline in the abovecaptioned proceeding so that the NYISO may submit its compliance tariff revisions no later than March 14, 2016.  The NYISO also respectfully requests that the Commission issue an order
granting the requested extension by no later than February 18, 2016 so that there will be certainty concerning the filing deadline.

 

 

 

4


 

 

 

 

 

 

 

Respectfully submitted,

 

/s/ Ted J. Murphy

 

Ted J. Murphy

Counsel for the New York Independent System Operator, Inc.

 

 

 

February 12, 2016

 

cc:Michael Bardee

Anna Cochrane
Kurt Longo
Max Minzner
Daniel Nowak
Larry Parkinson

J. Arnold Quinn
Douglas Roe

Kathleen Schnorf
Jamie Simler

Gary Will

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5


 

 

 

 

 

CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person

designated on the official service list compiled by the Secretary in this proceeding in accordance
with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. §
385.2010.

Dated at Rensselaer, NY this 12th day of February 2016.

 

 

 

By:/s/ John C. Cutting

John C. Cutting

New York Independent System Operator, Inc.