10 Krey Boulevard Rensselaer, NY 12144
November 29, 2016
By Electronic Delivery
Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE
Washington, DC 20426
Re: New York Independent System Operator, Inc., Docket No. ER16-1213-00_; Compliance
Filing Establishing an Effective Date for Behind-the-Meter Net Generation Tariff
Revisions
Dear Secretary Bose:
In accordance with the requirements of the Federal Energy Regulatory Commission’s
(“Commission”) May 17, 2016 order in this proceeding,1 the New York Independent System Operator,
Inc. (“NYISO”) submits this filing to provide notice of the expected effective date for the tariff
amendments integrating Behind-the-Meter Net Generation Resources (the “BTM:NG Tariff
Revisions”).2 In this filing, the NYISO also advises the Commission of certain matters related to the
transition of existing resources participating in the wholesale markets (e.g., Generators and Special
Case Resources (“SCRs”)) to Behind-the-Meter Net Generation Resources (“BTM:NG Resources”).
I.Documents Submitted
1.This filing letter;
2.A clean version of the accepted revisions to the Market Administration and Control Area
Services Tariff (“Attachment I”); and
3.A clean version of the accepted revisions to the Open Access Transmission Tariff
(“Attachment II”).
1 New York Indep. Sys. Operator, Inc., 155 FERC ¶ 61,166 (2016).
2 New York Indep. Sys. Operator, Inc. March 17, 2016 Proposed Amendments to the NYISO Open Access Transmission Tariff and Market Administration and Control Area Services Tariff to
Incorporate Behind-the-Meter Net Generation Resources into the NYISO’s Energy, Ancillary Services and Capacity Markets (“March 17 Filing”).
Honorable Kimberly D. Bose November 29, 2016
Page 2
II.Notice of Effective Date
In compliance with the May 17, 2016 order in this proceeding, the NYISO hereby provides notice to the Commission that it expects to fully implement the accepted revisions for the December 13, 2016 market day. Attachments I and II provide clean versions of the relevant tariff revisions with an effective date of December 13, 2016.3
III. Transition of Existing Wholesale Resources
As explained in the BTM:NG Tariff Revisions, the NYISO is working with existing wholesale
Generators4 that will qualify as BTM:NG Resources to facilitate an orderly transition from the
Generator’s current wholesale market participation as a “traditional” Generator to a BTM:NG
Resource (or other type of resource as appropriate).5 The NYISO anticipates that the transition will be
completed to permit participation in the Installed Capacity market beginning in March 2017.6
The NYISO is also working to ensure that existing SCRs intending to transition to BTM:NG
Resources satisfy all obligations incurred as a SCR. The NYISO anticipates transitioning existing
SCRs to BTM:NG Resources to allow participation in the Installed Capacity Market beginning in
March 2017. Affected resources will continue to have certain SCR performance testing, data
reporting, and other obligations related to their participation in the SCR program prior to transitioning
to a BTM:NG Resource until the completion of the Winter 2016-2017 Capability Period on April 30,
2017.
3 Should the NYISO determine that it will be unable to implement the Behind-the-Meter Net Generation tariff revisions for the December 13, 2016 market day, it will promptly notify its Market Participants and the Commission.
4 Capitalized terms not otherwise defined herein shall have the meaning specified in Section 2 of the NYISO Market Administration and Control Area Services Tariff and Section 1 of the NYISO Open Access Transmission Tariff.
5 In its March 17 Filing, the NYISO advised the Commission that it was aware of two existing
Generators participating in the NYISO’s wholesale markets that serve behind-the-meter Load. March
17 Filing at 2 n.5. As explained in the March 17 Filing, the NYISO will work to transition these resources to become BTM:NG Resources, or another type of resource as appropriate, upon the effective date of the BTM:NG Tariff Revisions.
6 “Traditional” Generators that sell Unforced Capacity for the months of December 2016 and
January - February 2017, and are transitioning to BTM:NG Resources, are required fulfill their
Installed Capacity market obligations for the months of December 2016 and January - February 2017.
These transitioning resources will thereafter have the opportunity to sell Unforced Capacity as
BTM:NG Resources beginning with the February 2017 ICAP Auctions for delivery starting in March
2017.
Honorable Kimberly D. Bose November 29, 2016
Page 3
IV. Communications and Correspondence
All communications and service in this proceeding should be directed to:
Robert E. Fernandez, General Counsel
Ray Stalter, Director of Regulatory Affairs *Gregory J. Campbell, Attorney
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-8540
Fax: (518) 356-7678
rfernandez@nyiso.com
rstalter@nyiso.com
gcampbell@nyiso.com
*Persons designated for receipt of service.
V.Service
The NYISO will send an electronic link to this filing to the official representative of each party
to this proceeding, to the official representative of each of its customers, to each participant on its
stakeholder committees, to the New York Public Service Commission, and to the New Jersey Board of
Public Utilities. In addition, the complete filing will be posted on the NYISO’s website at
www.nyiso.com.
VI.Conclusion
The New York Independent System Operator, Inc. respectfully requests that the Commission accept this compliance filing and the proposed effective date of December 13, 2016 for the tariff revisions referenced herein.
Respectfully submitted,
/s/ Gregory J. Campbell
Gregory J. Campbell Attorney
New York Independent System Operator, Inc.
10 Krey Blvd.
Rensselaer, New York 12144 (518) 356-8540
gcampbell@nyiso.com
Honorable Kimberly D. Bose November 29, 2016
Page 4
cc:Michael Bardee
Anna Cochrane
Kurt Longo
Max Minzner
Daniel Nowak
Larry Parkinson
J. Arnold Quinn
Douglas Roe
Kathleen Schnorf
Jamie Simler
Gary Will
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person
designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. §385.2010.
Dated at Rensselaer, NY this 29th day of November, 2016.
/s/ Mohsana Akter
Mohsana Akter
Regulatory Affairs
New York Independent System Operator, Inc
10 Krey Blvd
Rensselaer, NY 12144 (518) 356-7560