UNITED STATES OF AMERICA
BEFORE THE

FEDERAL ENERGY REGULATORY COMMISSION

 

 

)

ISO New England Inc. and)Docket No. ER16-2451-000

New England Power Pool Participants)

Committee)

MOTION TO INTERVENE AND LIMITED PROTEST OF

THE NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.

Pursuant to Rules 211, 212, and 214 of the Rules of Practice and Procedure of the Federal
Energy Regulatory Commission the “Commission”), 18 C.F.R. §§ 385.211 and 385.214 (2016),
the New York Independent System Operator, Inc. (“NYISO”) hereby moves to intervene, and
submits a limited protest in the above-captioned proceeding.  This filing addresses a single
aspect of the “Forward Capacity Market Enhancements” (“FCM Enhancements”) proposed by
ISO New England Inc. (“ISO-NE”) and the New England Power Pool Participants Committee.1
With the exception of the single point addressed herein, the NYISO has no objection to the FCM
Enhancements Filing or the timing of its implementation.  Although the issue identified here is
narrow, it is critically important.  If the relief sought by the NYISO is not granted there may be
material pricing inefficiencies that could unnecessarily increase costs for New York consumers
by hundreds of millions of dollars.

The FCM Enhancements Filing would, among other things, revise the qualification
requirements for “Import Capacity Resources” seeking to participate in ISO-NE’s
Reconfiguration Auctions (“RAs”) and make the revisions effective on October 19, 2016 (the

 

 

 

1 ISO New England Inc. and New England Power Pool Participants Committee, Forward

Capacity Market Enhancements, Docket No. ER16-2451-000 (August 19, 2016) (“FCM Enhancements
Filing”).


 

 

“RA Import Proposal”).2  As discussed below, the proposed effective date of this aspect of the
FCM Enhancements creates a substantial risk of unjustifiably increasing New York capacity
prices and creating inefficient price signals in the NYISO-administered capacity market.
Potentially severe economic consequences for New York consumers can be avoided if the
NYISO is allowed a reasonable time to make needed market rule changes to address capacity
exports from constrained capacity areas (“Localities”) in the New York Control Area
(“NYCA”).3

Specifically, Dr. David B. Patton, the President of Potomac Economics, Ltd., the

independent Market Monitoring Unit (“MMU”) for the NYISO,4 estimates based on a

hypothetical 500 MW sale that inefficient price increases potentially up to $341 million may
occur in New York starting on June 1, 2017,5 if the RA Import Proposal becomes effective as
requested.  As discussed below, the actual impact will depend on multiple variables, chiefly the
extent to which capacity from New York Localities is actually sold into ISO-NE’s market.
Although such sales are not certain in the next capacity year, the magnitude of the potential
impact makes it imperative to address this risk.  The NYISO seeks only to avoid inefficient and
therefore unjustified price increases that could result from the RA Import Proposal.

 

 

 

 

2 See FCM Enhancements Filing at 7-10.

3 Constrained capacity areas in the NYISO’s market are “Localities” in the NYISO’s Services
Tariff.  Capitalized terms not otherwise defined herein shall have the meaning specified in the NYISO’s Services Tariff.

4 See attached affidavit of the MMU’s President, David B. Patton (“Patton Affidavit”) at PP 17-

23.

5 ISO-NE’s and the NYISO’s capacity years differ by one month.  ISO-NE’s Tariff defines
“Capacity Commitment Year” as June 1 through May 31.  The NYISO’s Market Administration and Control Area Services Tariff (“NYISO’s Services Tariff”) defines a Capability Year as May 1 through April 30.  For ease of reference, in this pleading the NYISO uses the term “capacity year” to address the concept in both the NYISO and ISO-NE.

 

 

2


 

 

 

 

 

The NYISO is continuing to analyze the implications of this export scenario and is

working expeditiously to develop a solution to the inefficient outcomes that could arise under its
current market rules.  The NYISO has engaged stakeholders on these concerns and is in the early
stages of formulating a proposal.  The issue is extremely complex, however, and an appropriate
solution must address a range of issues, which include capacity market design changes, the
calculation of capacity market requirements, generator obligations, New York State Reliability
Council (“NYSRC”) requirements, NYISO software requirements, and related timing issues.
The NYISO therefore respectfully requests that the Commission defer the
implementation of the RA Import Proposal for one capacity year with respect to generators
located in NYCA Localities, i.e., so that it would first apply for capacity commitments beginning
June 1, 2018.6  This relief would prevent harmful, inefficient economic outcomes in New York
during ISO-NE’s 2017/2018 capacity year.  The NYISO has tailored its requested relief as
narrowly as possible to minimize disruption to ISO-NE’s proposed market enhancements.7
The deferral would not affect commitments that have been made or would be able to be made for ISO-NE’s 2018/2019 capacity year.  It also would not alter the reasonable expectations

 

 

 

 

 

6 The NYISO does not contend that any other aspect of the FCM Enhancements proposal should
be delayed, including allowing capacity resources located in the NYCA but outside of NYCA Localities
from gaining early access to RAs or through capacity supply obligation bilaterals (“CSO Bilaterals”).

7 The Commission has, in other contexts, approved RTO or ISO-wide practices as just and

reasonable generally, while invalidating the applicability of those very same practices in specific, narrow
circumstances because they triggered unjust and unreasonable consequences, or were otherwise unlawful
in those circumstances.  Cf. FirstEnergy Services Company v. Midwest Independent Transmission System
Operator, Inc. 153 FERC ¶ 61,101 at PP 117-18 and 164 (2015), order denying rehearing, 155 FERC ¶
61,174 (2016) (holding that presiding judge erred in holding that it would be just and reasonable to apply
Schedule 39 cost allocation methodology to two departing transmission owners in circumstances where
Schedule 39 was deemed to be inconsistent with the pre-withdrawal tariff, but nonetheless upholding

Schedule 39 as a just and reasonable approach for allocating the costs of transmission upgrades to departing transmission owners on a prospective basis).

 

3


 

 

 

 

 

of generators in NYCA Localities.  The request is only that the opportunity for generators in

NYCA Localities to import into ISO-NE not be accelerated by the FCM Enhancements Filing.8
This delayed effective date for one limited aspect of the FCM Enhancements Filing
would enable the NYISO to work deliberately to adopt a solution to prevent significant market
inefficiencies and adverse consumer impacts in New York.  If this request is denied, the NYISO
would attempt to fashion an immediate market rule change to try to avoid pricing inefficiencies.

I.COMMUNICATIONS

Communications and correspondence regarding this filing should be directed to:


 

Robert E. Fernandez, General Counsel
*Raymond Stalter, Director of Regulatory Affairs *Gloria Kavanah, Senior Attorney

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, N.Y.  12144 Tel:  (518) 356-6000

Fax:  (518) 356-4702 rfernandez@nyiso.com rstalter@nyiso.com

gkavanah@nyiso.com

* persons designated for service.9
II. MOTION TO INTERVENE


*Ted J. Murphy

Hunton & Williams LLP
2200 Pennsylvania Avenue, NW Washington, D.C. 20037
Tel: (202) 955-1500

Fax: (202) 778-2201
tmurphy@hunton.com


The NYISO is the independent entity responsible for administering Commission-

jurisdictional markets for electricity and capacity, and for maintaining electric reliability in the
NYCA.  The NYISO and ISO-NE are neighboring control areas.  There is substantial
interregional trading between the two areas, including exports and imports of capacity.  Changes

 

 

 

8 Capacity can be exported through participation in annual and monthly reconfiguration auctions,
and as proposed in the FCM Enhancements Filing, also annually and monthly through CSO Bilaterals.

9 The NYISO respectfully requests waiver of the requirements of Rule 18 C.F.R. § 385.203(b)(3) (2015) to permit service on more than two persons.

 

 

4


 

 

to one region’s capacity market rules can have substantial impacts on market outcomes in the
other.

As discussed below, ISO-NE’s proposal to accelerate the eligibility of NYCA capacity suppliers to export capacity to ISO-NE, through RAs and CSO Bilaterals, creates a risk of significant inefficiencies in the NYISO’s market.  The NYISO therefore has a direct and
substantial interest in the outcome of this proceeding that cannot be adequately represented by any other party.  It is appropriate and in the public interest that the NYISO be permitted to intervene in this proceeding and participate with full rights as a party.

III.LIMITED PROTEST

A.Background

Under the NYISO’s current capacity market design, a generator exporting capacity from a Locality is treated in the capacity market auction as though it no longer exists.  This means that its continued operation is not properly reflected in the NYISO’s capacity market clearing prices -
which would cause them to inefficiently increase.

In its 2015 State of the Market Report (“SOM Report”) issued in May 2016, the MMU
addressed this issue.  It recommended, among other things, that the NYISO “[m]odify the
capacity market and planning process to better account for capacity that is exported to
neighboring control areas from import-constrained capacity zones.”10  The SOM Report
explained that:

More than 500 MW of capacity was sold from the G-J Locality in each of the last
two ISO-NE Forward Capacity Auctions, which will give the associated generator

 

 

10 See 2015 State of the Market for the New York ISO Markets at xii, 117 (May 2016), available

at:

<http://www.nyiso.com/public/webdocs/markets_operations/documents/Studies_and_Reports/Reports/M
arket_Monitoring_Unit_Reports/2015/NYISO%202015%20SOM%20Report_5-23-2016-
CORRECTED.pdf>.

 

 

5


 

 

 

 

 

Capacity Supply Obligations to New England beginning in June 2018.  Currently,
NYISO’s tariffs and procedures do not specify how it would treat such a
generator in its planning process or in its capacity market. However, an efficient
market and planning process should recognize that a generator that exports from
an import-constrained capacity zone provides more reliability benefit to the
NYCA than a generator of the same size that exports to the same market from the
Rest of State (“ROS”) region.  Hence, we recommend that the NYISO’s capacity
market rules be amended to recognize this value in the spot capacity auctions and
other related processes.11

The quoted language uses the term “import-constrained capacity zones” to refer to certain Localities in the NYISO’s capacity market.  The SOM Report specifically referenced a capacity export ISO-NE awarded to one of the units at the Roseton generating station (“Roseton”) of 511 MW in ISO-NE’s FCA 9 (2018/2019) and 532 MW in FCA 10 (2019/2020).12  Roseton is
located in the G-J Locality.

The SOM Report emphasized that the NYISO should act promptly because the MMU

 

anticipated that “capacity clearing prices in the Lower Hudson Valley could rise far above

competitive levels . . .  at least during the two years for which capacity has already been sold into
ISO-NE.”13  The two years referenced are ISO-NE’s 2018/2019 and 2019/2020 capacity years.
The MMU believed that it was “possible for the NYISO to implement the necessary changes in
time to avoid a detrimental effect on the NYISO capacity market... ”  At the time the SOM

Report was published it was understood that those detrimental effects would not occur until June 2018.14  Based on ISO-NE’s current market rules, the NYISO also believed that there was
sufficient time to resolve this matter.

 

 

 

 

11 SOM Report at 117.

12 SOM Report at n. 103.

13 SOM Report at 117.

14 Id.

 

 

6


 

 

The NYISO began an evaluation of the MMU’s recommendation, including a review of its proposed solution and potential alternatives.  The issue was identified through the NYISO’s project prioritization process as a project to complete in time for the June 1, 2018 start of ISONE’s 2018/2019 capacity year.

Under ISO-NE’s current rules, resources are permitted to sell capacity only in Capacity
Commitment Periods for which they have qualified to sell in the FCA.  Thus, a generator located in the NYCA that did not qualify for FCA 9 could not participate in RAs that do not correspond to FCA 9; i.e., it would not be able to enter into commitments for periods prior to the June 1,
2018 start of the FCA 9 Capacity Commitment Period.  But the FCM Enhancements filing would permit “Import Capacity Resources Backed by One or More External Resources” to participate in earlier RAs and in CSO Bilaterals.15  If these revisions become effective for ISO-NE’s
2017/2018 capacity period, then generators in the NYISO’s Localities that qualified under the
RA Import Proposal could export capacity to New England as early as June 2017.  The RA
Import Proposal therefore exposes the New York customers to the serious pricing inefficiencies identified in the SOM Report a year sooner than expected.

B. If Capacity in NYCA Localities Is Allowed to Be Exported to New England

Before the NYISO Can Make Necessary Rule Changes, it Could Trigger
Market Inefficiencies and Have Significant Consequences for New York
Consumers

The SOM Report described the serious pricing inefficiencies that would result if there were capacity exports from a NYCA Locality to an external control area before the NYISO
implements a market solution.  The Patton Affidavit provides additional information regarding this pricing inefficiency.

 

 

15 See, e.g., proposed sections III.13.4.2.1.2.1.3, III.13.4.2.1.2.1.4, III.13.4.2.1.2.2 3.1, and III.13.4.2.1.2.2 3.2.

 

 

7


 

 

If a resource located in a NYISO Locality exports capacity before the NYISO can amend
its tariffs, then market clearing prices would signal a need for capacity in the Locality that likely
would be substantially in excess of the actual need.16  An efficient market should, but the
NYISO’s current market design does not, recognize that a generator that exports capacity from a
Locality continues to operate in that Locality.  Unless the NYISO’s market design is modified,
New York consumers could experience hundreds of millions of dollars in inefficient price
increases as an unintended consequence of the FCM Enhancements.17
As the Patton Affidavit explains, the precise impact of the inefficient price increases is difficult to quantify because it is dependent on multiple variables.  These variables include the actual volume of sales from a NYISO Locality to ISO-NE, the NYISO’s Installed Capacity
Demand Curves, and the effect of new entry and retirements.  The Patton Affidavit estimates that
the inefficient capacity price impacts in the NYCA during the 2017/2018 Capability Year could
be up to $341 million.  The estimate assumes that 500 MW of ICAP is exported from the G-J
Locality during the 2017/2018 capacity year.  It also assumes that the NYISO’s 2016/2017
Capability Year parameters continue to apply for the 2017/2018 NYISO Capability Year.  These
include the supply, Load forecasts, Locational Minimum Installed Capacity Requirements, and
locational Equivalent Demand Forced Outage Rate.18

While other assumptions might yield a higher or lower price impact, Dr. Patton’s

estimate clearly illustrates the risk of a significant inefficient pricing outcome in New York.

 

 

 

16 Patton Affidavit at PP 10-13.

17 As the Patton Affidavit notes the interaction between the RA Impact Proposal and NYISO’s

capacity market pricing rules is also likely to have impacts on the Long Island and NYCA capacity

Market-Clearing Prices.  See Patton Affidavit at P 23.  The NYISO is only seeking to avoid the inefficient price impacts.

18 Patton Affidavit at P 20.

 

 

8


 

 

 

 

 

C.The Commission Should Defer the Effectiveness of the RA Import Proposal

as Applied to Resources in NYCA Localities Until ISO-NE’s 2018/2019

Capacity Commitment Period to Prevent Significant Market Inefficiencies and Harmful Consumer Impacts

The potential market inefficiencies described above must be addressed, but the

underlying details and measures to address the problem are extremely complex.  The NYISO

anticipated addressing this issue during 2017, in time for the June 2018 expected start of capacity exports from Localities.  The NYISO considered that schedule to be aggressive but achievable given the high priority of this issue.  However, the RA Import Proposal would accelerate the eligibility of exports from New York Localities and significantly reduce the time available for the NYISO to modify its market design.  A number of factors that the NYISO must consider in rectifying the deficiency identified by Dr. Patton are outlined below.

Complex issues being considered include the extent to which capacity exported from a
Locality can be “replaced” by capacity located in the NYISO’s Rest of State area.  The issue of
capacity equivalence or “fungibility” could have a material effect on clearing prices and impact
consumers throughout New York.  The Patton Affidavit discusses this consideration further.19

The NYISO also must evaluate whether its market mitigation measures should be

modified to address exports from constrained Localities to avoid the exercise of market power in different ways than anticipated at the time the NYISO market power rules were developed.20 The Patton Affidavit addresses this concern in more detail.21

Market design changes to address inefficient capacity pricing could raise questions
regarding assumptions in New York’s planning processes, including setting the statewide
Installed Reserve Margin (“IRM”) which is overseen by the NYSRC, and the calculation of

19 See Patton Affidavit at PP 11-12.

20 These rules are set forth in Section 23.4.5 of the NYISO’s Services Tariff.

21 See Patton Affidavit at P 24.

 

 

9


 

 

Locational Minimum Installed Capacity Requirements, which are derived from the IRM.22  Thus
the NYISO will need to consider the potential reliability implications of any proposed solution.
Developing market rule changes for implementation by the 2017/2018 capacity year
would substantially limit the potential solutions that can be considered, and the opportunity for
stakeholders to provide input.  Presently, the optimal market design is unclear, and options need
analyzed and be vetted.

Given the inherent complexity of the issue, the prospects for obtaining the supermajority stakeholder support required for the NYISO to file tariff modifications pursuant to Section 205 of the FPA on such an expedited timetable are uncertain.  Nonetheless, the NYISO is, on a
parallel track with this filing, pursuing an immediate fix with its stakeholders in the event the
Commission denies its request for a deferral.  The status of that effort is described below.
While developing a solution on an abbreviated timeline presents a number of technical challenges, as a practical matter, it also decreases the opportunity to build consensus and reduce differences, and increases the likelihood that any resulting proposal would be more broadly contested at the Commission.  The NYISO believes it would be more prudent to allow the
NYISO an adequate opportunity to work with stakeholders, the NYSRC, and the MMU to fully explore and address issues prior to making a filing.

As noted above, the NYISO originally anticipated modifying its market design so that
necessary changes would be effective in time for exports for sales that occurred in FCA 9; i.e.,
for the 2018/19 capacity year.  Given the RA Import Proposal’s proposed acceleration, the
NYISO has intensified its efforts to develop a timely solution.   The NYISO explained the

 

22 Under Section 215(h)(3) of the Federal Power Act (“FPA”), New York State is authorized to have reliability rules that are more stringent than those adopted by the North American Electric
Reliability Organization and the regional reliability entities.  Under New York law, the NYSRC is
charged with developing such reliability rules.

 

 

10


 

 

market design issue to its stakeholders at a meeting of its Installed Capacity Working Group (“ICAP Working Group”) on August 2 and presented the framework of a proposed immediate solution on August 23.  The NYISO will further discuss that proposal on September 19.  It also discussed the matter with the NYSRC’s Installed Capacity Subcommittee on August 3 and August 30 and is scheduled to do so again on October 5.

In sum, the NYISO has reprioritized and shifted resources away from other projects to focus on this matter.  Despite these efforts, it is clear that the timeline introduced by the RA Import Proposal will not permit a full consideration of pricing inefficiencies identified by Dr. Patton and potential solutions.  The NYISO therefore respectfully asks that the Commission require ISO-NE to defer the implementation date of the RA Import Proposal for one capacity year solely with respect to resources located in NYCA Localities.

D. The NYISO’s Request for a Deferral is Equitable, Will not Disrupt

Reasonable Market Expectations, and is Consistent with Commission Policy Concerning Seams Issues

If NYISO’s request is granted, resources in NYCA Localities would not lose

 

opportunities they currently have under the ISO-NE tariffs.  Indeed, the FCM Enhancements

Filing, including the RA Import Proposal, only received NEPOOL approval in June 2016.  A few resources would not be afforded a new opportunity to export capacity to ISO-NE during the
2017/2018 Capacity Commitment Period.  The NYISO submits, however, that the potential
impact of hundreds of millions of dollars on New York consumers far outweighs a “lost”
opportunity for a handful of potential exporters.

As noted above, the NYISO has no objection to the FCM Enhancements Filing overall,
or to the merits of the RA Import Proposal.  The NYISO does not oppose ISO-NE’s efforts to
expand the ability of regional assets to meet its resource adequacy needs.  The NYISO is simply

 

 

 

11


 

 

requesting a deferral so that it may develop and implement market rule changes that will avoid pricing inefficiencies and harmful consumer impacts in New York.

The NYISO’s request is not unreasonable or inequitable.  The Patton Affidavit states that “approving the deferral is substantially superior to allowing this issue to remain unaddressed.”23 The NYISO’s understanding is that its requested deferral is not likely to have impacts in New
England on the same scale as the potential inefficient capacity price impacts that a deferral
would prevent in New York.

The NYISO is working as quickly as practicable to modify its market design and has narrowed this request to minimize any disruption of one narrow element of a broad package of FCM enhancements.

At this time, resources cannot participate in capacity exports prior to the FCA Capacity
Commitment Period for which they have qualified.  It is the NYISO’s understanding that it was
only in spring of 2016 that ISO-NE proposed to make earlier RA participation possible.  No
party could reasonably claim to have a settled expectation that the RA Import Proposal would be
accepted by the Commission without modification and made effective in October 2016.  In fact,
ISO-NE appears to be contemplating a delayed implementation of certain features of the next
phase of its planned enhancements to its FCM rules (which have not yet been filed).24
The requested deferral is consistent with Commission policy and precedent, which has recognized that rule changes that implicate inter-regional seams sometimes produce unjust and unreasonable results, and that such results should be minimized.25  If the NYISO had discovered

 

 

23 See Patton Affidavit at PP 27-28.

24 See Christopher Parent, ISO-NE, FCM Enhancements Phase II (July 18-20, 2016), available at:
<http://www.iso-ne.com/static-assets/documents/2016/07/07_18_19_20_mc_meeting_materials_1.zip>.

25 For example, the Commission moved to eliminate through-and-out rates in the PJM

Interconnection, Inc. and the Midcontinent Independent System Operator, Inc. as part of its effort to

 

12


 

 

the capacity pricing inefficiency after the RA Import Proposal was implemented the Commission would surely require expedited action to address the matter and to protect New York consumers. In this instance, there is an opportunity to take remedial action to address an unintended but
serious market outcome before it comes into effect.  Moreover, it will be much less disruptive to develop a permanent solution in advance than it would be to try to introduce an emergency
remedy after the implementation of the RA Import Proposal.

Accordingly, the NYISO submits that the Commission should grant its requested relief in
order to avoid unjust and unreasonable price impacts on New York consumers and that its
proposed relief is itself just and reasonable.  As noted above, if a deferral is denied, the NYISO
will attempt to implement an immediate remedy.  But at this time it is uncertain that a measure
could be implemented in time; that it could fully account for interrelated economic, reliability,
planning, and market power considerations; or that it would not have unintended consequences.
In short, although an immediate remedy might be devised, it would be imprudent to rush to
introduce one.  The better course by far is to allow the NYISO time to develop, test, and
implement a solution in 2018.

IV.CONCLUSION

Wherefore, NYISO respectfully requests that the Commission grant its intervention in the
above-captioned proceeding and defer for one year the implementation date of the RA Import
Proposal with respect to resources located in NYISO Localities.  Without Commission action,
the implementation of the RA Import Proposal could harm New York consumers by inefficiently

 

 

minimize the adverse impact of seams between the two regions, and to facilitate cross-market

transactions.  At the same time, it implemented a Seams Elimination Cost Adjustment surcharge as a

transition mechanism to compensate transmission owners for the elimination of through-and-out rates for
cross-border transactions.  See, e.g., Midwest Independent Transmission System Operator, Inc., 105
FERC ¶ 61,212 (2003); Midwest Independent Transmission System Operator, Inc., 105 FERC ¶ 61,288
(2003); Midwest Independent Transmission System Operator, Inc., 106 FERC ¶ 61,106 (2004).

 

 

13


 

 

increasing capacity prices by potentially hundreds of millions of dollars in the NYISO’s 2017/18 Capability Year.

 

 

Respectfully submitted,

 

/s/ Ted J. Murphy

Ted J. Murphy

Counsel for the New York Independent System Operator, Inc.

 

 

Dated: September 9, 2016

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

14