10 Krey Boulevard Rensselaer, NY  12144

 

 

 

 

 

June 20, 2016

 

By Electronic Delivery

 

Kimberly D. Bose, Secretary

Federal Energy Regulatory Commission 888 First Street N.E.

Washington, D.C.  20426

 

Re:    New York Independent System Operator, Inc., Proposed Tariff Revisions

Regarding NYISO’s Cost Allocation Methodology for its Reliability Planning Process; Docket No. ER16-____-000

Dear Ms. Bose:

Pursuant to Section 205 of the Federal Power Act (“FPA”),1 the New York Independent
System Operator, Inc. (“NYISO”) hereby submits proposed revisions to the cost allocation
methodology for the reliability planning component of its Comprehensive System Planning
Process (“Reliability Cost Allocation Methodology”).2  The NYISO proposes to add a new step
under its existing Reliability Cost Allocation Methodology to allocate the costs of regulated
transmission solutions that resolve transmission security violations.  Other proposed revisions
include removing the sunset provision of the Reliability Cost Allocation Methodology contained
in Section 31.5.3.2.1.6 of Attachment Y of the NYISO Open Access Transmission Tariff
(“OATT”) to continue the existing methodology without expiration, and conforming the cost
recovery formulas in Section 6.10 of the OATT (“Rate Schedule 10”) to the revised
methodology.  The NYISO’s proposed revisions were approved by its stakeholders without
objection and by its Board of Directors.

As described in Part V of this letter, the NYISO respectfully requests a waiver of the

Commission’s prior notice requirements to make the removal of the sunset provision in Section

31.5.3.2.1.6 of the OATT effective as of January 1, 2016.  The January 1, 2016, effective date will avoid a gap in the effectiveness of the existing Reliability Cost Allocation Methodology, which would otherwise expire on December 31, 2015.  The NYISO requests that the remaining tariff revisions to enhance the existing Reliability Cost Allocation Methodology have an
effective date of August 19, 2016, which is 60 days after the date of this letter.

 

 

 

1 16 U.S.C. § 824d; 18 C.F.R. § 385.205.

2 Capitalized terms that are not otherwise defined in this filing letter shall have the meaning specified in Attachment Y of the NYISO OATT, and if not defined therein, in the NYISO OATT and the NYISO Market Administration and Control Area Services Tariff.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 2

 

I.List of Documents Submitted

The NYISO submits the following documents along with this filing letter:

A clean version of the proposed revisions to the OATT, effective January 1, 2016

(Attachment I);

A blacklined version of the proposed revisions to the OATT effective January 1, 2016

(Attachment II);

A clean version of the proposed revisions to the OATT, effective August 19, 2016

(Attachment III);

A blacklined version of the proposed revisions to the OATT effective August 19, 2016

(Attachment IV);

A clean version of Section 31.5 of the OATT effective February 19, 2016 (Attachment V);3

A clean version of Section 31.5 of the OATT effective April 1, 2016 (Attachment VI);4

Affidavit of Zachary G. Smith - Transmission Planning for the NYISO (Attachment VII);

and

Transmission Security Cost Allocation Presentation (September 17, 2015), reposted on May

18, 2016 at Market Participants’ request (Attachment VIII).

 

II.Copies of Correspondence

Communications regarding this pleading should be addressed to:


Robert E. Fernandez, General Counsel
Raymond Stalter, Director of Regulatory Affairs *Carl F. Patka, Assistant General Counsel Brian R. Hodgdon, Attorney

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144
Tel:  (518) 356-6000
Fax:  (518) 356-4702
rfernandez@nyiso.com


*Ted J. Murphy

Hunton & Williams LLP
2200 Pennsylvania Avenue, NW Washington, D.C. 20037
Tel:  (202) 955-1500

Fax:  (202) 778-2201
tmurphy@hunton.com

 

*Michael J. Messonnier, Jr.5 Hunton & Williams LLP


 

 

3  Revisions to OATT Section 31.5 were filed in other proceedings on tariff section bases with effective
dates after the effective date requested for the tariff revision removing Section 31.5.3.2.1.6 of the OATT requested
herein.  See Docket Nos. ER16-966-000, -001 (requested effective February 19, 2016); Docket Nos. ER13-102-009,

-010 (requested to be effective April 1, 2016).

4  See footnote 3, supra.

5  The NYISO respectfully requests a waiver of 18 C.F.R. § 385.203(b)(3) to permit service on counsel for the NYISO in both Washington, D.C. and Richmond, VA.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 3

 

rstalter@nyiso.com951 E. Byrd Street

cpatka@nyiso.comRichmond, VA 23219

bhodgdon@nyiso.comTel:  (804) 788-8200

Fax: (804) 344-7999

mmessonnier@hunton.com

* -- Persons designated for service.

 

III.Background

A.NYISO’s Existing Reliability Cost Allocation Methodology

The NYISO’s Comprehensive System Planning Process (“CSPP”) is composed of the
NYISO’s reliability, economic, and public policy transmission planning processes.  The cost
allocation methodology for the reliability planning process component of the CSPP is located in
Section 31.5.3 of the OATT, with the related cost recovery requirements located in Rate
Schedule 10.  The NYISO initially established the Reliability Cost Allocation Methodology in
compliance with Order No. 890.6  The Commission subsequently accepted this methodology,
with minor revisions, as compliant with the Order No. 1000 regional cost allocation principles.7

The existing Reliability Cost Allocation Methodology allocates to Load Serving Entities (“LSEs”) the costs of a regulated solution to a Reliability Need on the New York State Bulk
Power Transmission Facilities (“BPTFs”) that arise from a resource adequacy issue.8  The
solutions eligible for cost allocation include a Responsible Transmission Owner’s regulated
backstop solution or an Other Developer’s or Transmission Owner’s alternative regulated
transmission solution selected by the NYISO as the more efficient or cost-effective transmission solution to a Reliability Need.9

The NYISO employs a “needs-based” methodology that allocates the cost of a reliability solution to those LSEs in New York that contribute to the Reliability Need and primarily benefit from the solution to that need.  More precisely, the existing Reliability Cost Allocation
Methodology has a three-step approach that focuses on whether there is a locational, statewide, or a bounded region Reliability Need arising from a resource adequacy issue.  The NYISO
performs this three-step process using the same system modeling that is used in identifying the Reliability Need necessitating the solution that will receive cost allocation.

 

 

6 See New York Independent System Operator, Inc., Order on Compliance Filing, 125 FERC ¶ 61,068

(2008) (accepting NYISO’s proposed methodology for allocating the costs of transmission projects constructed in response to Reliability Needs as consistent with the cost allocation principles in Order No. 890).

7 See New York Independent System Operator, Inc., 143 FERC ¶ 61,059 at PP 311-318 (2013) (finding the
NYISO’s cost allocation methodology for its reliability planning process as compliant with all but Regional
Principle #4); New York Independent System Operator, Inc., 148 FERC ¶ 61,044 at PP 296-297 (2014) (finding
NYISO’s cost allocation methodology for its reliability planning process as compliant with Regional Principle #4).

8  OATT, Attachment Y, Section 31.5.3.2.1.

9  OATT, Attachment Y, Section 31.5.3.2.1.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 4

 

Step one focuses on those areas within the New York Control Area (“NYCA”) that

have Locational Minimum Installed Capacity Requirements (“LCRs”) (i.e., allocation to LSEs in
Load Zones J, K, and G through J), which are referred to herein as “LCR Zones.”  The costs of
reliability upgrades in LCR Zones are allocated to LSEs in those Load Zones.  In step two,
the NYISO runs its reliability simulation model with all internal transmission constraints relaxed
to determine whether an unconstrained NYCA would have a Loss of Load Expectation
(“LOLE”) of less than 0.1 days per year.  If not, the reliability upgrades necessary to meet the
LOLE threshold are allocated to all Load Zones based on their coincident peak load contribution.
LSEs in LCR Zones receive credit for meeting their LCRs under this calculation.  If the
reliability simulation shows that there are still Reliability Needs, step three requires the NYISO
to apply a binding interface test.  This test identifies binding transmission constraints that prevent
the deliverability of capacity throughout the NYCA and allocates the remaining costs to LSEs
within the constrained area.

The existing Reliability Cost Allocation Methodology does not provide for the allocation
of the costs of a regulated transmission solution to a Reliability Need on the BPTFs resulting
from thermal, voltage, or dynamic stability transmission security issues.  Such costs are currently
deemed local and not allocated and recovered by the NYISO under the OATT.10  The NYISO
has previously informed the Commission, as part of its Order No. 1000 proceeding, of this
potential gap in its Reliability Cost Allocation Methodology and its intent to develop a new
process step to address it.11  The NYISO indicated that it would work with its stakeholders to
develop the transmission security step.  In the meantime, the NYISO included a placeholder in
Section 31.5.3.2.1.4 of the OATT, indicating that it would take such action with stakeholders.
The NYISO has subsequently worked with its stakeholders to develop this new step.12

In addition, the Reliability Cost Allocation Methodology includes a sunset provision that
requires the NYISO to evaluate the methodology with its stakeholders and to file either a
continuation of its existing methodology or a revised methodology for the Commission’s

 

 

 

 

10 OATT Section 31.5.3.2.1.4 (filed in 2008 as Section 14.2(d) of the OATT).

11 See New York Independent System Operator, Inc., Order on Rehearing and Compliance, 151 FERC ¶
61,040 at P 124 (2015) (acknowledging the NYISO’s development of a transmission security cost allocation
methodology and indicating that the Commission would address the methodology when it is filed by the NYISO);
New York Independent System Operator, Inc., and New York Transmission Owners, Compliance Filing, Docket Nos.
ER13-102-001, -002, -003 at pp 16-17 (September 15, 2014); New York Independent System Operator, Inc., Order
on Rehearing and Compliance, 148 FERC ¶ 61,044 at P 298 (2014); New York Independent System Operator, Inc.,
and New York Transmission Owners, Compliance Filing, Docket No. ER13-102-000 at p 56 (October 15, 2013).

12 As a part of the NYISO’s proposed revisions in its October 2015 Reliability-Must-Run compliance filing, the NYISO reviewed revisions to the existing cost allocation methodology with stakeholders on February 25, 2014, November 24, 2014, December 9, 2014, February 3, 2015, September 17, 2015, September 24, 2015, and October
13, 2015.  See New York Independent System Operator, Inc., Compliance Filing, Docket Nos. EL15-37-002 and
ER16-120-000 at p 60 (October 19, 2016) (“RMR Filing”).  As a part of the current filing, the NYISO reviewed the identical revisions (omitting those portions related to the proposed RMR process) with stakeholders on May 16,
2016, May 19, 2016, and May 25, 2016.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 5

 

approval prior to January 1, 2016, which was the start date of a new cycle for the NYISO’s
CSPP.13

B.NYISO Reliability-Must-Run Proceeding

On February 19, 2015, the Commission directed the NYISO to establish a reliability-

must-run (“RMR”) process in its OATT to govern “the retention of and compensation to

generating units required for reliability, including procedures for designating such resources, the
rates, terms and conditions for RMR service, provisions for the allocation of costs of RMR
service, and a pro forma service agreement for RMR service.”14  On October 19, 2015, the
NYISO filed tariff revisions proposing to situate its RMR process within the Gap Solution
portion of its reliability planning process.15  As a result, the NYISO proposed to revise its
Reliability Cost Allocation Methodology in Section 31.5.3 of the OATT to allow the NYISO to
allocate under its OATT the costs of RMR service.  As part of its revisions, the NYISO proposed
to modify the Reliability Cost Allocation Methodology to: (i) remove the sunset provision, and
(ii) provide for the allocation of the costs of RMR service or regulated transmission solutions
that are required to address any type of Reliability Need, including a need resulting from a
transmission security issue.16

In its April 21, 2016 order, the Commission directed the NYISO to separate its proposed
RMR process from the Gap Solution process under its reliability planning process and, in doing
so, also rejected the revisions to the Reliability Cost Allocation Methodology as beyond the
scope of the RMR proceeding.17  Specifically, the Commission rejected the proposed revisions
that would have: (i) provided cost allocation provisions to address reliability solutions that
resolve transmission security violations and (ii) satisfied the NYISO’s filing requirement under
Section 31.5.3.2.1.6 of the OATT to continue the use of the existing Reliability Cost Allocation
Methodology.18  The Commission directed the NYISO to submit the filing required under
Section 31.5.3.2.1.6 of the OATT within 60 days and invited the NYISO to re-file pursuant to
Section 205 of the Federal Power Act its proposed revisions to the Reliability Cost Allocation
Methodology.19

On June 7, 2016, the NYISO filed a compliance filing to address, in part, the

Commission’s April 21, 2016 order.  In the compliance filing, the NYISO proposed to remove

 

13 OATT Section 31.5.3.2.1.6 (filed in June 2008 as Section 14.2(f) of the OATT); see New York

Independent System Operator, Inc., Order No. 890 Transmission Planning Compliance Filing, Docket No. OA0852-
001 at pp 9-10 (June 18, 2008).

14  New York Independent System Operator, Inc., Order Instituting Section 206 Proceeding and Directing
Filing to Establish Reliability Must Run Tariff Provisions, 150 FERC ¶ 61,116 at P 11 (2015) (“RMR Order”).

15  RMR Filing at pp 13-14.

16  Id. at pp 56-68.

17  New York Independent System Operator, Inc., Order on Compliance and Rehearing, 155 FERC ¶ 61,076 at PP 113 (April 21, 2016) (“RMR Compliance Order”).

18  Id. at PP 113-114.

19  Id. at PP 114-115.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 6

 

the revisions concerning the Reliability Cost Allocation Methodology from Section 6.10 (and from subsequently effective versions of Section 31.5) of the OATT that were rejected in the April 21, 2016 order.20

IV.    Description of Proposed Tariff Revisions

The NYISO proposes to amend the reliability cost allocation methodology in Attachment
Y, OATT Section 31.5, to allocate the costs of regulated transmission solutions that resolve not
only resource adequacy needs, but also transmission security violations.  The NYISO also
proposes to remove the sunset date associated with its existing Reliability Cost Allocation
Methodology.  The revised methodology will appropriately allocate the costs of a regulated
transmission solution eligible for cost allocation under the OATT to those LSEs that contribute
to a Reliability Need and, therefore, benefit from that solution.  Additionally, the revised
methodology remains in compliance with the Commission’s six Order No. 1000 regional cost
allocation principles.

The NYISO’s revised cost allocation methodology is supported by the affidavit of Zachary G. Smith, Director - Transmission Planning for the NYISO, which is included as Attachment V to this letter.

A. Removal of Reliability Cost Allocation Methodology Sunset Provision

The NYISO proposes to continue its existing Reliability Cost Allocation Methodology in
Section 31.5.3 of the OATT.  Section 31.5.3.2.1.6 of the OATT requires the NYISO to file with
the Commission to either continue applying or revise its existing Reliability Cost Allocation
Methodology for the planning cycle beginning on January 1, 2016.21  The NYISO, through its
stakeholder process, reviewed its current cost allocation methodology and determined that it
should continue this methodology without expiration.  The Commission previously accepted the
Reliability Cost Allocation Methodology for regulated transmission solutions that resolve
resource adequacy issues.22  The NYISO, therefore, requests that the Commission accept this
filing as satisfying its filing requirement set forth in Section 31.5.3.2.1.6 and accept, with the
removal of that tariff provision, the NYISO’s continued use of the Reliability Cost Allocation

 

 

20  New York Independent System Operator, Inc., Compliance Filing, Docket No. ER16-120-002 (June 7,

2016).

21  Section 31.5.3.2.1.6 of the OATT provides, in relevant part: “This cost allocation methodology would be
used for any regulated backstop solution identified by the ISO prior to January 1, 2016 or alternative regulated
transmission solution selected by the ISO prior to the completion of the planning cycle commencing January 1,
2014, that is required to meet Reliability Needs identified in the RNA.  Costs associated with any regulated
transmission backstop solution identified by the ISO on or after January 1, 2016 or alternative regulated
transmission solution selected by the ISO as part of the planning cycle commencing January 1, 2016 will be
allocated according to a methodology, which, after proper consideration within the ISO stakeholder process, will be
filed by the ISO for the Commission’s approval prior to January 1, 2016, in accordance with the ISO governance
process.  The filing may provide for a continuation of the foregoing methodology or a revised methodology.”

22  See New York Independent System Operator, Inc., Order No. 890 Transmission Planning Compliance Filing, Docket No. OA0852-001 at pp 9-10 (June 18, 2008).


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 7

 

Methodology without expiration.  As described in Sections IV.B.1 and C below, and in

Attachment V, the existing resource adequacy cost allocation methodology has been accepted by the Commission and remains just and reasonable because it allocates the costs of solutions to the LSEs that benefit from the reliability solution.

B. The Revised Reliability Cost Allocation Methodology

Building off of the NYISO’s existing, Commission-accepted Reliability Cost Allocation Methodology, the NYISO will continue to apply its existing methodology for allocating the costs of a solution to a Reliability Need that arises from resource adequacy issues.  If, after addressing the resource adequacy issue, there remains further issues that contribute to the Reliability Need, the NYISO proposes to allocate those costs of the project that are attributable to further
reliability issues in the manner described in Parts IV.B.1 through IV.B.4 below.

More precisely, the NYISO will perform the steps to resolve the different types of

reliability issues based on the following hierarchy: (i) resource adequacy, (ii) BPTF thermal

transmission security, (iii) BPTF voltage security, (iv) dynamic stability, and (v) short circuit.23 The NYISO will proceed through this hierarchy until all of the costs of the solution have been
addressed.  The NYISO developed this hierarchy to reflect the level of importance of the
reliability issue underlying each of these steps in relation to maintaining system reliability.   The NYISO’s methodology is consistent with traditional electric planning practice, which begins by providing for resource adequacy with the design and siting of supply resources to provide
sufficient resources to service load.  This is followed by providing that the transmission system can accommodate the delivery of power from these supply resources to loads without creating
thermal overloads and ensuring that there is sufficient voltage and dynamic support for that
delivery.  Next, the methodology provides for maintaining dynamic system stability on the
BPTF.  Finally, solutions to exceeding fault current ratings of circuit breakers will be treated as a local matter without cost allocation through the NYISO’s tariff.

1.Resource Adequacy Cost Allocation Step

The first step of the revised Reliability Cost Allocation Methodology will continue to be
the existing resource adequacy cost allocation methodology described in Part III.A above.  The
Commission has previously determined that this methodology satisfies its six Order No. 1000
regional cost allocation principles, and this methodology continues to be just and reasonable, as
it, among other things, allocates the costs of new transmission facilities to LSEs based on their
contribution to the Reliability Need requiring the solution and the benefit that LSEs derive from
the solution.24

 

 

 

 

 

23  Proposed OATT, Attachment Y, Section 31.5.3.2.

24  See New York Independent System Operator, Inc., 143 FERC ¶ 61,059 at PP 311-318 (2013); New York Independent System Operator, Inc., 148 FERC ¶ 61,044 at PP 296-297 (2014).


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 8

 

2. BPTF Transmission Security Cost Allocation Step

Under this step, the NYISO will first allocate the costs for the portion of a regulated

transmission solution attributable to a thermal transmission security issue on the BPTFs and then the costs for the portion attributable to a voltage security issue on the BPTFs.

BPTF Thermal Transmission Security Cost Allocation Step

For the portion of a regulated transmission solution attributable to a BPTF thermal

transmission security issue, the NYISO will allocate the cost of the solution to those Subzones

that contribute to a thermal overload on the BPTFs based on the relative contribution of the Load
in each Subzone to the transmission security issue as described below.  The methodology is
illustrated in an example provided to stakeholders following the May 16, 2016 Electric System
Planning Working Group meeting, which is included in Attachment VI to this letter.  The use of
a Subzone evaluation methodology is consistent with the operation and market design of the
NYISO’s system and is the most granular level at which the NYISO’s billing and settlement
system can allocate the costs to LSEs that receive the benefit from the solution.

The NYISO will perform the BPTF thermal transmission security step using the same

system modeling that is used in identifying the Reliability Need necessitating the solution, which
costs are being allocated.25  The NYISO will first identify for each load bus in a Subzone a
“nodal distribution factor” and “nodal megawatt flow.”  The “nodal distribution factor”
represents the percentage of a Load that flows across the facility subject to the Reliability
Need.26  The sign (positive or negative) of the nodal distribution factor represents the direction of
the flow.27  The “nodal megawatt flow” represents the number of megawatts that flows across
the facility subject to the Reliability Need due to the Load.28  It is calculated by multiplying the
amount of Load in megawatts for the bus (the “Nodal Load”) by the nodal distribution factor
(positive or negative) for the bus.29

Based on these determinations, the NYISO will identify which Loads contribute to the
overloading of the facility and which help to resolve the overloading of the facility.  The Nodal
Load for a load bus with a positive nodal distribution factor contributes to the overloading
facility and is referred to as a “contributing Load.”30  The nodal megawatt flow for this Load is
referred to as “contributing flow.”31  The Nodal Load for a load bus with a negative nodal

 

 

 

 

25  Proposed OATT, Attachment Y, Section 31.5.3.2.2.1.

26  Proposed OATT, Attachment Y, Section 31.5.3.2.2.1.

27  Proposed OATT, Attachment Y, Section 31.5.3.2.2.1.

28  Proposed OATT, Attachment Y, Section 31.5.3.2.2.2.

29  Proposed OATT, Attachment Y, Section 31.5.3.2.2.2.

30  Proposed OATT, Attachment Y, Section 31.5.3.2.2.3.

31  Proposed OATT, Attachment Y, Section 31.5.3.2.2.3.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 9

 

distribution factor helps to resolve the overloading of the facility and is referred to as a “helping Load.”32  The nodal megawatt flow for this Load is referred to as “helping flow.”33

The NYISO will then determine which of the contributing Loads and helping Loads have a material impact on the Reliability Need.  The NYISO will first calculate the “contributing
materiality threshold,” which represents the percentage of all contributing Load that flows across the overloaded facility.34  This is calculated by dividing the sum of all contributing flow by the sum of all contributing Load.35  The NYISO will similarly calculate the “helping materiality
threshold,” which represents the percentage of all helping Load that flows across the overloaded element.36  This is calculated by dividing the sum of all helping flow by the sum of all helping
Load.37  For each load bus, the nodal megawatt flow will be considered material if the nodal
distribution factor is: (i) greater than or equal to the contributing materiality threshold, or (ii) less than or equal to the helping materiality threshold.38

The NYISO will calculate the net material flow for each Subzone as the sum of the

material Subzone contributing flow and material Subzone helping flow for that Subzone.39

Based on the net material flow, the NYISO will calculate the allocated flow for each Subzone.40
If the net material Subzone flow for a Subzone is positive, the allocated flow is equal to the net
material Subzone flow.  If the net material Subzone flow for a Subzone is negative or zero, the
allocated flow for that Subzone is zero.  Based on the net material flow, a Subzone that is
contributing to the overload will be allocated costs for the solution to the Reliability Need,
whereas a Subzone that is helping to alleviate the overload will not be allocated costs.

The NYISO will then check the reasonableness of the resulting allocation to verify that
sufficient contributing flow is being allocated costs.  If the total allocated flow is less than a
majority of the total contributing flow, represented as 60%, then the contributing materiality
threshold will be reduced until the total allocated flow is at least 60% of the total contributing
flow.41

Finally, the NYISO calculates the allocation percentage for each Subzone by dividing the total allocated flow for each Subzone by the total of all allocated flow in the NYCA.42

 

 

32  Proposed OATT, Attachment Y, Section 31.5.3.2.2.4.

33  Proposed OATT, Attachment Y, Section 31.5.3.2.2.4.

34  Proposed OATT, Attachment Y, Section 31.5.3.2.2.3.

35  Proposed OATT, Attachment Y, Section 31.5.3.2.2.3.

36  Proposed OATT, Attachment Y, Section 31.5.3.2.2.3.

37  Proposed OATT, Attachment Y, Section 31.5.3.2.2.4.

38  Proposed OATT, Attachment Y, Section 31.5.3.2.2.5.

39  Proposed OATT, Attachment Y, Section 31.5.3.2.2.5.

40  Proposed OATT, Attachment Y, Section 31.5.3.2.2.6.

41  Proposed OATT, Attachment Y, Section 31.5.3.2.2.6.

42  Proposed OATT, Attachment Y, Section 31.5.3.2.2.7.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 10

 

If a single solution addresses multiple BPTF thermal transmission security issues, the NYISO will calculate weighting factors based on the ratio of the present value of the estimated costs for individual solutions to the costs of resolving each BPTF thermal transmission security issue.43  The NYISO will apply the weighting factors to the cost allocation calculated for each Subzone for each individual BPTF thermal transmission security issue.44

In order to ensure that costs allocated to individual Subzones are commensurate with the benefit, the NYISO will exclude a Subzone from cost allocation if it does not exceed a de
minimis impact threshold.  If a Subzone is assigned a BPTF thermal transmission security cost allocation less than a de minimis dollar threshold, that Subzone will not be allocated costs.
However, the total de minimis Subzones may not exceed 10% of the total BPTF thermal
transmission security cost allocation.45  The de minimis dollar threshold would be reduced until the total de minimis Subzones do not exceed 10% of the total BPTF thermal transmission
security cost allocation.  The de minimis threshold is initially $10,000.

BPTF Voltage Security Cost Allocation Step

If, after addressing any resource adequacy or BPTF thermal transmission security issues, there remains a BPTF voltage security issue, the NYISO will allocate the costs of addressing the voltage security issue on a Load-ratio share basis to each Subzone to which the substation
subject to the violation is connected.  This is determined based on the total peak Load for that Subzone.46  Since transmission system voltage issues are inherently local in nature, it is
reasonable to allocate the costs of resolving these issues at the Subzone level, which is the lowest level of granularity at which the NYISO can allocate these costs.

3.Dynamic Stability Cost Allocation Step

If, after completion of the preceding steps in the methodology, there remains a dynamic
stability issue, the NYISO will allocate the costs of the portion of the solution attributable to
resolving a dynamic stability issue to all Subzones in the NYCA on a Load-ratio share basis.47
This additional step in the hierarchy is necessary as a regulated transmission solution may be
required to address a Reliability Need resulting from dynamic stability issues.  Dynamic stability
is a systemic issue that can lead to widespread cascading and outages across the whole system.
For this reason, the entire NYCA benefits from a solution resolving a dynamic stability issue.

 

 

 

 

 

43  Proposed OATT, Attachment Y, Section 31.5.3.2.2.8.

44  Proposed OATT, Attachment Y, Section 31.5.3.2.2.8.

45  Proposed OATT, Attachment Y, Section 31.5.3.2.2.9.  If the total allocation percentage of all de minimis Subzones is greater than 10%, then the de minimis monetary threshold will be reduced until the total allocation
percentage of all de minimis Subzones is less than or equal to 10%.  Id.

46  Proposed OATT, Attachment Y, Section 31.5.3.2.3.

47  Proposed OATT, Attachment Y, Section 31.5.3.2.4.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 11

 

4.Short Circuit Issues

Finally, if, after the completion of all of the prior steps in the methodology, there remains a short circuit issue, the short circuit issue will be deemed a local issue and the related costs will not be allocated under the OATT.48  Despite not receiving cost allocation under the OATT, the NYISO proposes to insert this final step for completeness of the cost allocation process.  It
clarifies how the NYISO will address a Reliability Need that results from a short circuit issue.
Short circuit issues, or fault current issues, are inherently local and driven primarily by local
generators, transmission system configuration, and transmission system impedance.  Regional
load and power transfers do not contribute to fault current and, therefore, should not be allocated costs for Reliability Needs related to fault current.

C.Consistency of Revised Reliability Cost Allocation Methodology with Order

No. 1000 Cost Allocation Principles

Order No. 1000 required a method, or set of methods, for allocating the costs of new
transmission facilities selected by the NYISO for purposes of allocating these costs under the
NYISO OATT.  The Commission established the Order No. 1000 six regional cost allocation
principles that must be satisfied by a cost allocation methodology.49  The Commission has
previously determined that the NYISO’s existing Reliability Cost Allocation Methodology
complies with these six regional cost allocation principles.50  As described above, the NYISO’s
proposed enhancements to the existing Reliability Cost Allocation Methodology would enable
the NYISO to allocate the costs of transmission solutions to Reliability Needs based upon not
only resource adequacy but also transmission security issues.  As explained below, the
Reliability Cost Allocation Methodology, as revised in this filing, remains consistent with the
Commission’s six regional cost allocation principles and constitutes a just and reasonable
methodology in allocating the cost of regulated transmission solutions to Reliability Needs.

Regional Principle #1

Regional Principle #1 provides that

The  cost  of  transmission  facilities  must  be  allocated  to  those  within  the
transmission planning region that benefit from those facilities in a manner that is
at least roughly commensurate with estimated benefits. In determining the
beneficiaries of transmission facilities, a regional transmission planning process
may  consider  benefits  including,  but  not  limited  to,  the  extent  to  which
transmission facilities, individually or in the aggregate, provide for maintaining

 

 

 

 

48  Proposed OATT, Attachment Y, Section 31.5.3.2.5.

49  Order No. 1000 at PP 586, 603.

50  New York Independent System Operator, Inc., 148 FERC ¶ 61,044 at PP 296-297 (2014) (finding

NYISO’s cost allocation methodology for its reliability planning process as compliant with Regional Principle #4).


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 12

 

reliability and sharing reserves, production cost savings and congestion relief, and/or meeting Public Policy Requirements.51

The NYISO’s revised Reliability Cost Allocation Methodology maintains a

“beneficiaries pay” approach and is compliant with Regional Principle #1.  Under the NYISO’s
revised needs-based methodology, the NYISO will allocate under each step in the methodology
only that portion of the regulated transmission solution to a Reliability Need that is attributable
to the specific reliability issue addressed by that step.  Within each step of the methodology, the
NYISO will only allocate the costs of the solution to those LSEs that contribute to creating the
reliability issue and, likewise, benefit from the solution.  For the resource adequacy step, costs
are appropriately allocated to LSEs at the Load Zone level.  Resource adequacy is modeled based
upon Load Zones, at the major interfaces, and resource adequacy Reliability Needs arise as LSEs
obtain resources and serve customers within these zones.  For the transmission security steps, the
NYISO proposes to allocate costs to LSEs that contribute to such Reliability Needs at the

Subzone level, as transmission security analysis uses nodal models that are sufficiently discrete
to identify Subzonal contributions.  The Subzone level is the lowest level of granularity at which
the NYISO can allocate such costs under its billing and settlement software and procedures.
Finally, for the dynamic stability step, the NYISO proposes to allocate the costs to LSEs across
the NYCA because a dynamic stability Reliability Need is a system-wide stability issue
impacting all LSEs.

Regional Principle #2

Regional Principle # 2 requires that “those that receive no benefit from transmission

facilities, either at present or in a likely future scenario, must not be involuntarily allocated any of the costs of those transmission facilities.”52  The methodology will not allocate costs to
customers that receive no benefit from the transmission facilities at issue.  As described in
response to Regional Principle #1, the methodology only allocates the costs of transmission solutions to LSEs that contribute to the Reliability Need and, therefore, that benefit from the solution to that need.  Therefore, the NYISO’s revised needs-based cost allocation methodology for the regional planning process is compliant with Regional Principle #2.

Regional Principle #3

Regional Principle # 3 requires that:

If a benefit to cost threshold is used to determine which transmission facilities
have sufficient net benefits to be selected in a regional transmission plan for the
purpose of cost allocation, it must not be so high that transmission facilities with
significant positive net benefits are excluded from cost allocation. A public utility
transmission provider in a transmission planning region may choose to use such a
threshold to account for uncertainty in the calculation of benefits and costs. If

 

51  Order No. 1000 at P 622.

52  Order No. 1000 at P 637.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 13

 

adopted, such a threshold may not include a ratio of benefits to costs that exceeds

1.25 unless the transmission planning region or public utility transmission provider justifies and the Commission approves a greater ratio.53

The NYISO’s revised cost allocation methodology for the regional planning process
complies with Regional Principle #3, as the methodology does not use a “benefit to cost”
threshold.

Regional Principle #4

Regional principle #4 requires that:

The allocation method for the cost of a transmission facility selected in a regional
transmission plan must allocate costs solely within that transmission planning
region unless another entity outside the region or another transmission planning
region voluntarily agrees to assume a portion of those costs.  However, the
transmission planning process in the original region must identify consequences
for other transmission planning regions, such as upgrades that may be required in
another region and, if the original region agrees to bear costs associated with such
upgrades, then the original region’s cost allocation method or methods must
include provisions for allocating the costs of the upgrades among the entities in
the original region.54

The NYISO does not propose in this filing any changes to its tariff requirements

applicable to Regional Principle #4.  Specifically, as previously accepted by the Commission, the
NYISO’s revised Reliability Cost Allocation Methodology continues to not provide for the
allocation of the costs of regulated transmission projects to entities outside of the NYCA.  Nor
has the NYISO proposed revisions to its existing tariff requirements, which address identifying
the consequences of the reliability transmission project on other regions or amended its existing
tariff provision stating that the NYISO will not bear the cost of required upgrades in another
region.55 Accordingly, the NYISO’s revised Reliability Cost Allocation Methodology complies
with Regional Principle #4.

Regional Principle #5

Regional Principle # 5 requires that:

The cost allocation method and data requirements for determining benefits and
identifying beneficiaries for a transmission facility must be transparent with

 

 

53  Order No. 1000 at P 646.

54  Order No. 1000 at P 657.

55  See OATT Attachment Y Section 31.2.2.7.  The Commission accepted these tariff requirements as compliant with regional principle #4.  New York Independent System Operator, Inc., Order on Rehearing and Compliance, 148 FERC ¶ 61,044 at P 335 (2014).


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 14

 

adequate documentation to allow a stakeholder to determine how they were applied to a proposed transmission facility.56

The revised methodology in Section 31.5.3.2 of the OATT provides transparent

information on the methodology and corresponding data requirements for determining benefits
and identifying beneficiaries.  The NYISO provides sufficient information for stakeholders to
determine how the methodology and requirements were applied for a specific project.  As an
initial matter, the NYISO has not amended its existing Reliability Cost Allocation Methodology
as it relates to resource adequacy, which step has already been determined by Commission to
satisfy Regional Principle #5.  The NYISO will administer the new cost allocation steps

proposed in this filing in the same transparent manner as the existing step.  The revised tariff
language in Section 31.5.3.2 includes detailed descriptions of the proposed steps in the
methodology, including the NYISO’s process steps and formulas for administering them.  In
addition, the NYISO has reviewed examples applying these formulas with stakeholders, which
presentation material is available on the NYISO’s website.57  Finally, the NYISO presents the
results of its analysis to stakeholders and posts them on its website.  Accordingly, the NYISO’s
revised cost allocation methodology for the regional planning process complies with Regional
Principle #5.

Regional Principle #6

Regional principle # 6 requires that:

A transmission planning region may choose to use a different cost allocation method for different types of transmission facilities in the regional transmission plan, such as transmission facilities needed for reliability, congestion relief, or to achieve Public Policy Requirements.  Each cost allocation method must be set out clearly and explained in detail in the compliance filing for this rule.58

The NYISO’s proposed tariff revisions in this filing do not amend the NYISO’s existing
approach, previously accepted by the Commission, of using different cost allocation
methodologies for its reliability planning process (Section 31.5.3 of the OATT), economic
planning process (Section 31.5.4 of the OATT), and Public Policy Transmission Planning
Process (Section 31.5.5 of the OATT).  The Commission has previously determined that the
aforementioned methodologies satisfy the requirement to be set out clearly and explained in
detail.  As described in response to Regional Principle #5, the NYISO has described its proposed

 

56  Order No. 1000 at P 668.

57  See, e.g., Transmission Security Cost Allocation Presentation (September 17, 2015 reposted on May 18, 2016 at stakeholder request) attached hereto and available at:

http://www.nyiso.com/public/webdocs/markets_operations/committees/bic_espwg/meeting_materials/2016-05-

16/TS_cost_allocation_ESPWG_2015-09-17.pdf ; Transmission Security Cost Allocation Presentation (September 24, 2015) available at:

http://www.nyiso.com/public/webdocs/markets_operations/committees/bic_espwg/meeting_materials/2015-09-
24/TS_cost_allocation_ESPWG_2015-09-24.pdf.

58  Order No. 1000 at P 685.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 15

 

revisions to the Reliability Cost Allocation Methodology in detail in Section 31.5.3.2 of the

OATT, including the detailed process steps and formulas and the reasons for each.  Therefore, the NYISO’s revised cost allocation methodology for the regional planning process remains compliant with Regional Principle #6.

D. Other Revisions to Cost Allocation Provisions

The NYISO proposes the following additional clarifications and enhancements related to the NYISO’s Reliability Cost Allocation Methodology:

  Include in Section 31.5.3.1.3 of the OATT a reference to Subzones, along with Load
Zones, as the new transmission security cost allocation methodologies are allocated
on a Subzone basis.59

  Remove Section 31.5.3.2.1.4 of the OATT, which contains the placeholder for the
NYISO, in conjunction with stakeholders, to develop a step in the Reliability Cost
Allocation Methodology to allocate costs for transmission solutions to a Reliability
Need based upon transmission security issues.

  Relocate from Section 31.5.3.2.1.5 to Section 31.5.1.3 of the OATT language

indicating that costs related to deliverability of a resource are addressed under the NYISO’s deliverability procedures in Attachment S of the OATT.60

E.Rate Schedule 10

Rate Schedule 10 of the OATT establishes the Reliability Facilities Charge pursuant to
which the NYISO recovers the costs of those regulated transmission projects eligible for cost
allocation and recovery under the OATT.  The NYISO’s revisions to its Reliability Cost
Allocation Methodology would allocate costs of transmission security violations on a Subzone
basis.  The NYISO proposes minor, conforming revisions to the cost recovery formulas in
Section 6.10.3 of the OATT to reference both Load Zones and Subzones, as applicable.

V.    Proposed Effective Date

The NYISO requests a waiver of the Commission’s prior notice requirements61 to make
the removal of the sunset provision of the Reliability Cost Allocation Methodology in OATT
Section 31.5.3.2.1.6 effective on January 1, 2016.62  There is good cause for a waiver under
Section 35.3 of the Commission’s regulations.  The January 1, 2016 effective date will provide
for the uninterrupted effectiveness of the NYISO’s resource adequacy component of the

 

59  Proposed OATT, Attachment Y, Section 31.5.3.1.3.

60  Proposed OATT, Attachment Y, Section 31.5.1.3.


61


18 C.F.R. §§ 35.3 and 35.11.


62  See Central Hudson Gas and Electric Corp., 60 FERC ¶ 61,106 at PP 338-339 (1992), reh'g denied, 61 FERC ¶ 61,089 (1992).


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 16

 

Reliability Cost Allocation Methodology following the December 31, 2015 sunset date.  The
NYISO is not proposing in this filing any revision to the resource adequacy component of the
methodology that was previously approved by the Commission.  Stakeholders have been on
notice regarding this proposed change since at least October 19, 2015 when the NYISO filed
with the Commission to remove this provision as part of its RMR compliance filing.  Moreover,
no Market Participant will be prejudiced by this request as there are no Developers currently
eligible to allocate the costs of a regulated transmission solution in the reliability planning
process, and the methodology would not be applied unless and until a Developer becomes
eligible for such allocation.

The NYISO requests that the remaining revisions to the Reliability Cost Allocation

Methodology become effective 60 days after the date of this filing letter—i.e., August 19, 2016. The NYISO is currently conducting its reliability planning process for the 2016 cycle with the commencement of a Reliability Needs Assessment.  Accordingly, approval of the new
transmission security steps by August 19, 2016 will be timely for allocating the costs of any required solutions to Reliability Needs identified during this planning cycle.

VI.    Requisite Stakeholder Approval

The NYISO and its stakeholders collaboratively developed the proposed tariff revisions at
meetings of the Electric System Planning Working Group in February, March, and April 2015 and,
again, in May 2016.  A majority of the stakeholder Operating Committee approved the proposed
tariff revisions by a show of hands vote on May 19, 2016, and a majority of the stakeholder
Management Committee approved the proposed revisions by a show of hands vote on May 25, 2016.
On June 14, 2016, the NYISO’s Board of Directors approved a motion directing the NYISO to file
the proposed tariff revisions.

VII.    Service List

The NYISO will send an electronic copy of this filing to the official representative of

each of its customers, to each participant on its stakeholder committees, to the New York Public
Service Commission and the New Jersey Board of Public Utilities.  In addition, the complete
public version of this filing will be posted on the NYISO’s website at www.nyiso.com.


 

 

Honorable Kimberly D. Bose June 20, 2016

Page 17

 

VIII.Conclusion

WHEREFORE, for the foregoing reasons, the New York Independent System Operator,
Inc. respectfully requests that the Commission accept the proposed tariff changes identified in
this filing with an effective date of January 1, 2016, for the removal of Section 31.5.3.2.1.6 of the
OATT and an effective date of 60 days following the date of this filing for the remaining
proposed revisions.

Respectfully submitted,

NEW YORK INDEPENDENT SYSTEM OPERATOR, INC. BY: /s/ Carl F. Patka


Robert E. Fernandez, General Counsel
Raymond Stalter, Director of Regulatory Affairs Carl F. Patka, Assistant General Counsel
Brian R. Hodgdon, Attorney

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY  12144
Tel:  (518) 356-6000
Fax:  (518) 356-4702
rfernandez@nyiso.com
rstalter@nyiso.com

cpatka@nyiso.com
bhodgdon@nyiso.com

 

 

 

cc:   Michael BardeeJ. Arnold Quinn

Anna CochraneDouglas Roe

Kurt LongoKathleen Schnorf

Max MinznerJamie Simler

Daniel NowakGary Will Larry Parkinson


Ted J. Murphy

Hunton & Williams LLP
2200 Pennsylvania Avenue, NW Washington, D.C.  20037
Tel:  (202) 955-1500

Fax:  (202) 778-2201
tmurphy@hunton.com

 

Michael J. Messonnier, Jr. Hunton & Williams LLP 951 E. Byrd Street

Richmond, VA  23219
Tel:  (804) 788-8200
Fax:  (804) 344-7999

mmessonnier@hunton.com