Amanda C. Downey

Counsel

 

 

 

May 19, 2015

 

 

The Honorable Kimberly D. Bose Secretary

Federal Energy Regulatory Commission 888 First Street, N.E.

Washington, DC 20426

 

Re:Niagara Mohawk Power Corporation d/b/a National Grid

Docket No. ER15-___-000

Filing of Amended Interconnection Agreement with General Mills Operations Inc. and Request for Waiver of Commission Notice Requirement

Dear Secretary Bose:

 

Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and Part 35 of the
Federal Energy Regulatory Commission’s (“Commission”) regulations,2 Niagara
Mohawk Power Corporation d/b/a/ National Grid (“National Grid”) submits an amended
Interconnection Agreement (“Interconnection Agreement”) with General Mills
Operations, LLC (“General Mills”).3  The enclosed Interconnection Agreement amends
the original Interconnection Agreement already on file with the Commission to extend its
term, update outdated references, and make minor clarifying changes and corrections.
National Grid requests waiver of the Commission’s prior notice requirement to permit the
amended Interconnection Agreement to go into effect as of April 1, 2015.

 

I.Background

The Interconnection Agreement sets forth the terms under which National Grid

provides interconnection service to General Mills.  The Commission accepted the original

Interconnection Agreement effective as of October 5, 2004.4


 

 

 

 

 

1

 

 

2

 

 

3


 

 

16 U.S.C. § 824d.

18 C.F.R. Part 35.
This filing refers to National Grid and General Mills together as the parties to the Interconnection


Agreement.


 

4


Commission Letter Order, Docket No. ER05-57-000 (Dec. 13, 2004).  The original


Interconnection Agreement is designated as Service Agreement No. 337 under the Open Access Transmission Tariff of the New York Independent System Operator, Inc. (“NYISO”).

 

 

40 Sylvan Road, Waltham, MA 02451

T: 781-907-2136 F: 781-907-5701 amanda.downey@nationalgrid.com www.nationalgrid.com


 

 

The Honorable Kimberly Bose May 19, 2015

Page 2

II. The Amended Interconnection Agreement

The parties have amended the Interconnection Agreement to make it effective

April 1, 2015 and extend its term through September 30, 2017.5  They have also amended the Interconnection Agreement to update outdated references and make minor clarifying changes and corrections.6

 

III. Effective Date and Request for Waiver

The Recitals to the amended Interconnection Agreement specify an effective date of April 1, 2015.7  Accordingly, National Grid respectfully requests that the amended Interconnection Agreement be permitted to go into effect as of April 1, 2015, and that the Commission grant waiver of the notice provisions in its regulations that require the filing of service agreements no more than 30 days after service has commenced.8

Granting the requested effective date will permit the amended Interconnection

Agreement to become effective as of the date agreed upon by the parties and will not

result in prejudice to any party.  For these reasons, the Commission should find that good cause exists to grant an effective date of April 1.

IV.Documents Enclosed

In addition to this filing letter, attached are the following documents:

i.The amended Interconnection Agreement, provided in clean format

(Attachment A); and

ii. Black-lined revisions showing the amendments to the original

Interconnection Agreement (Attachment B).

 

V.Communications and Service

Communications regarding this filing should be addressed to the following

individuals, whose names should be entered on the official service list maintained by the

Secretary for this proceeding:


 

 

 

 

5


 

Amended Interconnection Agreement, Recitals and Section 11.1.  Although section 11.1 of the


original Interconnection Agreement states that it will continue in effect for ten years, the parties have


continued to follow the terms of the original Interconnection Agreement to the present day and have not


filed to terminate it.


 

 

6

 

7


These amendments are shown in the black-lined revisions contained in Attachment B to this filing. See also amended Interconnection Agreement, Section 11.1 (stating that the amended


Interconnection Agreement “shall become effective as of the EFFECTIVE DATE, subject to its approval or acceptance for filing by the FERC”).


8


Specifically, pursuant to of Section 35.11 of the Commission’s regulations (18 C.F.R. § 35.11),


National Grid requests waiver of Section 35.3 of the Commission’s regulations (18 C.F.R. § 35.3).


 

 

The Honorable Kimberly Bose May 19, 2015

Page 3


 

Amanda C. Downey
National Grid USA

Service Company, Inc.

40 Sylvan Road

Waltham, MA  02451 (781)907-2136

amanda.downey@nationalgrid.com

 

 

William L. Malee

Director, Transmission Commercial National Grid USA

40 Sylvan Road

Waltham, MA 02451 (781) 907-2422

bill.malee@nationalgrid.com


Sean A. Atkins

Bradley R. Miliauskas Alston & Bird LLP The Atlantic Building 950 F Street, NW

Washington, DC 20004 (202) 239-3300

sean.atkins@alston.com
bradley.miliauskas@alston.com


Copies of this filing have been served on General Mills and the NYISO.

 

 

VI.Conclusion

For the reasons stated herein, National Grid respectfully requests that the

Commission accept the amended Interconnection Agreement contained in this filing effective April 1, 2015.

Respectfully submitted,

 

 

/s/ Amanda C. Downey

Amanda C. Downey
Counsel

National Grid USA

Service Company, Inc.

40 Sylvan Road

Waltham, MA 02451

 

Attorney for Niagara Mohawk Power
Corporation d/b/a National Grid