10 Krey Boulevard Rensselaer, NY 12144
October 21, 2014
By Electronic Delivery
Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE
Washington, DC 20426
Re: New York Independent System Operator, Inc., Response to Request for
Additional Information Concerning Compliance Filing in Docket No. ER14-
2573-000
Dear Ms. Bose:
The New York Independent System Operator, Inc. (“NYISO”) respectfully submits this filing on behalf of the NYISO and the New York Transmission Owners (“NYTOs”)1 in response to the Federal Energy Regulatory Commission’s (“Commission’s”) October 6, 2014 request for additional information in this proceeding (“October 6 Request”). The Commission’s October 6 Request concerns a single issue related to the August 1, 2014 compliance filing submitted in this proceeding (“Compliance Filing”). Specifically, the October 6 Request concerns the NYISO and the NYTOs (together, the “Filing Parties”) request for an increase in the pre-application report fee to cover the Filing Parties’ costs for providing such information.
Order No. 792 established a default $300 fee for the preparation of the pre-application
report and provided all filing parties the opportunity to propose a different fixed cost-based fee
supported by a cost justification as part of their compliance filing. 2 Order No. 792 indicated that while the default fee would be $300, “it would be unjust and unreasonable for Transmission
Providers not to recover their actual pre-application report preparation costs.” 3 In response, the Filing Parties proposed in the Compliance Filing a fee of $1000 and described the cost
justification for the higher fee.
1 The NYTOs are Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New
York, Inc., Long Island Lighting Company d/b/a LIPA (“LIPA”), New York Power Authority (“NYPA”), New
York State Electric & Gas Corp. (“NYSEG”), Niagara Mohawk Power Corp. d/b/a National Grid, Rochester Gas & Electric Corp. (“National Grid”), and Orange & Rockland Utilities, Inc. The Filing Parties note that LIPA and
NYPA, as transmission owners not subject to the Commission’s jurisdiction under section 205 of the Federal Power Act, have voluntarily participated in the development of this filing.
2 Order No. 792 at P 46.
3 Id.
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 2
The NYISO respectfully submits herein additional cost justification for the requested
$1000 pre-application fee in response to the information requested in the Commission’s October
6 Request. In support of this written response, the NYISO submits the affidavit of Steven L. Corey, NYISO’s Manager of Interconnection Projects (Attachment I). Mr. Corey is the
individual who oversaw the NYISO’s efforts to determine the time and resources required to complete the pre-application report for a sample project, the selection and representative nature of which is discussed in more detail below.
The NYISO recognizes that this filing constitutes an amendment to the August 1, 2014
Compliance Filing and therefore triggers a new notice and comment period. The NYISO renews the Filing Parties’ request that the tariff revisions filed in this proceeding become effective upon issuance of a Commission Order accepting this filing and that until the Commission so acts, the NYISO’s existing Commission-approved interconnection procedures and pro forma Small
Generator Interconnection Agreement remain in effect.4 This requested effective date is
consistent with the effective date ultimately granted to the Filing Parties with respect to their Order Nos. 2006, 2006-A and 2006-B compliance filings.5 The NYISO further renews the
Filing Parties’ request that the Commission direct a subsequent compliance filing of the accepted tariff revisions to reflect the ordered effective date as requested above.6
I.RESPONSES TO THE OCTOBER 6 LETTER
A.Request One
“Filing Parties state that the three test projects they selected had already been studied by the Connecting Transmission Owner and/or the NYISO and took approximately four hours to
complete with “actual costs ranging from $660 to $750.” Filing Parties then determined that approximately 7 hours would be more likely the amount of time needed to collect such
information for projects not previously evaluated. Please explain why approximately seven
hours total (with a range of $962.50 to $1,155) is an appropriate estimate to complete a report for an unstudied project. In your explanation, please describe the steps taken to compile the preapplication information for each test project, consisting only of readily available information. Also, does NYISO expect to undertake similar steps for future projects?”
4 Compliance Filing at 11.
5 See New York Indep. Sys. Operator, Inc, 119 FERC ¶ 61,333, at P 13 (2007) (granting rehearing with
respect to the effective dates for the Joint Filing Parties’ Order Nos. 2006, 2006-A and 2006-B compliance filings, and granting the Joint Filing Parties’ request that the tariff sheets filed in the compliance filings become effective upon the date of Commission action.)
6 Compliance Filing at 11.
2
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 3
1.Response to Request One
a) Steps Taken to Compile Pre-Application Information for Test Projects
The Filing Parties agreed on a process for selecting projects that would be representative
of historical Small Generating Facility interconnection requests in terms of size and location on
the grid. The Filing Parties also agreed to perform “trial runs” for three selected test projects in
order to determine a good faith estimate of the steps and time required to compile readily
available information in response to a pre-application request. One “trial run” was conducted by
the NYISO, one by NYSEG and one by National Grid. To facilitate the administration of these
trial runs, the Filing Parties created a standard pre-application report request form (“Pre-
Application Request Form”) and a separate pre-application report form (“Pre-Application Report
Form”).
The NYISO administered the pre-application trial run for a 12.6 MW facility proposing
to interconnect at 115 kV.7 The Filing Parties selected NYISO to evaluate this project because
the test project was proposing to interconnect at a voltage level for which the NYISO was more
likely to possess most of the readily available information.8 To perform the trial run, a NYISO
staff member filled out the Pre-Application Request Form, pulling data from the Interconnection
Request initially provided for the proposed interconnection of the 12.6 MW Small Generating
Facility. 9 Beginning with the completed Pre-Application Request Form, a second NYISO Staff
member set about compiling the readily available data required to complete the Pre-Application
Report Form and proceeded to insert the readily available data in the form. 10
The second NYISO staff member compiled data for the greater than twenty data points in
the Pre-Application Report Form, drawing from assorted NYISO databases and materials -
including: (i) the information in the Pre-Application Request Form; (ii) the relevant Connecting
Transmission Owner’s one-line diagrams on file with the NYISO; (iii) the NYISO’s Annual
Transmission Baseline Assessment;11 and (iv) the NYISO’s Load and Capacity Data Report
(“Gold Book”).12,13 The second NYISO Staff member spent approximately four (4) hours
collecting data from these sources and filling out the Pre-Application Report Form. 14
7 See Corey Affidavit at P 9.
8 See Id.
9 See Id. at P 10.
10 See Id. at P 11.
11 The Annual Transmission Baseline Assessment is a study conducted by the NYISO in accordance with
the requirements set forth in Attachment S of the NYISO OATT that identifies the System Upgrade Facilities that
Transmission Owners are expected to need during the time period covered by the assessment to comply with
Applicable Reliability Requirements, and reliably meet the load growth and changes in load pattern projected for the
New York Control Area.
12 The Gold Book is an annual NYISO report that presents historic and forecast load information, along with information regarding existing and proposed transmission and generation data.
3
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 4
The NYTOs, specifically NYSEG and National Grid, performed the trial runs for the
other two test projects. The Filing Parties selected these particular NYTOs to participate in the
trial run exercise because National Grid and NYSEG are the NYTOs that are the Connecting
Transmission Owners for most Small Generating Facilities evaluated in the NYISO’s Small
Generator Interconnection Procedures.15 NYSEG performed the trial run for a 4.8 MW facility
proposing to interconnect to its distribution facilities (a project that submitted an Interconnection
Request to the NYISO but was ultimately determined not to be subject to Commission
jurisdiction or the NYISO’s Small Generator Interconnection Procedures). National Grid
performed the trial run for a 3.2 MW facility proposing to interconnect to its 34.5 kV
transmission system.
The NYTOs advised that for these trial runs, NYSEG and National Grid took steps
similar to those taken by the NYISO that are described below. The NYTOs further advised that unlike the NYISO’s trial run, the NYSEG and National Grid exercises were not conducted under the direct supervision of one individual, but involved coordination with individuals in various functional groups at their respective organizations.
National Grid reported that it reviewed a 3.2 MW methane facility proposing to
interconnect at 34.5 kV, which it believes to be typical of the type of facility that would request a
pre-application report and was the basis upon which the company developed its estimate.
National Grid advised that because it performs work through a matrix organization model, it was
necessary to involve different functional departments at National Grid in order to address the
questions in the pre-application report - specifically, Distribution Asset Management and
Transmission Commercial Services departments. National Grid further advised that the number
of departments needing to be involved in future projects will be dependent, in part, on the
proposed point of interconnection, and could include Distribution Asset Management, Retail
Connection Engineering, Transmission Planning, Meter and Test, as well as Transmission
Commercial Services. National Grid advised that in order to complete the pre-application trial
run, it was necessary to not only consult different functional departments, but it was also
necessary to consult a number of different applications to determine the company’s readily
available information - including, PSSE models, Transmission ARCGIS, pertinent engineering
design drawings (line and substation) for the location, and National Grid’s Energy Management
System. National Grid further advised that in reviewing the 3.2 MW test project, and using its
experience with similar work on small retail generators, it estimated the number of hours needed
to complete the Pre-Application Report Form to be approximately four (4) to five (5) hours.
NYSEG performed a trial run for another small facility, specifically - a 4.8 MW facility
proposing to interconnect to NYSEG’s distribution facilities. Unlike the other two test projects,
13 See Corey Affidavit at P 12.
14 See Id. at P 13.
15 See NYISO Interconnection Queue at the following link:
http://www.nyiso.com/public/markets_operations/services/planning/documents/index.jsp
4
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 5
this project submitted a Small Generator Interconnection Request to the NYISO but was
ultimately determined not to be subject to Commission jurisdiction or the NYISO’s Small
Generator Interconnection Procedures.16 While the other two test projects proposed to connect to transmission facilities subject to Commission jurisdiction, this project proposed to connect to distribution facilities not subject to the Commission’s jurisdiction.17 Despite these unique
characteristics, this trial run required approximately the same amount of time as the two test
projects discussed above.
Specifically, NYSEG advised that to complete the Pre-Application Report Form for this test project, it performed the following steps:
• Reviewed the summary of the proposed project to determine the Point of
Interconnection (“POI”);
• Identified the voltage level and specific substation or line to which the project
would connect;
• Identified the number and rating of any protective devices and voltage regulation
devices in between the proposed POI and the substation;
• Searched databases to identify any existing and queued projects planned to
interconnect at the facility serving the POI;
• Reviewed load flow information available via PSSE software to determine (1) the
available capacity and total capacity of the line at the POI; (2) peak and minimum
load at the substation at the POI; (3) any existing or known constraints; and (4)
the limited conductor rating from the proposed POI to the substation; and
• Compiled the information.
Consistent with the trial runs conducted by both NYISO and National Grid, NYSEG advised that the above steps required approximately four (4) hours.
b) Additional Steps Required for Future Projects
Notably, all three of the test projects discussed above had previously submitted
Interconnection Requests and had therefore already been studied by the Connecting
Transmission Owner and/or the NYISO prior to the trial run exercises.18 As a result, most of the
information had already been identified and collected and was therefore more “readily available”
to the NYISO and Connecting Transmission Owner. The NYISO anticipates that in addition to
the above steps required for future projects, additional work will be required for projects that,
16 See Corey Affidavit at P 8.
17 See Id.
18 Capitalized terms that are not otherwise defined herein have the meaning set forth in the NYISO’s Services Tariff, and if not defined therein, in the Open Access Transmission Tariff (“OATT”).
5
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 6
unlike the test projects, have not been previously studied by the NYISO or the Connecting Transmission Owner.
Because the test projects had previously been evaluated, both the proposed POI and the
appropriate Connecting Transmission Owner for each of these projects was already clearly
identified. In most cases, the POI is ill-defined when the potential Small Generating Facility
customer requests interconnection information or submits a formal Interconnection Request.19
Clearly identifying the POI is critical to determining: (1) whether the project is proposing to
connect to FERC-jurisdictional facilities; and (2) which Transmission Owner would be the
Connecting Transmission Owner.20 For future projects, the NYISO anticipates that it and/or the
applicable Connecting Transmission Owner will spend at least three additional hours (for a total
of approximately seven (7) hours) to complete a pre-application report based on the following
specific tasks which must be performed before the form can even be routed to the respective
Transmission Owner:
• Work with the customer and the applicable Connecting Transmission Owner(s) to
clarify the point on the transmission system to which the facility proposes to
interconnect;
• Consult available resources to determine the transmission district in which the POI is
located (requiring the NYISO to examine the Transmission Owner service territory
maps, which may not identify the POI at certain low voltage levels, and may therefore
require consultation with one or more Transmission Owners);
• Work with the customer and Connecting Transmission Owner to determine whether
the proposed interconnection is FERC jurisdictional and subject to the NYISO’s
Small Generator Interconnection Procedures.21,22
The above estimate of time required to complete pre-application reports for future,
unstudied projects is quite conservative.23 The estimate does not take into account the following administrative tasks, which would also have to be completed in response to a formal pre-
application request - steps that were not taken for the test projects:
• Reviewing the Pre-Application Request Form for completeness and working with the
customer to complete any missing or incomplete information;
19 See Corey Affidavit at P 15.
20 See Id.
21 This determination requires (1) clarification from the customer regarding the manner in which they
intend to sell their output - via wholesale sales, via net metering or under a self-supply arrangement; and (2)
consultation with the Transmission Owner to determine whether the connection point is transmission or distribution and, if distribution, whether it is FERC-jurisdictional distribution
22 See Corey Affidavit at P 14.
23 See Corey Affidavit at P 15.
6
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 7
• Logging the request, routing it to the appropriate Transmission Owner and tracking
its completion;
• Reviewing information provided by the Transmission Owner for completeness; and
• Compiling the information into a formal Pre-Application Report Form and providing
it to the customer.
Based on the foregoing, the NYISO estimates that in addition to the approximately four
(4) hours that will be required for the “data pull” of readily available information that was
expended on the test projects, at least three (3) hours will be required before the data pull can
begin to determine the specific POI and the respective Connecting Transmission Owner and still
additional time will be required to administer the process.24 The total time required may be well
in excess of seven (7) hours total; however, the Filing Parties believe that this is a reasonable
estimate. Multiplying the estimated seven (7) hours by the blended rates of the interconnection
personnel expected to respond to these requests, the Filing Parties arrived at an estimate between
$962.50 and $1,155. Accordingly, the Filing Parties requested a $1000 pre-application report fee
and the NYISO respectfully renews their request that the Commission approves such fee.
B.Request Two
“Please provide a detailed explanation of how the three sample projects Filing Parties chosen for cost justification purposes are representative of future projects for which Filing Parties will complete pre-application reports.”
1.Response to Request Two
The pre-application report requirement will apply to varying types of projects.
Accordingly, the Filing Parties collectively reviewed the NYISO’s historical interconnection queue to see what types of Small Generating Facilities had requested interconnection and the related voltage levels. The Filing Parties selected projects for their trial runs discussed above that had requested to interconnect at different locations on the grid and at different voltage levels.25 The Filing Parties believed this selection to be representative of the diverse types of requests previously received and studied.
The Filing Parties selected three diverse projects:
• a 12.6 MW wind facility proposing to interconnect at 115kV;
• a 4.8 MW landfill gas facility proposing to interconnect to distribution facilities
ultimately determined not to be FERC-jurisdictional; and
24 See Id. at P 14-15.
25 See Id. at P 8.
7
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 8
• a 3.2 MW methane facility proposing to interconnect at 34.5kV.26
The Filing Parties selected a diverse group of test projects in order to determine whether
it would take more or less time to compile information for different types of projects. Despite
the wide-ranging voltage levels at which the three projects were connecting and the different
facility sizes and transmission districts, the time required to complete the Pre-Application
Reports for these previously reviewed projects was between four and five hours. Based on this
review, the NYISO respectfully submits that the size and characteristics of the projects are not
the determining factors. It took approximately the same time and effort to pull the data for each
of these three very diverse projects. The NYISO therefore believes it is reasonable to consider
the test projects representative with respect to the time it took to perform the steps taken for each,
detailed above.
As explained above, however, for future projects, the NYISO estimates that additional time will be required before the data pull can begin to determine critical information such as the specific POI and the respective Connecting Transmission Owner, and to administer the preapplication process. For all the foregoing reasons, the NYISO submits that the requested $1000 fee is therefore a reasonable and conservative estimate.
II. COMPLIANCE WITH ELECTRONIC TARIFF REQUIREMENTS
The October 6 Letter directed the Filing Parties to make an amendment filing in
accordance with the Commission’s electronic tariff requirements27 which requires the submittal
of at least one tariff record, even if no tariff changes are otherwise required. Accordingly, the
NYISO encloses the same clean and redlined revisions to the NYISO’s OATT as it filed in the
original August 1, 2014 Compliance Filing. Attachment II to this response is a clean version of
the OATT revisions submitted in compliance with Order No. 792 (unchanged from the August 1,
2014 Compliance Filing) and Attachment III is a redline showing the same proposed changes
presented in the August 1 Compliance Filing, and described there.28
III.DOCUMENTS SUBMITTED
• This filing letter;
• Affidavit of Steven L. Corey (Attachment I);
• A clean version of the proposed revisions to the NYISO’s OATT
(Attachment II); and
26 See Id.
27 October 6 Letter at 3 (citing Electronic Tariff Filings, 130 FERC ¶ 61,047 (2010)).
28 See August 1, 2014 Compliance Filing.
8
Honorable Kimberly D. Bose, Secretary October 21, 2014
Page 9
• A blacklined version of the proposed revisions to the NYISO’s OATT
(“Attachment III”).
IV.SERVICE
This filing will be posted on the NYISO’s website at www.nyiso.com. In addition, the
NYISO will e-mail an electronic copy or an electronic link to this filing to the official
representative of each party to this proceeding, to each of its customers, to each participant on its stakeholder committees, to the New York Public Service Commission, and to the New Jersey
Board of Public Utilities.
V.CONCLUSION
For the reasons specified in the August 1, 2014 Compliance Filing, and above, the NYISO respectfully renew the Filing Parties’ request that the Commission accept the tariff revisions submitted in this proceeding in compliance with Order No. 792.
Respectfully submitted,
/s/ Sara B. Keegan
Sara B. Keegan
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
skeegan@nyiso.com
Counsel for the New York Independent System Operator, Inc.