September 4, 2013

 

 

By Electronic Delivery

Kimberly D. Bose, Secretary

Federal Energy Regulatory Commission 888 First Street N.E.

Washington, D.C. 20426

 

Re:  Update to Informational Filing and Request to Defer Action Regarding TC
Ravenswood, LLC’s Black Start Service Rate Schedule;

Docket No. ER12-1418-000

Dear Ms. Bose:

In a May 24, 2012, order in the above-captioned proceeding, the Federal Energy

Regulatory Commission (“Commission”) accepted TC Ravenswood, LLC’s (“Ravenswood’s”) proposed stand-alone rate schedule to provide black start service in New York City
(“Ravenswood Rate Schedule”), subject to refunds and further order, and established
settlement procedures, which terminated on December 21, 2012.

 

The New York Independent System Operator, Inc. (“NYISO”) is procuring black start service on an interim basis as the sole customer under the Ravenswood Rate Schedule because Ravenswood’s steam turbine units play a significant role in the effectiveness and robustness of Consolidated Edison Company of New York, Inc.’s (“Consolidated Edison’s”) local plan for restoring electric service to New York City.

 

On March 8, 2013, the NYISO submitted an informational report indicating to the

Commission that, notwithstanding the termination of Commission-sponsored settlement

proceedings regarding the Ravenswood Rate Schedule, the parties continued to have

productive discussions on open issues regarding the rate schedule.  The NYISO, therefore,

believed that further action by the Commission was unnecessary at that time, respectfully

requested that the Commission defer taking further action in the proceeding, and indicated that

 

 

 

 

 

 

ATLANTA   AUSTIN   BANGKOK   BEIJING   BRUSSELS   CHARLOTTE   DALLAS   HOUSTON   LONDON   LOS ANGELES
McLEAN   MIAMI   NEW YORK   NORFOLK   RALEIGH   RICHMOND   SAN FRANCISCO   WASHINGTON

www.hunton.com


 

 

 

Kimberly D. Bose, Secretary September 4, 2013

Page 2

 

it would report back to the Commission within 180 days to describe the status of issues regarding the Ravenswood Rate Schedule.1

 

In accordance with its March 8 informational filing, the NYISO submits this update.
The NYISO continues to procure black start service under the Ravenswood Rate Schedule to
ensure the robustness and effectiveness of Consolidated Edison’s local black start plan.2  In
addition, the NYISO has continued to communicate with Ravenswood and with Consolidated
Edison regarding Ravenswood’s provision of black start service.  Since the last informational
report, Ravenswood has successfully conducted black start tests of its steam turbine units under
testing requirements comparable to the testing requirements set forth in the NYISO tariffs.

The NYISO believes that further action by the Commission is unnecessary at this time
and respectfully requests that the Commission continue to defer taking further action in this
proceeding.  The NYISO will continue to keep the Commission apprised of any material
change in the status of issues regarding the Ravenswood Rate Schedule.  Ravenswood and Con
Edison have authorized the NYISO to represent that they support the NYISO’s request.

 

 

Sincerely,

 

/s/ Kevin W. Jones
Kevin W. Jones

Michael J. Messonnier, Jr. Counsel for

New York Independent System Operator, Inc.

 

 

 

 

 

 

 

 

 

1 Ravenswood made a similar request for the Commission to defer action at that time.  See Informational Filing and Request to Defer Action Regarding TC Ravenswood, LLC’s Spot Black Start Service Rate Schedule, FERC Docket No. ER12-1418-000 (March 7, 2013).

 

2  The NYISO is procuring black start service under the Ravenswood Rate Schedule to ensure near-term

reliability.  The NYISO’s procurement of this service does not represent or constitute an acceptance of the

lawfulness of the Ravenswood Rate Schedule.  The NYISO has reiterated its objections to the Ravenswood Rate Schedule in its June 25, 2012, request for rehearing in the above-captioned proceeding.