10 Krey Boulevard   Rensselaer, NY  12144

 

 

 

 

 

June 28, 2013

 

 

Via Overnight Delivery

Hon. Kimberly D. Bose Secretary

Federal Energy Regulatory Commission 888 First Street, N.E.

Washington, D.C. 20426

 

Re:    New York Independent System Operator, Inc.’s Informational Filing in Docket
No. ER12-2568-000

 

Dear Ms. Bose:

This filing is submitted to the Commission on behalf of the New York Independent
System Operator (“NYISO”) in the above docket for informational purposes only.  No action
is requested.

I.   Background

On October 31, 2012, the Federal Energy Regulatory Commission (“FERC” or

“Commission”) issued an Order Accepting Proposed Tariff Revisions Subject to Conditions (“October Order”) that conditionally accepted a filing made by the NYISO on August 31,
2012 (“August Filing”) that substantially revised section 15.5 (Rate Schedule 5) of NYISO’s Services Tariff, as well as sections 6.6 and 30.2 of its Open Access Transmission Tariff.
Those changes revised numerous aspects of the program under which Consolidated Edison Company of New York, Inc. (“Con Edison”) provides System Restoration and Black Start
Services to the New York City Area.

The NYISO submitted its compliance filing on November 30, 2012 making minor changes to the process by which a unit obtains a unit-specific rate as well as adding an
obligation for the NYISO to submit to the Commission a copy of the Con Edison System Restoration Plan (“Con Edison Plan”) within 30-days of receipt.  The Commission issued an order on January 8, 2013 accepting NYISO’s compliance filing.

In the instant filing, NYISO is submitting to the Commission, for informational

purposes, a copy of the Con Edison Plan, titled “Start-Up Procedure for Rapid Energization of
the Con Edison Electrical System after Complete System Shutdown” dated June 2013.  The
NYISO submitted the version of the Con Edison Plan dated June 2012 to the Commission on


 

 

Kimberly D. Bose, Secretary June 28, 2013

Page 2

 

April 5, 2013.  NYISO is requesting non-public and Critical Energy Infrastructure

Information (“CEII”) designation for this document for the reasons outlined below.  The

NYISO received an updated Restoration Plan from Con Edison on June 6, 2013.  NYISO will continue to submit updated copies to the Commission in a similar manner as outlined in
section 15.5.4 of its Services Tariff.

II. CEII Designation/ Request for Exemption from FOIA

The information that the NYISO is providing includes CEII.  In accordance with 18 C.F.R. § 388.107, 18 C.F.R. § 388.112 and 18 C.F.R. 388.113 the NYISO hereby requests CEII designation and an exemption from disclosure under FOIA (5 U.S.C. 552) for the
enclosed document “Start-Up Procedure for Rapid Energization of the Con Edison Electrical System After a Complete System Shutdown.”

Critical Energy Infrastructure Information Designation

The NYISO respectfully requests the information submitted herewith be treated as non-public and exempt from disclosure pursuant to 18 C.F.R. § 388.107 and 18 C.F.R. §388.113.  The information that the NYISO is providing to the Commission includes CEII. As defined by 18 C.F.R. § 388.113, CEII is “specific engineering, vulnerability, or detailed design information about proposed or existing critical infrastructure that:

 

(i) Relates details about the production, generation, transportation, transmission, or distribution of energy;

(ii) Could be useful to a person in planning an attack on critical infrastructure;

 

(iii) Is exempt from mandatory disclosure under the Freedom of Information Act [“FOIA”], 5 U.S.C. 552; and

(iv) Does not simply give the general location of the critical infrastructure.”

 

The Con Edison Plan meets the definition of CEII set forth in 18 C.F.R. § 388.113
because (i) it identifies and provides connectivity information about the generators and bulk power transmission substations that are critical for the operation of the bulk power system in the New York City Area and Westchester County;  (ii) such information, if disclosed, could be useful to a person planning an attack on the New York State power system; (iii) it is
exempted from mandatory disclosure under FOIA (see discussion of FOIA exemptions 5
U.S.C. § 552(b)(3) and 5 U.S.C. § 552(b)(7)(F) below); and (iv) it provides more than simply the general location of critical infrastructure.


 

 

Kimberly D. Bose, Secretary June 28, 2013

Page 3

 

Request for Exemption from FOIA Disclosure

The Con Edison Plan is exempt from the public disclosure requirements under FOIA pursuant to 5 U.S.C. § 552(b)(3) and §552 (b)(7)(F) for the reasons set forth below.

First, 5 U.S.C. § 552(b)(3) protects documents and data from disclosure under FOIA if
the documents or data are specifically exempted from disclosure by statute.  Here, the Con
Edison Plan is specifically exempted from disclosure by statute - specifically, 18 C.F.R. §
388.113.  As evidenced above, the Con Edison Plan satisfies the definition of CEII in 18
C.F.R. § 388.113.  It is therefore exempt from disclosure under 5 U.S.C. § 552(b)(3).

 

Second, 5 U.S.C. § 552(b)(7)(F) specifically exempts from disclosure under FOIA
records or information that “could reasonably be expected to endanger the life or physical
safety of any individual.”  In the NYISO’s assessment, the disclosure of the Con Edison Plan
could pose a threat to the reliability of the New York State Electric System and to the health
and safety of New York residents supplied from the electric system.  Specifically, the Con
Edison Plan reveals the detailed plans on how to restore the electric system in the New York
City Area following an area wide power outage.  The Con Edison Plan identifies the key

generation and transmission facilities of the bulk power system and provides details of the
specific actions Con Edison will take to reenergize the system during a blackout event. It
contains detailed system diagrams and equipment information.  This information could be
used to thwart efforts to restore power to the New York City Area.  Of even greater
consequence, the information provides an intelligent adversary with a virtual blueprint of the
New York City Area power grid, highlighting the very facilities to target when attempting to
shut down the system and cause devastating damage from which recovery would be
indefinite.  The Con Edison Plan therefore contains CEII.  FERC has determined that CEII is
exempt from mandatory disclosure under this subsection of FOIA.1  For these reasons, the
Con Edison Plan is exempt from mandatory disclosure under 5 U.S.C. § 552(b)(7)(F).

 

The NYISO respectfully requests that, in the event the Commission receives a FOIA
request pertaining to the NYISO’s submittal, the Commission protect the confidentiality of
the information identified above by applying the applicable FOIA exemption (or other
applicable confidentiality provisions) to exempt the Con Edison Plan from disclosure.

 

Before the Commission determines that it is necessary or appropriate to make public any information submitted herewith (whether submitted pursuant to a claim of exemption from FOIA disclosure, or otherwise), the NYISO respectfully requests that it be given prior notice and an opportunity to comment on, or object to, the public disclosure of the
information it has submitted.

 

 

 

1 See, e.g In re Hala Ballouz, No. CE07-121-000, 119 F.E.R.C. P62,204, 2007 FERC LEXIS 1058 (June 8,

2007); In re Baumgardner, No. CE08-18-000, 122 F.E.R.C. P62,068, 2008 FERC LEXIS 158 (Jan. 25, 2008); In re Kritikson, No. CE08-26-000, 122 F.E.R.C. P62,020, 2008 FERC LEXIS 33 (Jan. 11, 2008).


 

 

Kimberly D. Bose, Secretary June 28, 2013

Page 4

 

Please feel free to contact me at the number or email address below with any questions
regarding the enclosed document or NYISO’s requests for exemption from public disclosure.

 

Respectfully submitted,

/s/  Kristin A. Bluvas

Kristin A. Bluvas, Attorney

New York Independent System Operator, Inc.

 

cc. Martin F. Heslin, Assistant General Counsel, Consolidated Edison Company, Inc.


 

 

 

 

 

CERTIFICATE OF SERVICE

I hereby certify that upon posting in eLibrary of the foregoing document, I will serve said document upon each person designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. § 385.2010.

Dated at Rensselaer, NY this 28th day of June, 2013.

 

 

 

By:/s/ John C. Cutting

John C. Cutting

Senior Regulatory Affairs Specialist

New York Independent System Operator, Inc.

10 Krey Blvd.

Rensselaer, NY 12144 (518) 356-7521