Independent Power Producers)
of New York, Inc.,)
)
Complainant,)
)
v.)
)
New York Independent System Operator, Inc.)
)
Respondent.)
ANSWER OF THE
Docket No. EL13-62-000
NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.
Pursuant to Rule 213 of the Commission’s Rules of Practice and Procedure,1 the New
York Independent System Operator, Inc. (“NYISO”) respectfully submits this answer to the
Complaint Requesting Fast Track Processing of the Independent Power Producers of New York, Inc. (“Complaint”). The arguments advanced by the Independent Power Producers of New
York, Inc. (“IPPNY”) are wholly without merit. IPPNY has failed to satisfy its burden of proof under the Federal Power Act (“FPA”) and there is no basis for revising the NYISO’s Market
Administration and Control Area Services Tariff (“Services Tariff”).2 Accordingly, the
Complaint, including both of its alternative proposals to revise the Services Tariff and each of its other requests for relief, should be denied.
As discussed in Section II.A of this answer and in the affidavit of Dr. David B. Patton
(“Patton Affidavit”) (Attachment 1), the Complaint is predicated on fundamental flaws that
1 18 C.F.R. § 385.213 (2013).
2 Terms with initial capitalization that are not otherwise defined herein have the meaning set forth in the Services Tariff.
completely invalidate its arguments. These include IPPNY’s: (i) flawed economic assertions that
the Cayuga Operating Company, LLC (“Cayuga”) and Dunkirk Power, LLC (“Dunkirk”)
generating facilities are not economic; (ii) flawed notion of what constitutes a competitive
capacity market; (iii) flawed understanding that the Cayuga and Dunkirk units should not be
permitted to clear in the capacity market; and (iv) flawed assumption that a competitive offer
should include Going Forward Costs (“GFCs”) but exclude revenues from competitive
Reliability Services Support Agreements (“RSSAs”).3 Dr. Patton explains that it is reasonable
for the Cayuga RSSA, and to the extent that they include such a provision, the Dunkirk RSSAs,4
to require that generating facilities offer their “capacity value into the NYISO UCAP Auction at
a de minimis price in compliance with NYISO market rules” (“Cayuga RSSA Bidding
Requirement”).5
The Patton Affidavit further establishes that the only circumstances in which RSSAs
would raise competitive concerns would be: (i) when there is no legitimate need for a resource;
or (ii) the need addressed by an RSSA is already fully captured by capacity market requirements.
There is no dispute in this proceeding that the Existing RSSAs were entered into in order to
3 See Section II.A, below.
4 Under the first Dunkirk RSSA, Dunkirk agreed to provide reliability support services from two units rated at 100 MW each to National Grid from September 1, 2012 through May 31, 2013. Under the second Dunkirk RSSA, Dunkirk will provide service from one 100 MW unit from June 1, 2013 through May 31, 2015. See Complaint at 13-14. Solely for ease of reference, when this answer refers to the
Cayuga RSSA and to the “first” and “second” Dunkirk RSSAs collectively it refers to them as the
“Existing RSSAs.” The NYISO’s use of this drafting convention is not intended to indicate, and should not be construed as indicating, that the Dunkirk RSSAs contain bidding requirements comparable to the Cayuga RSSAs. As the Complaint notes, the portions of the Dunkirk RSSAs where bidding requirements would be located are confidential. See Complaint at 14.
5 The Complaint assumes, but IPPNY acknowledges that it does not know and has simply
inferred, that the Dunkirk RSSAs include a capacity bidding requirement that is identical or very similar to the one in the Cayuga RSSA. See Complaint at 13-14.
2
address legitimate reliability needs.6 Dr. Patton also explains that the reliability needs addressed
by the Existing RSSAs are not otherwise captured by NYISO capacity market requirements.7
The Patton Affidavit supports the NYISO’s position that “there has been, and currently is, no exercise of buyer-side market power or ‘artificial price suppression’ in the NYCA capacity market related to the ‘uneconomic retention’ of existing resources.”8 It also agrees with the
NYISO that “there is no reason for the Commission to require revisions to the Market
Administration and Control Area Services Tariff and that the Complaint should be rejected.”9
The Complaint’s remaining concerns about possible future threats to the NYISO capacity markets are unsubstantiated and it would be premature for the Commission to address them now. For example, the Complaint suggests that the Services Tariff must be revised to protect the
markets against additional RSSAs that may be executed in the future.10 Even if there are “Future
RSSAs” they would only be harmful if they fell into one of the two categories that Dr. Patton has
explained would raise competitive concerns. The Complaint briefly mentions various pending
New York State initiatives and proposed legislation that IPPNY asserts might someday threaten
the NYISO capacity markets. Cursory and unsupported statements regarding problems that
might arise in the future fall short of what is required to satisfy a complainant’s burden of proof.
6 See Patton Affidavit at P 12; Section I.C below. The NYISO uses the term “reliability need” in this answer in the same general way that the Patton Affidavit uses it and the Complaint uses the “system condition.” References herein to “reliability needs” should not be construed as necessarily referring to “Reliability Needs” as defined in the NYISO’s Open Access Transmission Tariff.
7 See Patton Affidavit at P 20.
8 Id. at P 15.
9 Id.
10 See Complaint at 33-38 and Attachment B - Affidavit of Mark D. Younger (“Younger Affidavit”) at P 29.
3
The NYISO and the independent Market Monitoring Unit (“MMU”)11 have the authority to
address any genuine market power issues that may arise. Further, there is no basis to presume
that the NYISO would not act to address future threats to the market as (and if) they appear.
Finally, although IPPNY is not legally barred from filing the Complaint, neither it nor its members (with one very limited exception,)12 made an effort to first address their concerns
through the NYISO stakeholder process. IPPNY’s approach is contrary to Commission policy
and precedent.13 This is especially true in this proceeding because IPPNY was aware of the core issues addressed by the Complaint for at least nine months14 and is now attempting to
unilaterally impose its own preferred tariff revisions on the NYISO-administered markets and
other stakeholders. IPPNY had ample time and opportunity to raise these issues in the NYISO
stakeholder process but never did.15 The Commission should take this opportunity to remind
IPPNY and its members that it strongly discourages such “end-runs” and will treat them with
disfavor. It should also encourage IPPNY to bring any remaining concerns about Future RSSAs, or other potential future issues, to the stakeholder process.
11 The independent MMU is Potomac Economics, Ltd. Dr. Patton is the President of Potomac Economics.
12 A single IPPNY member, TC Ravenswood, LLC (“TCR”) raised “uneconomic retention,”
including current and future RSSAs, as part of a proposal to revise the Services Tariff at one ICAP
Working Group Meeting (on April 30, 2013). When TCR next presented its proposal in the stakeholder process, it removed the aspects related to “uneconomic retention.” These very limited efforts by TCR do not excuse IPPNY’s clear and admitted failure to attempt stakeholder resolution of its issues, before
submitting its proposed tariff modifications in this Complaint.
13 See Section II.B, below.
14 See Complaint at 13 (noting August 16, 2012, New York Public Service Commission order approving the “Dunkirk Term Sheet” and stating that “the parties should have expected and we would expect that the capacity associated with Dunkirk Units 1 and 2 will be bid into the capacity market at a correspondingly de minimis price.”).
15 IPPNY is an active participant in the NYISO shared governance process as a guest, and IPPNY’s Managing Director is the Chair of the ICAP Working Group.
4
I.BACKGROUND
A.The NYISO and the Independent Market Monitoring Unit Strongly Support
Buyer-Side Market Power Measures When and Where they Are Needed
The NYISO recognizes the importance of having effective “supplier-side” and “buyer-
side” market power mitigation measures, when and where appropriate, to mitigate the potential
exercise of market power. When such measures are in place, the NYISO applies them
impartially and with equal diligence.16 New York has had buyer-side mitigation measures since
2008 to prevent “uneconomic entry” from artificially suppressing prices in New York City. The
MMU was a principal advocate for such measures both in New York and elsewhere.17 The
NYISO has proposed that the existing framework of buyer-side mitigation measures that
currently applies only to New York City (Load Zone J) be adapted for use in New Capacity
Zones,18 including the new “G-J” Locality that it has proposed to establish in pending Docket
No. ER13-1380-000.19 In short, the NYISO and the MMU both have a record of supporting the
creation of effective buyer-side mitigation rules that are appropriate and necessary.
That does not mean, however, that the NYISO, or the MMU, must necessarily support all proposals to extend buyer-side market power mitigation to encompass new forms of conduct. Both entities must determine whether a claimed incident of “artificial price suppression” really represents the exercise of buyer-side market power. They must also consider that over-
16 The NYISO recognizes that IPPNY’s members have disagreed with a number of the
implementation decisions that it has made under the uneconomic entry mitigation rules for New York City but notes that IPPNY strongly defended the NYISO’s application of them in Docket No. EL12-98-
000. See Motion to Intervene and Protest of Independent Power Producers of New York, Inc., Docket No. EL12-98-000 (filed Nov. 13, 2012).
17 See, e.g., Patton Affidavit at P 8.
18 See New York Independent System Operator, Inc., Further Compliance Filing, Docket No. EL12-360-001 (filed June 29, 2012).
19 See Proposed Tariff Revisions to Establish and Recognize a New Capacity Zone and Request for Action on Pending Compliance Filing, Docket No. ER13-1380-000 (filed April 30, 2013).
5
mitigation can do as much to impede necessary investments in new and existing capacity resources as under-mitigation.20
B. The NYISO and the Independent MMU Have Consistently Agreed that
“Uneconomic Retention” Is Not Causing Artificial Price Suppression in the NYISO Capacity Markets
In this proceeding, and in pending Docket No. ER13-405 (the “Cayuga RSSA
Proceeding”), IPPNY has advanced a novel but fundamentally flawed hypothesis that it
extrapolated from the Commission’s uneconomic entry precedent. According to IPPNY,
“uneconomic retention” is necessarily the economic equivalent of uneconomic entry.21 IPPNY also asserts that the Cayuga RSSA Bidding Requirement, and any similar requirement that may exist in the Dunkirk RSSAs, effectuate the exercise of buyer-side market power and thus are causing artificial price suppression in the NYCA Capacity markets.22
The NYISO is not aware of the Commission ever having approved a proposal to extend
the reasoning underlying its uneconomic entry precedent to encompass “uneconomic retention”
of existing resources and IPPNY does not point to any such rulings. IPPNY notes that the
Commission’s May 2010 Order23 indicated that buyer-side mitigation of existing resources
might conceivably be needed in the future. The May 2010 Order rejected a request for rehearing
20 See, e.g., New York Independent System Operator, Inc., 136 FERC ¶ 61,077 at P 28 (2011)
(“The whole purpose of the NYC mitigation program is to deter uneconomic entry, not economic entry”);
Midwest Independent Transmission System Operator, Inc., 122 FERC ¶ 61,172 at P 121 (accepting a
proposal that “both protects consumers from market power, while also avoiding over-mitigation that can
cause reliability problems to the extent that it keeps capacity out of the market over the longer term”);
Midwest Independent Transmission System Operator, Inc., 123 FERC ¶ 61,297 at P 63 (2008) (finding
that the conduct threshold proposed “strikes an appropriate balance between the need to protect
consumers from the exercise of market power and the goal of avoiding over-mitigation that may keep
capacity out of the market”).
21 See Complaint at 20-21; Younger Affidavit at 3, 27, 70-71, 77-83.
22 Complaint at 38.
23 See Complaint at 4; see also New York Independent System Operator, Inc., 131 FERC ¶ 61,170 (2010) (“May 2010 Order”).
6
that called for existing resources to be subject to buyer-side mitigation. The Commission stated
that:
We reject Ravenswood’s claim that a change in contractual or financial
arrangements pertaining to an existing generation facility should transform that
facility into a unit subject to new entry mitigation rules. As we concluded earlier,
new entry mitigation is intended to deter the construction of uneconomic capacity
and such deterrence would not apply in this case. We understand that
Ravenswood remains concerned that entities with buyer market power may have
an incentive to suppress market clearing prices below the competitive level by
retaining uneconomic capacity that should be mothballed or retired, and that they
might attempt to exercise this market power through contractual means, i.e., that
new uneconomic entry is not the only mechanism available for generators to
exercise such market power. However, we find the possibility for such action too
speculative at this point to require an immediate remedy. We conclude that the
evidence to date supports only the offer floor mitigation for uneconomic new
entry by generators and SCRs (see discussion below) that this order addresses.
Ravenswood’s concerns should be addressed in the annual report prepared by
the independent market monitor to the extent the monitor finds evidence to
support their concerns.24
The MMU, however, has never found evidence that would justify adopting rules to
mitigate the “uneconomic retention” of existing resources either before or after the issuance of the May 2010 Order. None of its annual State of the Market Reports identify any possible need for tariff changes or make any other recommendations related to “uneconomic retention.” This includes the recent 2012 State of the Market Report25 which was issued well after IPPNY first expressed concerns about the RSSAs.26
As noted in the Patton Affidavit, the MMU has been aware of the Existing RSSAs, and IPPNY’s claims regarding them since it was first determined that they were needed for
24 See May 2010 Order at P 43 (emphasis added).
25 See 2012 State of the Market Report for the New York ISO Markets (April 2013) available at
<http://www.nyiso.com/public/webdocs/markets_operations/documents/Studies_and_Reports/Reports/M
arket_Monitoring_Unit_Reports/2012/NYISO2012StateofMarketReport.pdf>.
26 See Section I.D below.
7
reliability.27 The MMU has consistently advised the NYISO that those claims are fundamentally flawed and that the Cayuga RSSA Bidding Requirement, and any other comparable requirement that may exist in the Dunkirk RSSAs, are efficient given the identified need not addressed by the market.28 The MMU has never suggested that the NYISO should take any action to “remedy” IPPNY’s concerns or recommended Services Tariff revisions. The MMU’s reasoning is set forth in the Patton Affidavit and in Section II.A of this answer.
The NYISO has previously noted that it was “not a party to, and was not involved in the development of ” the Cayuga RSSA.29 It likewise was not a party to or involved in the
development of the Dunkirk RSSAs. Nevertheless, the NYISO has monitored the Commission’s proceedings involving the Existing RSSAs and their impacts on its markets. The NYISO’s
Market Mitigation and Analysis department has consistently agreed with the MMU’s
conclusions and recommendations regarding the Existing RSSAs.
C.There Is No Question that the Existing RSSAs Address Legitimate Reliability
Needs
The Complaint notes that the Dunkirk RSSAs were executed because the local New York
Transmission Owner, i.e., Niagara Mohawk Power Corporation d/b/a National Grid (“National
Grid”) “conducted an analysis that found that the loss of Units 1 and 2 of the Dunkirk Facility
would have adverse reliability impacts.”30 Similarly, it observes that the Cayuga RSSA was
instituted because the relevant local New York Transmission Owner, i.e., New York State
Electric & Gas Corporation (“NYSEG”), “found that the Cayuga Facility would need to address
27 See Patton Affidavit at P 9.
28 Id. at PP 9, 39.
29 See Limited Comments of the New York Independent System Operator, Inc., Docket No. ER13-
405-000 (filed Jan. 22, 2013).
30 Complaint at 11.
8
an identified system condition.”31 IPPNY has “acknowledged the need to address identified system conditions” and made it clear that its objection to the RSSAs has to do solely with its theory that the RSSAs’ bidding requirements are resulting in artificial price suppression in the NYCA capacity market.32
D. IPPNY Had Ample Time and Opportunity to Raise the Issues Addressed in
the Complaint Through the NYISO’s Shared Governance Process
As the NYISO noted in its Initial Answer Opposing Fast-Track Processing in this
proceeding, the purported market harm alleged by IPPNY (i.e., the supposed “artificial
suppression” of NYCA capacity prices) supposedly began with the February 2013 ICAP Spot
Market Auction.33 The results of that auction were posted in January 2013.
IPPNY has been aware of the Dunkirk and Cayuga RSSAs, which the Complaint cites as the cause of the alleged “artificial suppression” of prices,34 since at least August 2012. As the Patton Affidavit demonstrates, and as discussed below, IPPNY’s arguments concerning the
Existing RSSAs have no economic underpinning. Despite IPPNY’s dire warnings of the adverse
consequences that the Existing RSSAs will supposedly bring, it has inexplicably failed to address
the root of its concerns, i.e., the content of certain contract terms approved in the New York
31 Id. at 15.
32 Id. at 17 (citing Protest of Independent Power Producers of New York, Inc., Docket No. ER13-
405-000 (filed Jan. 7, 2013); Request for Expedited Order Prohibiting Implementation of an Unapproved Contract for Reliability Must Run Service Subject to FERC Jurisdiction and Limited Answer of
Independent Power Producers of New York, to Comments of the New York Independent System Operator, Inc., Docket No. ER13-405-000 (filed Jan. 25, 2013). See also Complaint at 27 (“That the Cayuga and Dunkirk Facilities are needed to address an identified system condition does not alter the fact that they are uneconomic ”). See also Younger Affidavit at PP 34-36 (acknowledging that the Existing RSSAs
were executed in response to “system conditions”).
33 See Initial Answer of the New York Independent System Operator, Inc. Opposing Fast Track Processing, Docket No. EL13-62-000 at 4 (filed May 13, 2013); See also Complaint at 21.
34 Complaint at 41-42; see also Younger Affidavit at P 27.
9
Public Service Commission (“NYPSC”) proceeding. In fact, IPPNY affirmatively demurred when it had an opportunity to comment before the NYPSC.35
Issues relating to the Dunkirk RSSAs have been pending before this Commission since
July of 2012, while the Cayuga RSSA Proceeding commenced in November 2012.36 IPPNY is a
party in both of those proceedings. It filed a lengthy protest, which included another affidavit by
Mr. Younger, in the Cayuga RSSA Proceeding. IPPNY acknowledges that its protest included
arguments regarding the supposedly price-suppressive effects of the Cayuga RSSA Bidding
Requirement that are very similar to those included in the Complaint.37 TCR, the only IPPNY
member to have mentioned Existing RSSAs issues in the stakeholder process, also filed
comments filed in the Cayuga RSSA Proceeding. The NYISO stated four months ago that
IPPNY should have first brought these concerns to the stakeholder process.
Accordingly, IPPNY became aware of the core issues addressed by the Complaint, and developed lengthy arguments concerning them, more than four months ago.38 It had ample time to avail itself of the NYISO stakeholder process. IPPNY simply failed to do so. 39
35 See IPPNY’s July 30, 2012 letter in NYPSC Case No. 12-E-OI36 at 3
A.The Existing RSSAs Are Not Causing the “Uneconomic Retention” of
Existing Resources or “Artificial Price Suppression” in the NYISO Capacity
2. It Is Efficient and Reasonable for the Cayuga and Dunkirk Units that
Are Covered by Existing RSSAs to Clear in the Capacity Market
The Complaint contends that it is inappropriate for RSSAs to require that capacity
resources offer into the NYISO capacity markets at “de minimus” levels.52 According to
48 The NYISO notes that Mr. Younger is speculating when he suggests that the Cayuga and
49 See Patton Affidavit at P 21. See Dunkirk Power LLC, Filing of Unexecuted Cost of Service
50 See Patton Affidavit at P 21.
The Patton Affidavit highlights the error underlying IPPNY’s theory. In reality, it is
3. The Complaint’s Proposal to Require the Cayuga and Dunkirk Units
As Dr. Patton states, from an economic perspective,
60 Complaint at 36; see also Younger Affidavit at P 100.
4.The Complaint’s Arguments Regarding the Proposed Price
The Complaint, and the Younger Affidavit, make lengthy arguments concerning the
63 Complaint at 4, 26, 41; Younger Affidavit at P 13.
65 Id. at P 27; see also Complaint at 41.
66 See Complaint at 26, 39; Younger Affidavit at PP 8, 20, 28, 48, 98.
will cause the capacity markets to “unravel.” Future RSSAs will only cause artificial price
IPPNY to raise its concerns about these initiatives in the stakeholder process in the first
instance.74 By rejecting these aspects of the Complaint, the Commission would recognize the
74 The NYISO is aware that the Patton Affidavit indicates that Dr. Patton shares some of Mr.
Younger’s concerns regarding potential future “initiatives that could offer public support to prompt
C. Because the Existing RSSAs Do Not Result in “Uneconomic Retention”
The Complaint asks that the NYISO be required, immediately upon the issuance of a
75 Complaint at 5. See also Complaint at 36-37 and n. 141 (stating that because these tariff
D.The Commission Should Discourage IPPNY from Attempting to Circumvent
The Complaint’s substantive defects are addressed in Section II.A above and in the
The Commission has repeatedly discouraged attempts to make “end-runs” around
ISO/RTO governance processes by proposing tariff changes that have not had the benefit of
79 See, e.g., California Independent System Operator, Inc., 143 FERC ¶ 61,087 at P 73 (2013)
independent Board of Directors.80 While interested parties may ask that tariff changes be
IPPNY effectively acknowledges that the Complaint represents an end-run around the
stakeholder process.82 IPPNY attempts to justify its conduct based on its supposed need for
IPPNY also compares the unilateral action it took by filing the Complaint with an
86 See, e.g., Braintree Elec. Light Dept. v. ISO New England, Inc., 128 FERC ¶ 61,008 at P 50
(2009) (“The Commission does not find reliance on the stakeholder process to be an impermissible
may adversely affect the Commission’s statutory responsibilities under the FPA finding that “the
action is not prohibited does not mean that it cannot, or should not, be strongly disfavored. 87
Communications regarding this proceeding should be addressed to:88
New York Independent System Operator, Inc.
Rensselaer, NY 12144
Tel: (518) 356-6000
Fax: (518) 356-4702
rfernandez@nyiso.com
rstalter@nyiso.com
*persons designated to receive service
Hunton & Williams LLP
2200 Pennsylvania Avenue, NW Washington, DC 20037-1701 Tel: (202) 955-1500
Compliance with Commission Rule 213(c)(2)
A. Specific Admission and Denials of Material Allegations
•The NYISO denies that prices in the NYCA capacity market have been, or currently
• The NYISO denies that the Commission must act to protect the market from the
• The NYISO denies that the Cayuga and Dunkirk units are “uneconomic” because
they have RSSAs to retain them to address a reliability requirement. (Complaint
at 4, 27)
• The NYISO denies that the considerations that previously led the Commission to
State region...” (Complaint at 4, 11, 20)
•The NYISO neither admits nor denies the Complaint’s allegations and inferences
• The NYISO denies the Complaint’s allegations regarding the level of the financial
• The NYISO denies the Complaint’s predictions that the market will be harmed in the
• The NYISO denies that there is any need for Commission action in this proceeding to
• The NYISO denies that the Commission must act to protect the “sustainability” of the
• The NYISO denies that the possibility that Existing RSSAs may remain in effect for
• The NYISO denies that there is any need for expedited action or “immediate”
• The NYISO denies that the Existing RSSAs result in “uneconomic retention” that
harms the market in the same way as uneconomic entry. (Complaint at 21-23)
• The NYISO denies that the Existing RSSAs are inconsistent with or “disrupt” the
design of the NYISO-administered markets. (Complaint at 23, 27)
• The NYISO denies that using GFCs but ignoring RSSA revenues “as the proxy for a
competitive bid is economically sound.” (Complaint at 23-25)
• The NYISO neither admits nor denies the Complaint’s statements regarding factors
•The NYISO denies that either of the Complaints proposed tariff revisions would be
just and reasonable. (Complaint at 33-36)
• The NYISO denies that the Complaint has justified IPPNY’s end-around the NYISO
stakeholder process, is “limited in scope,” showed “deference” to the stakeholder
• The NYISO denies that past emergency actions by the NYISO to address market
•As it did in its Initial Answer, the NYISO denies that fast-track processing is
appropriate in this proceeding especially in light of Commission precedent
establishing that complex filings that propose tariff revisions should not be fast-
tracked and IPPNY’s own delays. (Complaint at 39)
• The NYISO admits that a purpose of the NYISO-administered capacity markets is to
• The NYISO admits that the descriptions of IPPNY and the NYISO in Section II of
the Complaint are correct. (Complaint at 6-7)
• The NYISO admits that Section III.A of the Complaint’s description of the existing
• The NYISO admits that Section III.B of the Complaint’s high level description of the
• The NYISO admits that Section III.C.1 of the Complaint’s description of the Dunkirk
RSSAs and the NYPSC proceedings addressing them is accurate, including its
acknowledgement that the Dunkirk RSSAs were and are needed for reliability
• The NYISO admits that Section III.C.2 of the Complaint’s description of the Cayuga
but denies any suggestion that the Cayuga RSSA has, or has had, anti-competitive or
price-suppressive effects.(Complaint at 14-18)
• The NYISO admits that the Cayuga and Dunkirk units appear to be “needed to
address an identified system condition...” (Complaint at 27)
In accordance with Commission Rule 213(c)(2)(ii), the NYISO sets forth the following defenses:
• Complainant has failed to meet its burden of proof under Sections 206 and 306 of the
• Complainant’s theory that the “uneconomic retention” of existing resources under the
• Complainant’s theory that Future RSSAs would cause artificial price suppression