Amanda C. Downey
Counsel
May 9, 2013
The Honorable Kimberly D. Bose Secretary
Federal Energy Regulatory Commission 888 First Street, N.E.
Washington, DC 20426
Re:Niagara Mohawk Power Corporation, d/b/a National Grid
Docket No. ER13-1077-001
Amendment to Large Generator Interconnection Agreement with Indeck-Yerkes Limited Partnership and
Request for Waiver of Commission Notice Requirement
Dear Secretary Bose:
Pursuant to Section 205 of the Federal Power Act (“FPA”),1 and Part 35 of the
Federal Energy Regulatory Commission’s (“Commission”) regulations,2 Niagara Mohawk Power Corporation d/b/a/ National Grid (“National Grid”) submits an amended Large
Generator Interconnection Agreement (“LGIA”) between National Grid and Indeck-Yerkes Limited Partnership (“Indeck-Yerkes”). The attached LGIA (the “Amended Indeck-Yerkes LGIA”) is designated as First Revised Service Agreement No. 1970 under the New York Independent System Operator, Inc.’s (“NYISO”) Open Access Transmission Tariff
(“OATT”). National Grid requests that the Commission accept the Amended Indeck-Yerkes LGIA effective as of the date it was executed, December 26, 2012.
I.Background
National Grid filed the original version of the Indeck-Yerkes LGIA in this
proceeding on March 13, 2013, with a requested effective date of December 26, 2012.
Subsequently, Commission Staff informed National Grid that the Indeck-Yerkes LGIA
needed to be amended to replace the term Network Access Interconnection Service, which is
no longer used in the NYISO OATT, with the terms Capacity Resource Interconnection
Service (“CRIS”) and Energy Resource Interconnection Service (“ERIS”), as defined in the
NYISO OATT.
II.The Amended Indeck-Yerkes LGIA
National Grid proposes to replace the term Network Access Interconnection Service
with the terms CRIS and ERIS in Articles 1, 4.1.1, 13.4.2, and 29.8 of the Indeck-Yerkes
1
2
16 U.S.C. § 824d.
18 C.F.R. Part 35.
40 Sylvan Road, Waltham, MA 02451
T: 781-907-2136 F: 781-907-5701 amanda.downey@nationalgrid.com www.nationalgrid.com
The Honorable Kimberly Bose May 9, 2013
Page 2
LGIA. The Amended Indeck-Yerkes LGIA defines CRIS and ERIS using the same definitions of those terms set forth in Article 1 of Appendix 6 to Appendix X (Large Generator Interconnection Procedures) to the NYISO OATT.
III. Effective Date and Request for Waiver
Pursuant to Section 35.11 of the Commission’s regulations,3 National Grid
respectfully requests waiver of the requirement contained in Section 35.3 of the
Commission’s regulations to file service agreements not more than 30 days after service
under the agreements has commenced,4 in order to allow the Amended Indeck-Yerkes LGIA to become effective as of December 26, 2012.
The Parties have agreed that the Indeck-Yerkes LGIA “shall become effective upon
execution by the Parties, subject to acceptance by FERC.”5 The Parties executed the
Indeck-Yerkes LGIA on December 26, 2012. Granting the requested waiver will permit the
Amended Indeck-Yerkes LGIA to become effective as of the date agreed upon by the
Parties and will not result in prejudice to any party. For these reasons, the Commission
should find that good cause exists to grant an effective date of December 26, 2012.
3
4
5
18 C.F.R. § 35.11.
18 C.F.R. § 35.3.
Indeck-Yerkes LGIA, Article 2.1.
The Honorable Kimberly Bose May 9, 2013
Page 3
IV.Documents Enclosed
In addition to this filing letter, attached are the following documents:
i. The Amended Indeck-Yerkes LGIA (First Revised Service Agreement No.
1970 under the NYISO OATT), provided in clean format (Attachment A)
ii. Black-lined revisions showing the differences between the Amended Indeck-
Yerkes LGIA and the Indeck-Yerkes LGIA as originally filed in this proceeding on March 13, 2013 (Attachment B)
V.Communications and Service
Communications regarding this filing should be addressed to the following
individuals, whose names should be entered on the official service list maintained by the
Secretary for this proceeding:6
Amanda C. Downey
Counsel for National Grid
Service Company, Inc.
40 Sylvan Road
Waltham, MA 02451 (781) 907-2136
amanda.downey@nationalgrid.com
William L. Malee
Director, Transmission Commercial National Grid USA
40 Sylvan Road
Waltham, MA 02451 (781) 907-2422
bill.malee@nationalgrid.com
Sean A. Atkins
Bradley R. Miliauskas Alston & Bird LLP The Atlantic Building 950 F Street, NW
Washington, DC 20004 (202) 239-3300
sean.atkins@alston.com
bradley.miliauskas@alston.com
Copies of this filing have been served on Indeck-Yerkes, the NYISO, and the New York State Public Service Commission.
6
National Grid requests waiver of 18 C.F.R. § 385.203(b) to allow four persons to be added to the
service list in this proceeding.
The Honorable Kimberly Bose May 9, 2013
Page 4
VI.Conclusion
For the reasons stated herein, National Grid respectfully requests that the
Commission accept the Amended Indeck-Yerkes LGIA effective as of December 26, 2012.
Respectfully submitted,
/s/ Amanda C. Downey
Amanda Downey
Counsel
National Grid USA
Service Company, Inc.
40 Sylvan Road
Waltham, MA 02451
Attorney for Niagara Mohawk Power
Corporation d/b/a National Grid