UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
New York Independent System Operator, Inc.)Docket No. ER13-1380-000
REQUEST FOR PARTIAL RECONSIDERATION
OF THE NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.
In accordance with Rule 212 of the Commission’s Rules of Practice and Procedure,1 the New York Independent System Operator, Inc. (“NYISO”), respectfully submits this request for partial reconsideration of one element of the Commission’s Order Accepting Proposed Tariff Revisions and Establishing a Technical Conference (“August 13 Order”).2 Specifically, the Commission should reconsider the August 13 Order’s rejection of a proposed “phase-in” of the price impacts of the G-J Locality;3 i.e., the New Capacity Zone proposed by the NYISO in its April 30, 2013 filing and accepted by the August 13 Order.4
The NYISO continues to believe that implementing the G-J Locality by May 1, 2014
would “send more efficient price signals, enhance reliability, mitigate potential transmission
security issues, and serve the long-term interest of all consumers in New York State.”5 But the
NYISO also believes that there is a significant likelihood of short-term consumer impacts that
merit action by the Commission. After considering more current information about the potential
1 18 C.F.R. 385.212 (2013).
2 New York Independent System Operator, Inc., 144 FERC ¶ 61,126 (2013) (“August 13 Order”).
3 Capitalized terms that are not defined herein shall have the meaning set forth in the NYISO’s Market Administration and Control Area Services Tariff.
4 See also Letter Order Accepting New York Independent System Operator, Inc's Compliance
Filing Dated 6/19/13 in Response to the Commission's June 6, 2013 Order under ER12-360, Docket No. ER12-360-003 (August 14, 2013).
5 New York Independent System Operator, Inc., Proposed Tariff Revisions to Establish and Recognize a New Capacity Zone and Request for Action on Pending Compliance Filing, Docket No. ER13-1380-000 (April 30, 2013) (“April 30 Filing”) at 1.
retail rate impacts of implementing the G-J Locality, the NYISO has concluded that a phase-in of the price impacts is necessary to ameliorate effects on consumers and mitigate what has been described as potential “rate shock.” 6
After considering the information now available, the NYISO believes phasing in the
capacity price increases associated with creating the G-J Locality is an equitable means to protect
consumers from the risk of immediate and significant increases in their electric bills. A phase-in
would provide retail customers with an opportunity to mitigate bill increases, e.g., through
energy efficiency and conservation measures. Further, a principal goal of creating New Capacity
Zones, i.e., incentivizing investment in new capacity, would not be defeated by gradually
implementing the price signals over the three year duration of the initial ICAP Demand Curve
for the G-J Locality. Even with a phase-in, investments in new generation, which typically have
a construction cycle of two to three years, will receive the needed price signal. The NYISO also
believes that existing capacity needed for reliability can be expected to be retained even with a
phase-in over the three year period. Thus, a phase-in can mitigate short-term consumer impacts
without suppressing desired investment signals, necessary to satisfy reliability requirements.
Finally, adopting a phase-in of the first New Capacity Zone is consistent with prior Commission
actions concerning NYISO ICAP Demand Curves.
The NYISO recognizes the August 13 Order’s concern that a phase-in could “delay the
capacity market’s ability to send more efficient price signals,”7 that the creation of the G-J
Locality has been anticipated for years, and that the record includes pleadings opposing a
6 See Petition for Rehearing of the New York Power Authority, Docket No. ER13-1380-003 at 17
(“A phase-in would reduce the rate shock imposed on consumers without undermining or delaying the
development of the new supply in the G-J NCZ that the NCZ is intended to incentivize.”); Request for
Rehearing of the Central Hudson Gas and Electric Corp., Docket No. ER13-1380-003 at 2 (“rapidly
approaching rate shock... ”) (September 12, 2013) (“Central Hudson Request for Rehearing”).
7 August 13 Order at P 31.
2
phase-in. Nevertheless, since the NYISO’s April 30 Filing, more current information has
become available concerning the potential consumer impacts of implementing the G-J Locality
for the Capability Period beginning May 1, 2014. As discussed below, the consumer
responsiveness requirements applicable to all Independent System Operators and Regional
Transmission Organizations under Order No. 7198 caused the NYISO to bring this new
information to the Commission’s attention through this request for reconsideration.
I.BACKGROUND
In the April 30 Filing, the NYISO included analyses of potential price impacts of the G-J
Locality based on information available and reasonable assumptions at that time. Specifically,
the April 30 Filing included an affidavit by the NYISO’s Consumer Interest Liaison, Mr. Tariq
N. Niazi (“Niazi Affidavit”) that focused on two forward-looking wholesale consumer impact price analyses. Mr. Niazi’s affidavit indicated that his analyses were based upon a number of assumptions including the reference prices and zero crossing points that would be incorporated in the New Capacity Zone ICAP Demand Curves. Moreover, the NYISO made clear that the analyses discussed in the Niazi Affidavit were just two of many that the NYISO conducted and were not intended to be price forecasts.9
Mr. Niazi’s simulations showed that there would be increased capacity prices in Load
Zones G, H, and I over the prices likely to occur absent the creation of the G-J Locality. He
quantified those increases at $173 million per year, which would translate into approximately
$500 million over the first three years of the G-J Locality. As discussed below, a more current
assessment of the price impacts utilizing information contained in the report of the NYISO’s
8 Wholesale Competition in Regions with Organized Electric Markets, Order No. 719, FERC
Stats. & Regs. ¶ 31,281 (2008), order on reh’g, Order No. 719-A, FERC Stats. & Regs. ¶ 31,292 (2009), order denying reh’g, Order No. 719-B, 129 FERC ¶ 61,252 (2009).
9 April 30 Filing at n. 35.
3
independent ICAP Demand Curve reset consultant (“Independent Consultant”)10 and the NYISO staff’s ICAP Demand Curve proposal to the Board of Directors dated September 6, 2013,
suggests the potential for even greater price impacts. Moreover, several parties, notably the
New York State Public Service Commission (“NYPSC”), have now quantified the G-J Locality’s potential retail rate impacts to New York ratepayers.
It is important to note that the NYISO has not objected to a phase-in in this proceeding;
rather it has deferred until this point, to other parties and the Commission. The Indicated New
York Transmission Owners’ (“Indicated NYTOs”)11 protest of the April 30 Filing requested that
the Commission direct the NYISO to “phase-in the capacity price increases that will result from
the creation of the NCZ over a reasonable period.”12 The NYISO responded that it continued to
support the creation of the G-J Locality but stated that it took no position on the question of
“whether a phase in of capacity price increases is warranted on noneconomic grounds.”13 Specifically, the NYISO stated that:
The NYISO … notes that it cannot yet evaluate whether any phase-in option
would be administratively feasible or would threaten the timing of the
implementation of the NCZ (or the ICAP Demand Curves). The NYISO expects
that other parties will create a complete record on the equitable considerations
10 The Independent Consultant, selected in accordance with Services Tariff Section 5.14.1.2, is NERA Economic Consulting, with its subcontractor, Sargent & Lundy.
11 The Indicated NYTOs are Central Hudson Gas & Electric Corporation, Consolidated Edison Company of New York, Inc., New York Power Authority, New York State Electric & Gas Corporation, Niagara Mohawk Power Corporation d/b/a National Grid, Orange and Rockland Utilities, Inc., and
Rochester Gas and Electric Corporation. See Request for Rehearing of the Indicated New York
Transmission Owners, Docket No. ER13-1380-003 (September 12, 2013.)
12 Motion to Intervene and Protest of the Indicated New York Transmission Owners, Docket No. ER13-1380-000 at 2 (June 13, 2013); NYPSC Request for Rehearing at p. 9 (supporting Indicated
NYTOs' request for phase-in).
13 Answer to Comments and Request for Leave to Answer and Answer to Protests of the New York Independent System Operator, Inc., Docket No. ER13-1380-000 (June 5, 2013) at 34 (quoted language capitalized in original).
4
posed by phase-in proposals. Accordingly, the NYISO does not believe that there is anything further for it to add to the record on this issue at this time.14
It was not until after the August 13 Order and the filing of requests for rehearing that further specific information was proffered on the retail rate impacts of the G-J Locality. For example, the NYPSC’s rehearing request asserted that without a phase-in some consumer retail rates could increase by as much as 25% upon implementation.15 In addition, Central Hudson’s request for rehearing emphasizes that implementing the G-J Locality would result in wholesale capacity price increases of as much as 475% to its customers.16
The NYPSC also contends on rehearing that such price increases would not send efficient
long-term price signals because Governor Andrew Cuomo’s “Energy Highway Blueprint”17 is
expected to result in the construction of new transmission facilities that will alter the
configuration of the New York State Transmission System over the next few years. The NYPSC
asserts that the State programs have progressed and questions “the effectiveness of creating an
NCZ at this time, while requiring ratepayers to pay hundreds of millions in additional Installed
Capacity costs within the NCZ with no concomitant benefits to consumers.”18 The NYISO notes
that on October 17, 2013, the NYPSC approved several projects that were proposed in a NYPSC
14 Id. at 34-35.
15 Request for Rehearing and Clarification of the New York State Public Service Commission,
Docket No. ER13-1380-001 (September 12, 2013) (“NYPSC Request for Rehearing”) at 5, 9-10. Central Hudson Request for Rehearing at 8-9.
16 Central Hudson Request for Rehearing at 8-9, 15. See also NYPSC Request for Rehearing at 8,
n. 16 (“As noted above, the NYPSC estimates the price impacts may be upwards of $350 million per year, which translates to a rate increase of over 25% for some customers.”)
17 See, e.g., NYPSC Request for Rehearing at 7-8 (describing New York State’s ongoing transmission policy initiatives)
18 See, e.g., NYPSC Request for Rehearing at 8 citing New York State Public Service Commission
Notice of Intervention and Protest, Docket No. ER13-1380-000 (May 21, 2013) at 3 (emphasis in
original).
5
proceeding established to further the Energy Highway Blueprint.19 The NYPSC describes the
approved projects as “three transmission projects capable of reducing capacity needs by upwards of 600 MW and extension of existing programs and creation of new programs designed to reduce downstate electricity use by 180 MW through energy efficiency and demand response.”20
II. REQUEST FOR PARTIAL RECONSIDERATION
The Commission has discretion to reconsider its orders at any time.21 A request for
reconsideration “must show new information or evidence of changed circumstances that would
warrant reconsideration by the Commission.”22 There is new information not currently before
the Commission that warrants reconsideration of the August 13 Order’s phase-in ruling.23
A. Description of New Information
In the six months since the April 30 Filing, new information has developed concerning
the potential severity of the capacity price impacts of implementing the G-J Locality. Most
significantly, the proposed parameters of the G-J Locality’s ICAP Demand Curves for the
2014/2015 through 2016/2017 Capability Years (and therefore the prices that may result from it)
have been developed by the NYISO’s Independent Consultant. The NYISO staff reviewed those
parameters and, in large part, recommended them to the NYISO Board of Directors. This
information was not available when Mr. Niazi performed his initial consumer analyses.
19 NYPSC Docket No. 12-E-0503, press release issued October 17, 2013, available at
˂http://www3.dps.ny.gov/pscweb/WebFileRoom.nsf/Web/A0167A43AAA2952585257C07005A9F37/$F
ile/pr13076.pdf?OpenElement˃, (“PSC Details Plans to Ensure Grid Reliability and Safeguard
Customers”).
20 Id.
21 See Florida Power & Light Co., 122 FERC ¶ 61,159 at P 9 and n.19 citing Cities of Campbell and Thayer v. FERC, 770 F.2d 1180, 1183 (D.C. Cir. 1985).
22 Enterprise Texas Pipeline, L.P., 117 FERC ¶ 61,025 at P 7 (2006).
23 This filing does not seek reconsideration of any other element of the August 13 Order and the NYISO is not addressing any other issue raised by the requests for rehearing at this time.
6
Mr. Niazi’s analyses were instead based on scenarios that used assumptions about the various
ICAP Demand Curve reset parameters. More specifically, the NYISO’s Independent Consultant completed its study of the parameters for the 2014/15 through 2016/17 ICAP Demand Curves in early August 2013.24 The NYISO staff issued its own recommendations, which adopted most of the consultant’s proposals on September 6, 2013.25 By contrast, Mr. Niazi’s analyses were
undertaken in January through April when the data used in the reports was only in the initial
stages of development. Thus the analyses presented in the April 30 Filing were not informed by the data used to formulate these later reports. More refined information about reference prices
and zero crossing points was likewise not available when Mr. Niazi performed his initial
consumer impact analyses. The more current information is consistent with the NYPSC’s and
other parties’ assertions that there may be a severe price impact from the first-time application of a Locational Minimum Installed Capacity Requirement and implementation of a new ICAP
Demand Curve for Load Serving Entities in the G-J Locality.
The NYPSC has asserted that some consumer rates would increase by 25% solely from
implementing these changes in the NYISO’s capacity market rules. By way of comparison, the
NYISO’s understanding, based on publically available information, is that recently approved
24 Section 5.14.1.2 of the Services Tariff requires the NYISO to initiate an independent review of
the ICAP Demand Curves every three years in accordance with the ISO Procedures to determine the
parameters of the ICAP Demand Curves for the next three Capability Years. In accordance with Section
5.14.1.2, the NYISO retained the ICAP Demand Curve consultant which prepared its “Independent Study
to Establish Parameters of the ICAP Demand Curve for the New York Independent System Operator”
available at
˂http://www.nyiso.com/public/webdocs/markets_operations/committees/bic_icapwg/meeting_materials/2
013-08-13/Demand%20Curve%20FINAL%20Report%208-2-13.pdf˃.
25 See New York Independent System Operator, Inc., "Proposed NYISO Installed Capacity
Demand Curves for Capability Years 2014/2015, 2015/2016 and 2016/2017 - Final" (dated September 6, 2013) available at
˂http://www.nyiso.com/public/webdocs/markets_operations/committees/bic_icapwg/meeting_materials/2
013-09-11/2013%20NYISO%20Demand%20Curve%20Recommendation_9-6-13_clean.pdf ˃.
7
retail electric rate increases in New York have ranged from 2.5% to 5.8%.26 Thus the potential
retail rate increases associated with the implementing this new capacity zone could be
significantly larger than any other recent retail rate increase. The record in this proceeding
contains little, if any, information discussing the potential price impacts in the context of retail
rates.
In October 2013 the NYISO’s Board of Directors received written comments and heard oral arguments from stakeholders concerning the proposed ICAP Demand Curves. The
stakeholder information further highlighted the real possibility that there could be severe price increases in the G-J Locality resulting from ICAP Demand Curves based upon information in the Independent Consultant’s report and the NYISO staff’s proposal.27
26 See, e.g., PSC Adopts 3-Year Electric Rate Plan for O&R, NYPSC Press Release No. 12043,
Case No. 11-E-0408 (June 14, 2012) (average annual rate increase of 5.8%); PSC Sets Rate Plans for
NYSEG and RG&E, NYPSC Press Release No. 1088, Case Nos. 09-E-0715, 09-G-0716, 09-E-0717; 09-
G-0718 (Sept. 16, 2010) (increasing electric rates by between 2.6 percent and 4.3 percent per year); New
Gas, Electric Rates for Central Hudson Approved, NYPSC Press Release No. 10056, Case Nos. 09-E-
0588; 09-G-0589 (June 17, 2010) (electric rate increases between 3.2 percent and 4.5 percent per year);
New 3-Year Rate Plan Approved for Con Edison, New York Public Service Commission, NYPSC Press
Release No. 10028. Case Nos. 07-E-0523, 08-E-0539, 09-E-0428 (March 25, 2010) (3.60% levelized
annual rate increase); PSC Adopts 3-Year Electric Rate Plan for O&R, NYPSC Press Release No. 08079, Case No. 07-E-0949 (July 16, 2008) (electric rate increase of 2.5 percent per year). Copies of all NYPSC press releases are posted at
<http://www3.dps.ny.gov/pscweb/WebFileRoom.nsf/PressReleases?OpenForm&Count=5000>.
Individual electric case numbers may be searched at
<http://www3.dps.ny.gov/W/PSCWeb.nsf/All/B428BB2B680CD9B485257687006F3890?OpenDocumen
t>.
27 See also Comments of the Indicated New York Transmission Owners on Proposed ICAP
Demand Curves for 2014-17 at 1 (arguing that the NYISO Staff Proposal would result in “a major
unjustified price increase for New York State’s electricity customers” and that “ICAP costs could
unnecessarily increase in by approximately $140 million annually in the LHV and more than $350 million
annually in New York City if the appropriate proxy unit for those demand curves is not selected.”)
available at
˂http://www.nyiso.com/public/webdocs/markets_operations/market_data/icap/Reference_Documents/201
4-
2017%20Demand%20Curve%20Reset/Demand_Curve_Reset/NYTO%20Demand%20Curve%20Reset% 20Comments%20to%20Board(final).pdf˃.
8
The NYISO Board has not completed its deliberations regarding the parameters of the ICAP Demand Curves for the Capability Years 2014/15 through 2016/17.28 ICAP Demand Curves that are ultimately approved by the NYISO Board of Directors will be filed with the Commission on or before November 29, 2013.29
B. The NYISO’s Consideration of Consumer Impacts
The NYISO’s principal focus is to administer efficient and competitive markets without favoring any Market Participant or stakeholder group. While the New York wholesale electricity markets are designed to send long-term economically efficient price signals, the NYISO cannot be indifferent to the short-term consumer impacts resulting from its market rules. This is true even where those rules are intended to provide the correct long-term price signal that in the long term would be in consumers’ best interests.30
Under Section 35.28(g)(6) of the Commission’s regulations, i.e., the “responsiveness”
rules promulgated by Order No. 719, the NYISO has an obligation to consider consumer
impacts. This obligation includes an “ongoing responsiveness” requirement under which the
NYISO must “continue over time to consider customer and other stakeholder needs as the
architecture or market environment of the RTO or ISO changes.”31 The NYISO believes that the
potential capacity price increases for the G-J Locality constitute a change in “market
environment” that justifies seeking reconsideration. Given the information that is now available
28 On October 17, 2013 the NYISO notified stakeholders that the Board has directed it to conduct
further due diligence on the appropriate proxy unit to be used to establish the G-J Locality and other
ICAP Demand Curves. The NYISO indicated that the results of the due diligence would be made public
and that stakeholders would be afforded an opportunity to provide supplemental written comments to the
Board.
29 See Services Tariff 5.14.1.2.11.
30 The NYPSC Request for Rehearing notes at 7 that the NYPSC “did not dispute that creating an NCZ could have long-term reliability benefits, or that the creation of a new NCZ in Zones G-J may
eventually incent new generation in that location... ”
31 Order No. 719 at P 509.
9
to it, the NYISO cannot ignore the potentially significant consumer impacts of implementing this new capacity zone without a phase-in.32
As noted above, the NYISO now believes that the Commission should order a phase-in over the initial Demand Curve period (i.e., three years). Importantly, the NYISO believes that phasing-in the G-J Locality price increase can be accomplished in a balanced and equitable manner that will not interfere with price signals necessary to attract investment in new capacity or maintain existing efficient capacity. Further, existing economic capacity will still see a new price signal even with a phase-in, and this request for reconsideration only proposes to address dramatic short-term price increases that may occur.
It is important to recall that Commission took a similar approach when it first approved
the implementation of ICAP Demand Curves in New York. In 2003, the Commission concluded
that a phase-in was appropriate to “ameliorate” ratepayer impacts by gradually implementing the
cost of new entry into the newly-adopted demand curves.33 A similar situation exists today. The
G-J Locality is the first new capacity zone implemented since the NYISO’s inception. As with
the ICAP Demand Curves first adopted in 2003, the New Capacity Zone is a major change in the
market. Given its potentially significant retail rate impact, it is a market change that should be
32 The NYISO intends to follow the August 13 Order’s suggestion that it explore with its
stakeholders possible mechanisms to determine whether there is a need to eliminate “unneeded” zones,
and if so the mechanism to do so. See August 2013 Order at P 82 (“[w]e reiterate here that NYISO
should work with its stakeholders, and if a mechanism for zone elimination is deemed necessary, NYISO
should file appropriate tariff revisions with the Commission.”); see also, New York Indep. Sys. Operator,
Inc., 136 FERC ¶ 61,165 at P 70 (2011). However, no such effort would be responsive to short-term
price concerns since, as the NYPSC Request for Rehearing states, transmission construction under the
Energy Highway Blueprint may not occur until 2018. See NYPSC Request for Rehearing at 8.
33 New York Independent System Operator, Inc., 103 FERC ¶ 61,201 at P 6 (2003).
10
undertaken in a measured fashion that takes into consideration the short-term implications for retail customers.34
Moreover, a short-term phased approach likely would not interfere with long-term
investment decisions to develop new generation in the G-J Locality because of the revenue
forecast horizon utilized by developers. So long as a sufficient price signal is present in the third year of the G-J Locality ICAP Demand Curve and beyond, the NYISO expects that there will be an appropriate incentive for new investment. In other words, phasing-in capacity prices during the first three years of this new capacity zone should not materially affect investors’ responses. Further, as mentioned above, existing capacity needed for reliability will still realize increased prices and revenues within this three-year period.
As an equitable matter, a phase-in would provide retail ratepayers with an opportunity to better anticipate, and take steps to respond to, potentially large price increases. Consumers
generally, and retail customers in particular, are generally not poised to react quickly to
wholesale price increases. Given sufficient time, however, they may be able to mitigate their
exposure to a wholesale price increase through energy efficiency and other demand-side actions, and thus avoid potential rate shock.
An additional basis for reconsideration is the fact that the NYISO has now concluded that
it would be administratively feasible to implement a phase-in. Specific phase-in proposals were
not presented in pleadings when the NYISO first addressed the issue in June. The NYISO
subsequently determined that it can administer a phase-in through structuring the ICAP Demand
34 This filing brings to the Commission's attention information provided by parties on retail
consumer price impacts that might result from the NYISO’s market rules in the absence of a phase-in. It is possible that both the NYISO Board of Director’s ultimate determination about the new ICAP Demand Curves and future market activities could result in different price impacts.
11
Curve for the G-J Locality.35 This approach would not require significant software revisions. Based on this approach, which had not been previously considered in this proceeding, the
NYISO now believes that a phase-in of capacity price increases in the G-J Locality is
administratively feasible.36
As noted above, the Commission accepted a very similar phase-in of the original ICAP
Demand Curves in 2003 on the ground that it would “ameliorate rate impacts.”37 The
Commission has also traditionally accepted rate treatments designed to avoid customer rate
shock, particularly in its decisions permitting the inclusion of up to 100 percent of Construction
Work in Progress (“CWIP”) costs in utility rate base in order to preserve rate stability and avoid
abrupt rate increases.38 Thus, providing for a phase-in of capacity price increases for the G-J
35 As noted above, the ICAP Demand Curve for the G-J Locality, along with the ICAP Demand Curves, will be filed on or before November 29, 2013.
36 There are likely also additional administratively feasible ways that a phase-in could be implemented.
37 New York Independent System Operator, Inc., 103 FERC ¶ 61,201 (2003)
38 See, e.g., Northern Indiana Public Service Co., 141 FERC ¶ 61,231 at P 33 (“Furthermore, as
the Commission has previously determined in prior orders, the CWIP incentive will help insulate
NIPSCO’s customers from “rate shock” that might otherwise accompany use of AFUDC.”); PJM
Interconnection LLC, 135 FERC ¶ 61,229, at P 78 (2011) (“As explained in prior orders, when certain
large-scale transmission projects come on line, there is a risk that consumers may experience “rate shock”
if CWIP is not permitted in rate base. By allowing CWIP in rate base, the rate impact of each of the three
projects can be spread over the construction period and will help reduce rate shock.”) (footnotes omitted);
PPL Electric Utilities Corp., 123 FERC ¶ 61,068, at PP 40-43 (2008); American Elec. Power Serv. Corp.,
116 FERC ¶ 61,059, at P 59 (2006), order on reh'g, 118 FERC ¶ 61,041, at P 27 (2007).] See also
Promoting Transmission Investment through Pricing Reform, Order No. 679, FERC Stats. & Regs. ¶
31,222 at PP 29, 117 (establishing a policy that allows utilities to include, where appropriate, 100 percent
of prudently-incurred transmission-related CWIP costs in rate base), order on reh’g, Order No. 679-A,
FERC Stats. & Regs. ¶ 31,236 (2006), order on reh’g, 119 FERC ¶ 61,062 (2007).Construction Work In
Progress for Public Utilities; Inclusion of Costs in Rate Base, Order No. 298, 48 Fed. Reg. 24,323
(1983), at 30,499 (“Without any CWIP in rate base, a new plant has no direct effect on consumer prices
until it begins to provide service. Then, when it does come on line, consumer’s rates must be increased to
give the company a cash return on both the direct cost of the plant and the capitalized [(AFUDC)] as well
as a return of capital through depreciation. If the plant is large relative to the existing rate base, the result
can be a rate increase that is both large and sudden, producing a so-called ‘rate shock’. In contrast, with
all CWIP in rate base, the impact of new plant is spread over the entire construction period, and the rates
12
Locality would be consistent with Commission precedent. It would also appear to align with the Commission’s recent indications of its greater willingness to accommodate “legitimate state
policy objectives” within the framework of competitive capacity markets.39 Accommodating
consumer interests in this proceeding would not prevent the G-J Locality from having its
intended market design effect.
III.COPIES OF CORRESPONDENCE
Copies of correspondence concerning this filing should be served on:
Robert E. Fernandez, General Counsel
Raymond Stalter, Director of Regulatory Affairs *Gloria Kavanah, Senior Attorney
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-6000
Fax: (518) 356-4702
rfernandez@nyiso.com rstalter@nyiso.com
gkavanah@nyiso.com
* -- Persons designated for service.
*Ted J. Murphy
Hunton & Williams LLP
2200 Pennsylvania Ave., NW Washington, DC 20037-1701 Tel: (202) 955-1500
Fax: (202) 778-2201
tmurphy@hunton.com
when the plant begins to provide service are lower because they do not include a return on and of capitalized AFUDC.”).
39 See Notice Allowing Post-Technical Conference Comments, Docket No. AD13-7-000 (October
25, 2013) (seeking written comments regarding “[a]ccommodating state policies . . . ,”); Supplemental
Notice of Technical Conference, Docket No. AD13-7-000 (August 23, 2013) (raising questions
concerning whether “centralized capacity markets effectively accommodate various federal and state
policies... ” and what might be done to ensure that the market designs do so more effectively); See also
New England States Committee on Electricity v. ISO New England, Inc., 142 FERC ¶ 61,108 (2013)
dissenting opinion of Chairman Wellinghoff and Commissioner Norris (questioning whether the existing
New England capacity market design does enough to accommodate “legitimate state policy goals.”).
13
IV.CONCLUSION
In conclusion, for the reasons set forth above, the NYISO respectfully requests that the Commission reconsider the August 13 Order’s decision to reject a phase-in of the price impacts for the G-J Locality.40
Respectfully submitted,
/s/ Robert E. Fernandez
Robert E. Fernandez
Gloria Kavanah
Ted J. Murphy, Hunton & Williams LLP On behalf of
New York Independent System Operator, Inc.
October 28, 2013
cc:Michael A. Bardee
Gregory Berson
Anna Cochrane
Jignasa Gadani
Morris Margolis
David Morenoff
Michael McLaughlin Daniel Nowak
40 As noted above, the actual ICAP Demand Curves will be filed on or before November 29,
2013.
14
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person
designated on the official service list compiled by the Secretary in this proceeding in accordance
with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. §385.2010.
Dated at Rensselaer, NY this 28th day of October, 2013.
/s/ Joy A. Zimberlin
Joy A. Zimberlin
New York Independent System Operator, Inc.
10 Krey Blvd.
Rensselaer, NY 12144 (518) 356-6207