10 Krey Boulevard Rensselaer, NY 12144
July 10, 2013
By Electronic Delivery
Ms. Kimberly D. Bose Secretary
Federal Energy Regulatory Commission 888 First St, NE
Washington, DC 20426
Re: New York Independent System Operator, Inc. and New York Transmission Owners,
Interregional Compliance Filing, Docket Nos. RM10-23-000, ER13-___-000
Dear Ms. Bose:
In compliance with Order No. 1000, the Commission’s Final Rule on Transmission
Planning and Cost Allocation by Transmission Owning and Operating Public Utilities,1 the New
York Independent System Operator, Inc. (“NYISO”) respectfully submits this compliance filing.
The New York Transmission Owners (“NYTOs”)2 jointly submit with the NYISO Section VII of
1 Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, Order No. 1000, 136 FERC ¶ 61,051 (2011) (“Order No. 1000), order on reh’g and
clarification, Order No. 1000-A, 139 FERC ¶ 61,132 (2012) (“Order No. 1000-A), order on reh’g and clarification, 141 FERC ¶ 61,044 (2012) (“Order No. 1000-B”). For convenience, unless otherwise
specified, references in this filing to “Order No. 1000” should be understood to encompass Order Nos. 1000, 1000-A, and 1000-B.
2 The NYTOs are: Central Hudson Gas & Electric Corporation, Consolidated Edison Company of
New York, Inc. (“Con Edison”), Long Island Lighting Company d/b/a LIPA (“LIPA”), New York Power
Authority (“NYPA”), New York State Electric & Gas Corp., Niagara Mohawk Power Corp. d/b/a
National Grid, Rochester Gas & Electric Corp., and Orange & Rockland Utilities, Inc. (“O&R”). The fact
that the NYTOs are only parties to Section VII of this filing should not be interpreted as meaning that
they oppose the other parts. However, the NYTOs reserve the right to comment separately on this filing.
LIPA and NYPA as transmission owners not subject to the FERC’s rate jurisdiction under Section 205 of
the Federal Power Act have voluntarily participated in the development of this comprehensive filing and
thereby join the other NYTOs in this pleading. Though Con Edison, O&R, NYPA, and LIPA support this
compliance filing, they disagree with the application of the avoided cost methodology to an interregional
transmission project that costs more than the cost of the displaced regional projects and reserve the right
to file a protest to this aspect of the filing.
1
this filing. Accordingly, solely for purposes of Section VII, the NYISO and the NYTOs are referred to in this filing as the “Joint Filing Parties.”3
The NYISO developed this interregional compliance filing in close collaboration with the
NYTOs and with its two Commission-jurisdictional neighboring transmission system operators,
i.e., the PJM Interconnection, L.L.C. (“PJM”) and ISO New England, Inc. (“ISO-NE”). The
collaborative process included extensive outreach to stakeholders in all three regions. PJM and
ISO-NE are concurrently submitting their own Order No. 1000 interregional compliance filings.
Naturally, there is substantial overlap among the NYISO’s, PJM’s, and ISO-NE’s interregional
compliance filings because each is largely concerned with the same proposed amendments to the
same interregional planning arrangements. As noted below in Section VIII, it is also desirable
that the common revisions proposed in each filing become effective at the same time, in this case
proposed to be January 1, 2014.4 Nevertheless, the NYISO is making this individual compliance
filing to seek the Commission’s approval of the interregional planning arrangements and to
demonstrate its own compliance with Order No. 1000’s interregional requirements.5
The NYISO already complies with many of Order No. 1000’s interregional transmission
planning requirements. This compliance filing proposes revisions to the NYISO’s current
transmission planning processes set forth in its agreements and tariffs to bring them into full
compliance with all of the Order No. 1000 interregional transmission planning requirements.
Specifically, the NYISO, along with PJM and ISO-NE, have revised the existing Northeastern
ISO/RTO Planning Coordination Protocol (“Protocol”), which is an agreement that existed prior
to Order No. 1000 between and among the NYISO, PJM, and ISO-NE as well as their
neighboring Canadian system operators.6 The Protocol is being amended to set forth enhanced
interregional coordination procedures that address most of Order No. 1000’s interregional
planning requirements (“Amended Protocol”). In accordance with the Commission’s electronic
tariff filing requirements, only one entity, in this case ISO-NE, is filing the Amended Protocol.
The NYISO fully supports the Amended Protocol and is submitting, through ISO-NE’s filing, a
certificate of concurrence regarding the Amended Protocol pursuant to Section 35.1(a) of the
3 Nothing in this filing should be interpreted to adversely affect, limit, or diminish the Section 205 filing rights of the Joint Filing Parties.
4 ISO-NE proposes an effective date of July 10, 2013 for the Northeastern ISO/RTO Planning Coordination Protocol, which is its date of executive by the CEOs of ISO-NE, PJM and NYISO.
5 By filing individually, the NYISO seeks to assist the Commission by demonstrating its own compliance with Order 1000’s interregional planning principles and directives.
6 The NYISO and ISO-NE have discussed the proposed compliance changes to the Protocol that
are described in this compliance filing with our non-jurisdictional neighboring transmission system
operators in Canada, i.e., the Ontario Independent Electricity System Operator, Hydro-Quėbec
TransÉnergie and New Brunswick Power. These Canadian entities are not joining this filing and will not
be directly impacted by the proposed changes to the Protocol. The NYISO has confirmed that these
entities will continue to coordinate inter-regional transmission planning with the NYISO (and with PJM
and ISO-NE) as already provided in the Protocol’s existing provisions. The NYISO is therefore in full
compliance with the international coordination requirement set forth in Paragraph 421 of Order No. 1000.
2
Commission’s regulations.7 For the Commission’s convenience, the NYISO is also including a copy of the Amended Protocol as an exhibit to this filing letter. In addition, this filing letter includes a description of the Amended Protocol’s interregional planning enhancements that is consistent with the language used by ISO-NE and by PJM in their filings.
Section 9 of the Amended Protocol indicates that the cost allocation for identified
Interregional Transmission Projects8 between the NYISO and PJM shall be conducted in
accordance with the Joint Operating Agreement Among and Between New York Independent
System Operator, Inc. and PJM Interconnection, L.L.C. (“Joint Operating Agreement” or
“JOA”) in Attachment CC of the NYISO’s Open Access Transmission Tariff (“OATT”). It also specifies that the cost allocation for identified Interregional Transmission Projects involving the NYISO and ISO-NE shall be conducted in accordance with their respective tariffs.
In conjunction with Section 9 of the Amended Protocol, the NYISO is submitting
proposed revisions to the Joint Operating Agreement that establish the cost allocation
requirements for Interregional Transmission Projects involving both the NYISO and PJM.9 In
addition, the NYISO is submitting proposed revisions to Attachment Y of its OATT that
establish the cost allocation requirements for Interregional Transmission Projects involving the
NYISO and ISO-NE. The NYISO understands that ISO-NE will include parallel tariff revisions
in its own interregional compliance filing. As discussed below, the NYISO’s proposed cost
allocation compliance revisions would establish substantially identical cost allocation
methodologies between the NYISO and PJM and between the NYISO and ISO-NE for
Interregional Transmission Projects, which would allow for the use of the same cost allocation
methodology for any Interregional Transmission Project that spans all three regions.10
7 The NYISO is, therefore, in full compliance with the requirement to file an agreement with its neighbors regarding interregional planning as required in Paragraph 475 of Order No. 1000.
8 In this compliance filing, the term “Interregional Transmission Project” means a new
transmission project that will be physically located within two or more neighboring transmission planning regions. As described below, the term is defined as such in the Amended Protocol and Attachment Y of the NYISO OATT.
9 Order No. 714, Electronic Tariff Filings, ¶ 31,276 (2008), and Section 35.1 of the Commission’s regulations, 18 C.F.R. § 35.1(a), allow multiple public utilities that are parties to the same tariff (e.g, a
joint tariff such as the JOA) to designate one of the public utilities as the designated filer of the joint
tariff. The designated filer submits a single tariff filing for inclusion in its database that reflects the joint tariff, along with the requisite certificates of concurrence from the other parties to the joint tariff. NYISO is the designated filing party for the JOA. Therefore, NYISO is submitting the JOA modifications in the instant filing along with PJM’s certificate of concurrence. The designation of the NYISO as the
designated filer for the JOA is for administrative convenience and in no way shall limit PJM’s filing
rights under the Federal Power Act as they relate to the JOA.
10 An Interregional Transmission Project that spans all three regions would have to be selected for cost allocation purposes in all three regions’ regional transmission planning processes to be eligible for interregional cost allocation.
3
As part of this compliance filing, the Joint Filing Parties are submitting additional
revisions to Attachment Y of the OATT to integrate the interregional transmission planning
process and Interregional Transmission Projects into the NYISO’s regional transmission
planning process, to recognize the allocation of costs both between the NYISO and its
neighboring regions and within the NYISO’s region, and to make additional compliance
revisions. The NYISO respectfully submits that, taken together, the proposed modifications to
the Amended Protocol, the Joint Operating Agreement, and Attachment Y of the OATT, meet,
and in parts exceed, full compliance with Order No. 1000’s interregional transmission planning
requirements.
As further explained below, Section III of this compliance filing summarizes Order No.
1000’s interregional coordination and cost allocation requirements, along with the history of the
existing Protocol. Section IV explains the revisions to the Protocol proposed by the NYISO,
PJM, and ISO-NE and how the Amended Protocol satisfies Order No. 1000’s interregional
transmission planning requirements. Section V explains the proposed revisions to the Joint
Operating Agreement regarding the cost allocation methodology for Interregional Transmission
Projects involving the NYISO and PJM and how the methodology satisfies Order No. 1000’s
interregional cost allocation requirements. Section VI explains the proposed revisions to
Attachment Y of the NYISO OATT regarding the cost allocation methodology for Interregional
Transmission Projects involving the NYISO and ISO-NE and how the methodology satisfies
Order No. 1000’s interregional cost allocation requirements. Section VII explains the additional
compliance revisions to Attachment Y of the NYISO OATT proposed by the Joint Filing Parties.
The Joint Filing Parties request that these proposed tariff modifications be made effective
January 1, 2014. The NYISO understands that PJM and ISO-NE are requesting the same
effective date for their proposed Order No. 1000 interregional compliance filings that implicate
the NYISO.
Capitalized terms that are not otherwise defined in this filing letter shall have the
meaning specified in the Amended Protocol, the NYISO-PJM Joint Operating Agreement, and Attachment Y of the NYISO OATT, respectively, and if not defined therein, in the NYISO OATT and Market Administrative and Control Area Services Tariff.
I.COMMUNICATIONS
Communications and correspondence regarding this filing should be directed to:
Robert E. Fernandez, General Counsel
Raymond Stalter, Director of Regulatory Affairs
*Carl F. Patka, Assistant General Counsel
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-6000
Fax: (518) 356-4702
rfernandez@nyiso.com
*Ted J. Murphy
Hunton & Williams LLP 2200 Pennsylvania Ave, NW Washington, DC 20037
Tel: (202) 955-1500
Fax: (202) 778-2201
tmurphy@hunton.com
vcolon@hunton.com
4
rstalter@nyiso.com
cpatka@nyiso.com
Company representatives listed in Attachment I12
*Persons designated to receive service
II.LIST OF DOCUMENTS SUBMITTED
*Michael Messonnier11
Hunton & Williams LLP
Riverfront Plaza, East Tower 951 East Byrd Street
Richmond, VA 23219
Tel: (804) 788-8712
Fax: (804) 343-4646
mmessonnier@hunton.com
*Elias G. Farrah
Winston & Strawn, LLP 1700 K Street, NW
Washington, DC 2006-3817 efarrah@winston.com
*Paul L. Gioia
Whiteman Osterman & Hanna LLP 111 Washington Avenue
Suite 401
Albany, NY 12210
Tel: (518)449-3337
pgioia@woh.com
The NYISO respectfully submits the following documents:
1. This filing letter;
2. A list of the company representatives for the New York Transmission Owners
(“Attachment I”);
3. A blacklined version of the NYISO OATT sections containing the proposed
compliance modifications (“Attachment II”);
4. A clean version of the NYISO OATT sections containing the proposed compliance
modifications (“Attachment III”);
11 Waiver of the Commission’s regulations (18 C.F.R. § 385.203(b)(3) (2012)) is requested to the
extent necessary to permit service on counsel for the NYISO in both Richmond, VA and Washington,
DC.
12 Waiver of the Commission’s regulations (18 C.F.R. § 385.203(b)(3)) is also requested to the extent necessary to permit service on counsel for the NYTOs in both Albany, NY and Washington, DC, as well as the inclusion on the service list of all of the parties listed in Attachment I.
5
5. PJM’s certificate of concurrence for the Joint Operating Agreement (“Attachment
IV”); and
6. A copy of the Amended Protocol being filed with the Commission by ISO-NE on
behalf of ISO-NE, PJM, and the NYISO (“Attachment V”).
III.BACKGROUND
A.The Interregional Coordination and Cost Allocation Requirements of Order
No. 1000
Order No. 1000 imposes requirements for interregional coordination and for the
allocation of the costs of Interregional Transmission Projects agreed to by neighboring regions under interregional coordination procedures.
1. Interregional Coordination
Order No. 1000 requires neighboring planning regions to:
• develop and implement procedures for the joint evaluation and sharing of
information regarding their respective transmission needs and potential interregional solutions;13
• develop and implement procedures14 for identification and joint evaluation15 of
interregional facilities to determine whether those facilities are more efficient or cost-effective than regional solutions;16
• conduct their joint evaluations in the same general timeframe as, rather than
subsequent to, each transmission planning region’s individual consideration of the
proposed project,17 with a meaningful opportunity to review and evaluate through
13 See Order No. 1000 at PP 345, 396.
14 Stakeholders must have the opportunity for input into the development of the interregional coordination procedures and the commonly agreed-to language to be included in the OATTs of the neighboring regions. Id. at P 466.
15 The procedures must include a description of the types of transmission studies conducted to evaluate conditions on neighboring systems for determining whether interregional facilities are more efficient or cost-effective than regional facilities. Id. at P 398. The analyses and determinations must be made transparent to stakeholders. Id. at P 465.
16 Id. at P 398.
17 Developers of interregional transmission projects must first propose their projects in the regional processes of each of the neighboring regions. Id. at P 436.
6
the interregional coordination procedures information developed through the regional planning process and vice versa;18 and
•condition eligibility for interregional cost allocation on the interregional
transmission facility’s being selected in both of the relevant regional transmission
plans.19
Interregional coordination is subject to the following implementation requirements:
•The neighboring regions must exchange and share planning data and information
at least annually;20
• The neighboring regions must develop procedures for identifying and resolving
differences in data, models, assumptions, planning horizons and criteria used to study a proposed transmission project, for purposes of jointly evaluating the proposed facility;21 and
• Each coordinating region must communicate via website (or e-mail list)
information related to interregional transmission coordination procedures,22 as well as information on the progress and construction of portions of interregional transmission facilities within its region.23
18 Id. at PP 436, 439. Order No. 1000-A indicates (at P 519) that it is “through participation in the
regional transmission planning process that stakeholders will have the primary opportunity to participate
fully in the consideration of interregional facilities,” and recognizes that “it may be the case that much of
the interregional transmission coordination would occur through sharing computer modeling results
regarding the effects and benefits of a proposed interregional transmission facility, which may be harder
for a broad community of stakeholders to participate in than would face to face meetings be. If we are
being asked to require there be in-person meetings for interregional transmission coordination with all
stakeholders attending, we would be concerned about requiring a cumbersome process that could
necessitate significant expense and travel time to multiple neighboring regions by the large number of
stakeholders in each region.”
19 Order No. 1000 at P 400.
20 Id. at PP 345, 454-55.
21 Id. at P 437.
22 Id. at P 345.
23 Id. at P 400. The information must be posted in such a way as stakeholders can distinguish between interregional and regional planning information. Id. at P 458.
7
Neighboring planning regions must include the same language in their OATTs describing the procedures used to satisfy the interregional coordination requirements, or may utilize an
interregional planning agreement.24
2. Interregional Cost Allocation
The cost allocation provisions of Order No. 1000 interregional compliance filings must comply with the following principles:
• Interregional Cost Allocation Principle 1: The costs of a new interregional
transmission facility must be allocated to each transmission planning region in
which that transmission facility is located in a manner that is at least roughly
commensurate with the estimated benefits of that transmission facility in each of
the transmission planning regions. In determining the beneficiaries of
interregional transmission facilities, transmission planning regions may consider
benefits including, but not limited to, those associated with maintaining reliability
and sharing reserves, production cost savings and congestion relief, and meeting
Public Policy Requirements.25
• Interregional Cost Allocation Principle 2: A transmission planning region that
receives no benefit from an interregional transmission facility that is located in that region, either at present or in a likely future scenario, must not be
involuntarily allocated any of the costs of that transmission facility.26
• Interregional Cost Allocation Principle 3: If a benefit-cost threshold ratio is used
to determine whether an interregional transmission facility has sufficient net
benefits to qualify for interregional cost allocation, this ratio must not be so large
as to exclude a transmission facility with significant positive net benefits from
cost allocation. The public utility transmission providers located in the
neighboring transmission planning regions may choose to use such a threshold to
account for uncertainty in the calculation of benefits and costs. If adopted, such a
threshold may not include a ratio of benefits to costs that exceeds 1.25 unless the
pair of regions justifies and the Commission approves a higher ratio.27
24 Id. at P 475. The provisions must address how the regional transmission planning process will enable meaningful and timely stakeholder input on consideration of interregional facilities, and how
stakeholders and transmission developers can propose interregional facilities in the regional processes. Order No. 1000-A at P 522. If an interregional agreement is utilized, the regions’ OATTs must
nonetheless “provide enough description for stakeholders to follow how interregional transmission
coordination will be conducted, with links included to the actual agreement where the details can be
found.” Order No. 1000 at P 475, n.372.
25 Id. at P 622 (footnote omitted).
26 Id. at P 637.
27 Id. at P 646 (footnote omitted).
8
•Interregional Cost Allocation Principle 4: Costs allocated for an interregional
transmission facility must be assigned only to transmission planning regions in
which the transmission facility is located. Costs cannot be assigned involuntarily
under this rule to a transmission planning region in which that transmission
facility is not located. However, interregional coordination must identify
consequences for other transmission planning regions, such as upgrades that may
be required in a third transmission planning region and, if the transmission
providers in the regions in which the transmission facility is located agree to bear
costs associated with such upgrades, then the interregional cost allocation method
must include provisions for allocating the costs of such upgrades among the
beneficiaries in the transmission planning regions in which the transmission
facility is located.28
• Interregional Cost Allocation Principle 5: The cost allocation method and data
requirements for determining benefits and identifying beneficiaries for an
interregional transmission facility must be transparent with adequate
documentation to allow a stakeholder to determine how they were applied to a proposed interregional transmission facility.29
• Interregional Cost Allocation Principle 6: The public utility transmission
providers located in neighboring transmission planning regions may choose to use
a different cost allocation method for different types of interregional transmission
facilities, such as transmission facilities needed for reliability, congestion relief,
or to achieve Public Policy Requirements. Each cost allocation method must be
set out clearly and explained in detail in the compliance filing for this rule.30
B.The History of Interregional Coordination in the NYISO/ISO-NE/PJM and
Adjacent Canadian Regions
The NYISO, ISO-NE, PJM and adjacent Canadian regions are already proactively engaged in interregional coordination pursuant to the Protocol. The parties to the Protocol, which was adopted in 2004, are ISO-NE, PJM and NYISO (the “Protocol Parties”), with the technical participation of Ontario’s Independent Electricity System Operator, Hydro-Québec TransÉnergie and New Brunswick Power.
At a high level, the Protocol: (i) serves as the vehicle for exchange of data and
information among these systems; (ii) establishes the committee structure (as discussed further below) for the coordination of inter-area planning activities, and (iii) describes the Northeastern Coordinated System Plan prepared periodically by the Protocol Parties.
28 Id. at P 657 (footnotes omitted).
29 Id. at P 668 (footnote omitted).
30 Id. at P 685 (footnotes omitted).
9
The Protocol’s primary purpose is to contribute to the ongoing reliability and enhanced operational and economic performance of the neighboring systems. To this end, the Protocol requires the parties to coordinate the studies performed in response to interconnection and longterm firm transmission requests that could impact other Protocol Parties’ systems. The Protocol has served as a vehicle for the exchange of data and information among these systems and
established system planning analysis procedures to be utilized by the Protocol Parties. The Protocol has been the platform for the parties’ development of annual Northeastern Coordinated System Plans that, inter alia, integrate the individual system plans.31
The Protocol also has provided a forum for numerous analyses exploring the interregional
impacts of regional and cross-border transmission projects. The Joint Interregional Planning
Committee (“JIPC”) - formed by the NYISO, ISO-NE, and PJM pursuant to the provisions of
the Protocol - coordinates the planning process among the system operators, and the Protocol’s
Inter-area Planning Stakeholder Advisory Committee (“IPSAC”) facilitates participation in
interregional planning by stakeholders from all sectors in the entire northeast region and adjacent
portions of Canada. Among the activities that have been conducted pursuant to the Protocol are:
•the study of transmission upgrades, including improvements in the Plattsburgh,
NY - Burlington, VT area;
•the coordination of interconnection queue studies and transmission improvements
to ensure reliable interregional planning;
•consideration of cross-border transmission security issues, including the
consideration of loss-of-source contingencies in New England;
•studies aimed at investigating generator-deliverability issues and load-
deliverability issues;
• market efficiency analyses, reflecting coordinated models of the three
Commission-jurisdictional ISO/RTOs and neighboring regions; and
• reporting on the effects of environmental regulations, including the integration of
wind and other renewable resources, as well as the effect of demand-side resources on interregional operations and planning.
The Protocol also provides for periodic interregional studies and analyses that may, for example, identify potential transmission bottlenecks and trigger the need for transmission
planning analyses.
Through interregional planning coordination, the NYISO has added significant
interregional transmission ties with PJM, including the Neptune DC cable between Long Island
and New Jersey, the Linden Variable Frequency Transformer connecting Linden, New Jersey
31 See, e.g., 2011 Northeast Coordinated Electric System Plan (May 31, 2012), posted at
http://www.pjm.com/~/media/committees-groups/stakeholder-meetings/ipsac/postings/2011-northeast-
coordinated-system-plan.ashx.
10
and New York City, and the HTP project connecting Bayonne, New Jersey and West 49th Street, Manhattan.
Similarly, New England, together with its neighbors, has successfully added a second 345 kV tie between New Brunswick and Maine and a merchant transmission line between Long
Island and Connecticut, and has enhanced other ties with New York (e.g., replaced the NorwalkNorthport “1385” underwater cable between Connecticut and Long Island and upgraded the
equipment on the Plattsburgh - Vermont tie (PV-20)).
IV. THE AMENDED PROTOCOL AND COMPLIANCE WITH THE
INTERREGIONAL COORDINATION REQUIREMENTS OF ORDER NO. 1000
The Amended Protocol (along with the related revisions to Attachment Y of the NYISO
OATT described in Section VII of this compliance filing) meets, and in many cases exceeds, the
interregional coordination requirements of Order No. 1000. The Amended Protocol is being
filed by ISO-NE contemporaneously on behalf of the Protocol Parties, along with a certificate of
concurrence by the NYISO. A copy of the Amended Protocol is attached to this filing.
A.Interregional Coordination
As explained below, the interregional coordination requirements of Order No. 1000 are
met through: (i) the provisions of the Amended Protocol and (ii) the related modifications to
Attachment Y of the NYISO OATT, as described in Section VII of this compliance filing.
1. Background: the Role of the Amended Protocol
The Amended Protocol - developed through an extensive stakeholder process, as
described below - builds on existing inter-ISO and interregional stakeholder committees and
processes to implement the interregional coordination elements of Order No. 1000.
Representatives of the Protocol Parties (i.e., ISO-NE, NYISO and PJM) comprise the Joint
Interregional Planning Committee (“JIPC”).32 The Interregional Planning Stakeholder Advisory Committee (“IPSAC”) has an open membership from those three regions, including any party with an interest in the coordination of planning.33
The JIPC will, inter alia, undertake and coordinate the activities outlined in Section 7 of the Amended Protocol, which (in high-level summary) include:
• A proactive JIPC review (at least annually) of the regional needs and solutions
identified in regional planning processes of the Protocol Parties in order to
identify, with IPSAC input, whether there are concepts for potential Interregional
32 The JIPC’s structure and responsibilities are described in Section 2.1 of the Amended Protocol.
33 The IPSAC’s structure and responsibilities are described in Section 2.2 of the Amended Protocol.
11
Transmission Projects34 that could meet regional needs more efficiently and costeffectively than separate regional transmission projects;35
• The JIPC’s use (in its review of needs and solutions, and its analysis of
Interregional Transmission Projects) of data and information exchanged and reconciled among the Protocol Parties pursuant to Section 3 of the Amended Protocol;36 and
• Coordination and performance of studies, with IPSAC input, deemed necessary
by the Protocol Parties to allow the effective consideration by the respective
regional stakeholder processes, in the same general timeframe, of an Interregional
Transmission Project proposed in the planning process of more than one region.37
The IPSAC - in connection with Section 7 of the Amended Protocol - will:
• Provide input into the JIPC’s review of regional needs and solutions to identify
concepts for potential Interregional Transmission Projects;38 and
• Review the results of the JIPC’s studies and analyses of a proposed Interregional
Transmission Project, to allow the regional stakeholder processes to benefit from IPSAC input on the proposed project.39
If the Interregional Transmission Project is approved by each region that has a need
addressed by the project, the corresponding existing regional transmission projects will be
displaced, and the costs of the interregional project will be allocated pursuant to the formula
specified in Attachment Y of the NYISO OATT, 40 as described in Section VI of this compliance
filing.
34 Consistent with the terms of Order No. 1000, an “Interregional Transmission Project” is
defined in the Amended Protocol (in fn. 1) as a transmission project that will be physically located within two or more neighboring transmission planning regions, where the regions are those administered by the respective Parties. Other types of projects may be identified pursuant to the periodic interregional
assessments and system expansion planning studies performed by the JIPC with IPSAC input (see
Amended Protocol § 6), but these will be handled on a case-by-case basis and not pursuant to the Order No. 1000-related procedures of Section 7 of the Amended Protocol.
35 See Amended Protocol § 7.1.
36 See Amended Protocol § 7.2.
37 See Amended Protocol § 7.3.
38 See Amended Protocol § 2.2 (first bullet).
39 See Amended Protocol § 7.3.
40 See Amended Protocol § 7.4.
12
2. The Amended Protocol Exceeds the Requirements of Order No. 1000
The Amended Protocol (and related revisions to Attachment Y of the NYISO OATT) exceeds the requirements of Order No. 1000 in a number of respects.
In particular, the Amended Protocol facilitates the consideration of efficient and cost-
effective interregional transmission projects spanning three regions, and not just between two
neighboring regions as required by Order No. 1000. This region encompasses not only the entire
Northeast United States, but areas of the Midwest, Mid-Atlantic and Southern regions. In
addition, Order No. 1000’s requirements are exceeded by the incorporation in the Amended
Protocol of: (i) a standing interregional committee at the ISO/RTO level (i.e., the JIPC) that
undertakes data exchange, the joint study of potential interregional transmission concepts and
projects, and the provision of assistance in each region’s consideration of interregional projects;
and (ii) a standing interregional stakeholder advisory committee (i.e., the IPSAC) that provides
input to the JIPC in its conduct of studies and analyses, as well as input to the regional
consideration of interregional projects. Importantly, both committees have already established a
strong history of cooperative endeavor through the period during which the Protocol has been in
place.
3. Compliance with Specific Interregional Coordination Requirements of
Order No. 1000
a. Specific Obligations for Exchanging and Sharing Planning Data
and Information
Order No. 1000 requires the inclusion of specific obligations for exchanging and sharing planning data and information between neighboring transmission planning regions at least
annually, to assist in joint evaluation of interregional facilities.41
This requirement is implemented in Section 3 of the Amended Protocol. Specifically, Section 3.1(c) of the Amended Protocol provides:
Each Party shall exchange information regarding their respective regional
transmission system plans, including the determination of transmission needs
based upon reliability, public policy and economic considerations as well as the
regional transmission solutions identified to meet those needs. This information
shall be used by the JIPC to identify and evaluate Interregional Transmission
Projects which may have the potential to meet the respective regional
transmission needs in a more efficient or cost-effective manner, as specified in
Section 7 hereof.
Section 3.2 provides that this data and information:
shall be exchanged on an annual basis, recognizing the varying planning cycles of
the respective regions. The dates for the exchange of such data and information
41 Order No. 1000 at PP 8, 345, 454-55.
13
shall be established by the JIPC to correspond to the appropriate point in the
annual planning process timeline of each Party. Reports of planning or operational analyses and evaluations shall be provided in a timely manner.
b. Identification and Resolution of Differences in Data, Models,
Assumptions, Planning Horizons and Criteria
Order No. 1000 requires the development of procedures for the identification and
resolution of differences in data, models, assumptions, planning horizons and criteria used to
study a proposed transmission project, for purposes of jointly evaluating the proposed facility.42
This requirement is addressed in Sections 3.3 and 3.4 of the Amended Protocol. Section
3.3 provides:
To the extent practical, the maintenance and exchange of power system modeling
data shall be implemented through databases. The formats of the databases
exchanged shall be agreed upon by the Parties exchanging the data. Other
information such as geographical system maps and one-line diagrams shall be
provided in an electronic format agreed upon by the Parties exchanging the
information.
Section 3.4 of the Amended Protocol provides:
The Parties shall identify differences in their data, models, assumptions, planning
horizons and criteria to be used in joint evaluation of proposed Interregional
Transmission Projects, and engage in discussions to reconcile those differences, to
the extent possible. In instances where differences cannot be reconciled, other
means, such as the use of scenario analysis, may be used for interregional studies.
Where such differences cannot be harmonized, the Parties shall document the
reasons for those differences for discussion at the IPSAC. If the Parties are
unable, despite these efforts, to reconcile differences, any of the Parties may
initiate use of the dispute resolution procedures of Section 10.1 of the Protocol.43
Pursuant to Section 7.2 of the Amended Protocol, the JIPC utilizes data and information exchanged and reconciled pursuant to Section 3 of the Amended Protocol to assist its review of regional needs and solutions, and to conduct its subsequent analysis of Interregional
Transmission Projects.
42 Order No. 1000 at P 437.
43 Section 10.1 of the Amended Protocol calls for the referral of issues that cannot be resolved by
the JIPC to the Chief Executive Officers (the “CEOs”) of the Parties. In the event that the CEOs do not
reach agreement on any issue referred to them within ten (10) days, then any Party may refer the matter to
a neutral, third-party Dispute Resolution Service, which may include the Commission’s Dispute
Resolution Service, and request a session be convened to initiate non-binding dispute resolution services.
14
c. Description of Types of Studies
Order No. 1000 requires that the neighboring regions describe the types of transmission studies conducted to evaluate conditions on neighboring systems for determining whether
interregional facilities are more efficient or cost-effective than regional facilities.44
This requirement is met by Sections 3.5 and 7.3 of the Amended Protocol. Section 3.5 provides (in relevant part):
The Parties shall, as necessary, prepare and document procedures for the
development of common power system analysis models used to perform the
analyses required to develop the NCSP and to assist with FERC Order 1000-
related efforts specified in Section 7 hereof. Models shall be developed for
necessary interregional system planning analyses such as power flow analyses,
short circuit analyses, stability and production cost analyses…. Changes to
baseline data and updates to the power system analysis models shall be performed
annually to capture all system upgrades and allow analyses to accurately identify
cross border impacts. Coordination of power system analysis models shall rely
upon existing working groups to the maximum extent practical.
Section 7.3 provides:
The JIPC shall coordinate all interregional studies deemed necessary by the
Parties to allow the effective consideration by the regions, in the same general timeframe, of an Interregional Transmission Project. The studies performed by JIPC may include, but are not limited to: power flow, production cost, stability and short-circuit studies.
d. Sharing of Information Regarding Transmission Needs, and
Identification and Evaluation of Interregional Facilities
Order No. 1000 requires the development and implementation of procedures for joint
evaluation and sharing of information regarding the transmission needs of neighboring regions and potential interregional solutions and information, as well as the development and
implementation of procedures for identification and joint evaluation by neighboring regions of interregional facilities to determine whether those facilities are more efficient or cost-effective than regional solutions.45
These requirements are implemented in Section 7 of the Amended Protocol and
Attachment Y of the NYISO OATT, as described in Section VII of this compliance filing.
44 Order No. 1000 at P 398.
45 Order No. 1000 at PP 8, 345, 394, 396, 398-99, 401, 435.
15
Sharing information regarding the needs of the regions, and the identification of potential Interregional Transmission Project concepts that could meet those needs, is accomplished
through the proactive review of the JIPC pursuant to Section 7.1, which provides:
On an annual basis, or at the request of any of the Parties, the JIPC will
proactively review regional needs and solutions identified in regional planning processes of the Parties and identify, with input from the IPSAC, whether there are concepts for potential Interregional Transmission Projects that could - in the reasonable engineering judgment of the JIPC − meet regional needs of more than one region (whether driven by reliability, economic or public policy
requirements) more efficiently and cost-effectively than separate regional
transmission projects. The Parties shall post the results of its review on the
interregional pages of the websites of the regions.
Under Section 7.3, once an Interregional Transmission Project is proposed in the
planning process of more than one region to address system needs identified in the planning process of those respective regions, the Protocol Parties with the identified needs “consider IPSAC input” and “analyze whether the Interregional Transmission Project may be more
efficient and cost-effective than the separate regional transmission projects.” Section 7.3 also provides that the JIPC will coordinate, and present to the IPSAC for its input, all interregional studies deemed necessary by the Protocol Parties to allow the effective consideration by the regions of an Interregional Transmission Project.
Section 7.4 requires the Protocol Parties to consider the proposed Interregional
Transmission Project in their respective transmission planning processes “in the same general timeframe.”
e. Transparent Analyses
Order No. 1000 requires transmission providers to make transparent the analyses
undertaken and determinations reached by neighboring regions in identifying and evaluating interregional facilities.46
This requirement is fulfilled, inter alia, in Sections 7.1 and 7.3 of the Amended Protocol.
As discussed above, the results of the JIPC’s proactive review of regional needs and solutions,
and identification of potential interregional project concepts, are posted on the interregional
planning pages of each region’s website. Pursuant to Section 7.3, the results of each region’s
analysis of whether an Interregional Transmission Project is more efficient and cost-effective
than separate regional projects are posted on the interregional pages of the websites of the
regions.
46 Order No. 1000 at P 465.
16
f. Developer Proposals Made Initially in Regional Planning
Processes
Order No. 1000 requires the developer of an interregional transmission project to first propose its project in the regional processes of each of the neighboring regions in which the project is to be physically located.47
This requirement is met by Section 7.3 of the Amended Protocol, which indicates that the analysis by the Parties (through the JIPC) of an Interregional Transmission Project is premised on the project having been “proposed in more than one region to address system needs identified in the planning process of those respective regions….”
g. Communication of Information
Order No. 1000 requires the neighboring regions to communicate information (through websites or e-mail lists) related to interregional transmission coordination procedures, including the provision of information on the progress and construction of portions of interregional
transmission facilities within its region.48
This requirement is met through the provisions of Sections 2.1, 7.1 and 7.3 of the
Amended Protocol. Section 2.1 (in the second bullet) provides that the JIPC members (i.e., the NYISO, PJM and ISO-NE) are charged with the responsibility for:
Communicating information related to the coordinated planning process,
including identification and approval of a Party’s materials produced under this
Protocol to be posted on each other Party’s website and maintenance of required
e-mail lists; Information relating to interregional coordination and studies
conducted in accordance with this Protocol shall be clearly identified and posted
on each Party’s website subject to confidentiality and Critical Energy
Infrastructure Information (“CEII”) restrictions of each respective region….
In a similar vein, Section 7.1 provides that the Protocol Parties will post the results of the JIPC’s review of regional needs and solutions, and its identification of concepts for potential Interregional Transmission Projects that could meet the regional needs of more than one region, “on the interregional pages of the websites of the regions.” Further, Section 7.3 requires, as part of the analysis and consideration of these projects, that the results of their analysis be posted “on the interregional pages of the websites of the regions.”
Order No. 1000 also requires that information be posted on the transmission provider’s
website “in such a way that stakeholders are able to distinguish between interregional
transmission coordination and information related to regional transmission planning.”49
47 Id. at ¶ 436.
48 Order No. 1000 at PP 345, 400, 458.
49 Order No. 1000 at P 458.
17
This requirement is met through the provisions of Sections 7.1 and 7.3 of the Amended
Protocol. Section 7.1 states that the results of the JIPC’s review of regional needs and solutions
to identify concepts for potential Interregional Transmission Projects will be posted “on the
interregional pages of the websites of the regions.” (emphasis added). Section 7.3 states that the
results of the Protocol Parties’ analysis of “whether an Interregional Transmission Project may
be more efficient and cost-effective than the separate regional transmission projects” will be
posted “on the interregional pages of websites of the regions.” (emphasis added).
h. Implementation in OATT/Interregional Agreement
Order No. 1000 permits the interregional coordination procedures to be contained in an interregional agreement, with a summary of the agreement included in the regional OATT.50
This is the approach taken by the NYISO. The Amended Protocol contains the coordination
procedures, and a summary of the Amended Protocol’s interregional coordination provisions is contained in Section 31.1.6 of Attachment Y of the NYISO OATT, as described in Section VII of this compliance filing.
i. Stakeholder Participation in Development of Interregional
Coordination Procedures, Interregional Cost Allocation Methodology, and OATT Language
Order No. 1000 requires that stakeholders be afforded the opportunity for input into
development of interregional coordination procedures and the commonly agreed-to language to be included in OATT.51
ISO-NE, NYISO and PJM sought stakeholder input on the Amended Protocol and the interregional cost allocation through meetings of the IPSAC held on: March 30, 2012; June 22, 2012; August 27, 2012; January 28, 2013; February 26, 2013; March 20, 2013; April 3, 2013; April 24, 2013; and June 20, 2013.
The NYISO’s stakeholder reviewed the JIPC/IPSAC process and the Amended Protocol, NYISO-PJM JOA and Attachment Y amendments at meetings of the Interregional Planning Task Force on February 27, 2012, April 23, 2012, November 29, 2012, December 20, 2013, January 9, 2013, January 23, 2013, February 7, 2013, February 21, 2013, March 6, 2013, March 21, 2013, April 5, 2013, April 17, 2013, May 2, 2013, and June 14, 2013.
j. Connection between Interregional Coordination and Cost
Allocation
Order No. 1000 conditions the eligibility of an interregional transmission project for
interregional cost allocation on the selection of the project in both of the relevant regional
transmission plans in which the interregional transmission project is physically located.52
50 Order No. 1000 at PP 346, 475, Order No. 1000-A at P 522.
51 Order No. 1000 at P 466.
18
This condition is reflected in Section 7.4 of the Amended Protocol. Section 7.4 provides:
If the proposed Interregional Transmission Project is approved in each region by
including it in the respective regional transmission plans in accordance with
procedures for each Party’s reliability, economic and/or public policy
transmission planning processes, the corresponding existing regional transmission
projects shall be displaced, and the costs of the Interregional Transmission
Project shall be allocated as described in Section 9 hereof. (emphasis added)
V.THE JOINT OPERATING AGREEMENT AND COMPLIANCE WITH THE
INTERREGIONAL COST ALLOCATION REQUIREMENTS OF ORDER NO.
1000
The revisions to the Joint Operating Agreement53 satisfy the interregional cost allocation
requirements of Order No. 1000 with regard to the allocation of costs of Interregional
Transmission Projects involving the NYISO and PJM. The revisions to the Joint Operating
Agreement are being filed by the NYISO on behalf of the NYISO and PJM. The NYISO is also
submitting with this filing PJM’s certificate of concurrence for the JOA on its behalf.
A. Interregional Cost Allocation Methodology
Section 9 of the Amended Protocol provides a roadmap to the applicable cost allocation
methodologies for: (i) Interregional Transmission Projects identified under Section 7 of the
Amended Protocol that, as described above, are identified and evaluated pursuant to Order No.
1000-related procedures, and (ii) other transmission projects identified under Section 6 of the
Amended Protocol.54 The cost allocation methodology for such projects involving the NYISO
and PJM is determined in accordance with the Joint Operating Agreement between NYISO and
PJM, as described in this Section V. The cost allocation methodology for such projects under the
Amended Protocol involving the NYISO and ISO-NE is determined in accordance with a
substantially identical methodology to the methodology used by the NYISO and PJM as set forth
in Attachment Y of the NYISO OATT and the ISO-NE tariff, as described in Section VI of this
compliance filing.
B. The Cost Allocation Requirements of Order No. 1000
Order No. 1000 requires that a public utility transmission provider:
have, together with the public utility transmission providers in its own
transmission planning region and a neighboring transmission planning region, a
common method or methods for allocating the costs of a new interregional
transmission facility among the beneficiaries of that transmission facility in the
52 Order No. 1000 at P 400.
53 The Joint Operating Agreement is located in Attachment CC of the NYISO OATT.
54 See footnote 34 above.
19
two neighboring transmission planning regions in which the transmission facility is located.55
Within an ISO/RTO region, the ISO/RTO is responsible for developing the interregional cost
allocation methodology with its neighbors on behalf of its public utility transmission owning
members56 and must file such methodology in its OATT.57 The Commission provides the public utility transmission provider with the flexibility to develop its own cost allocation
methodology.58 As described above, the interregional cost allocation methodology must satisfy six cost allocation principles adopted in Order No. 1000: (1) costs must be allocated in a way
that is roughly commensurate with benefits; (2) there must be no involuntary allocation of costs to non-beneficiaries; (3) a benefit to cost threshold ratio cannot exceed 1.25; (4) costs must be
allocated solely within the transmission planning region or pair of regions unless those outside
the region or pair of regions voluntarily assume costs; (5) there must be a transparent method for determining benefits and identifying beneficiaries; and (6) there may be different methods for
different types of transmission facilities.59 An Interregional Transmission Project must be
selected in both of the relevant regional transmission planning processes for purposes of cost
allocation to be eligible for interregional cost allocation.60
C.Cost Allocation for Interregional Transmission Projects Located in NYISO
and PJM
The Joint Operating Agreement was executed by PJM and NYISO in May 2007 and filed
separately by each entity in Dockets Nos. ER07-1369-000 and ER07-1376-000 respectively.61
The Commission accepted these filings by letter orders dated Nov. 2, 2007.62 The NYISO and
PJM propose to revise the Joint Operating Agreement by adding new sections 35.10.2 through
55 Order No. 1000 at P 578.
56 Order No. 1000 at P 584.
57 Order No. 1000 at P 578.
58 Order No. 1000 at P 580.
59 Order No. 1000 at PP 578, 603; Order No. 1000-A at P 524. These six interregional cost
allocation principles only apply to “a new transmission facility that is located in two neighboring
transmission planning regions and accounted for in the interregional transmission coordination procedure in an OATT.” Order No. 1000 at P 603.
60 Order No. 1000 at PP 436 and 582.
61 PJM Interconnection, L.L.C., PJM/NYISO Joint Operating Agreement, Docket No. ER07-
1369-000 (filed Sept. 13, 2007); New York Independent Sys. Operator, Inc., Joint Operating Agreement with PJM Interconnection, L.L.C., Docket No. ER-07-1376-000 (filed Sept. 14, 2007).
62 PJM Interconnection, L.L.C., Docket No. ER07-1369-000 (letter order issued Nov. 2, 2007);
New York Independent Sys. Operator, Inc., Docket No. ER07-1376-000 (letter order issued Nov. 2,
2007).
20
35.10.6 to establish the method for allocating between their regions the costs of Interregional
Transmission Projects - as defined in the Amended Protocol63 - that are evaluated under the
Amended Protocol and are selected by both PJM and the NYISO in their respective regional
transmission plans for purposes of cost allocation.64 Such cost allocation only applies to an
Interregional Transmission Project that has been selected in both PJM’s and the NYISO’s
regional transmission plans for purposes of cost allocation and is planned for construction in both regions.65
The NYISO and PJM propose to allocate the costs between their regions using an avoided cost methodology.66 Section 35.10.2(b) provides:
The share of the costs of an Interregional Transmission Project allocated to a
region will be determined by the ratio of the present value of the estimated costs of such region’s displaced regional transmission project or projects to the total of the present values of the estimated costs of the displaced regional transmission projects in the regions that have selected the Interregional Transmission Project in their regional transmission plans.67
For purposes of performing this analysis:
• the present value of the estimated costs of each region’s displaced regional transmission
project will be based on a common base date that will be the beginning of the calendar
month of the cost allocation analysis for the subject Interregional Transmission Project
(the “Base Date”);68
• the estimated cost of the displaced regional transmission projects shall specify the year’s
dollars in which those estimates are provided;69
63 As defined in the Amended Protocol, “Interregional Transmission Project” shall mean “a
transmission project that will be located within two or more neighboring transmission planning regions.
The transmission planning regions referred to herein are those administered by the respective Parties.”
64 Proposed JOA Section 35.10.2.
65 Proposed JOA Section 35.10.2(a). The cost allocation requirements in Section 35.10 of the
Joint Operating Agreement do not preclude the development of an Interregional Transmission Project that is funded solely by a merchant transmission developer or by an individual transmission owner. Proposed JOA Section 35.10.5.
66 Though Con Edison, O&R, NYPA, and LIPA support this compliance filing, they disagree
with the application of the avoided cost methodology to an interregional transmission project that costs
more than the cost of the displaced regional projects and reserve the right to file a protest to this aspect of
the filing.
67 Proposed JOA Section 35.10.2(b).
68 Proposed JOA Section 35.10.2(c).
69 Proposed JOA Section 35.10.2(d).
21
• the present value analysis for all displaced regional transmission projects shall use a
common discount rate. PJM and the NYISO, in consultation with their respective
transmission owners, and the NYISO in consultation with other stakeholders, will agree on the discount rate to be used for the present value analysis.70
• PJM and the NYISO, in consultation with the transmission owners in their respective
regions, and NYISO in consultation with other stakeholders, will also review and
determine that the cost estimates of the displaced regional transmission projects have
been determined in a comparable manner prior to applying this cost allocation.71
An example illustrating the application of this cost allocation methodology is set forth in Section
35.10.2(j) of the JOA and Section V.E of this compliance filing.
The cost allocation methodology expressly excludes allocating the costs of Interregional Transmission Projects to regions that do not have an identified regional need for the project. Section 35.10.2(g) provides that:
No cost shall be allocated to a region that has not selected the Interregional Transmission Project in its regional transmission plan.
Section 35.10.2(h) also provides that:
When a portion of an Interregional Transmission Project evaluated under the
Protocol is included by a region (Region 1) in its regional transmission plan but
there is no regional need or displaced regional transmission project in Region 1
and the neighboring region (Region 2) has a regional need or displaced regional
project for the Interregional Transmission Project and selects the Interregional
Transmission Project in its regional transmission plan, all of the costs of the
Interregional Transmission Project shall be allocated to Region 2 in accordance
with the methodology in this Section 35.10.2 and none of the costs shall be
allocated to Region 1.
Moreover, the JOA provides that NYISO’s and PJM’s regions do not agree to be
responsible to each other for impacts of interregional transmission facilities, except as
provided in the JOA itself, or for compensating a third region for consequences
associated with regional and interregional transmission facilities. Section 35.10.6
provides that:
Except as provided herein in sections 35.10.2 and 35.10.3 of this Agreement, or
where cost responsibility is expressly assumed by NYISO or PJM in other
documents, agreements or tariffs on file with FERC, neither the NYISO region
70 Proposed JOA Section 35.10.2(e).
71 Proposed JOA Section 35.10.2(f).
22
nor the PJM region shall be responsible for compensating another region or each
other for required upgrades or for any other consequences in another planning
region associated with regional or interregional transmission facilities, including
but not limited to, transmission projects identified pursuant to Section 6 of the
Protocol and Interregional Transmission Projects identified pursuant to Section 7
of the Protocol.
The above cost allocation methodology is the exclusive means to allocate the costs of
Interregional Transmission Projects that will be located in, and have been approved by both, the
NYISO’s and PJM’s regions with the following exception. The NYISO, PJM, and the
transmission owners and transmission developers in their regions may enter into a separate
agreement to allocate the costs of an Interregional Transmission Project or a transmission project
that is identified under Section 6 of the Amended Protocol in a manner other than described
above.72 Such agreement shall: (i) be filed with and accepted by the Commission, (ii) have been
filed consistent with each of the party’s filing rights, described in Section V.F of this compliance
filing, and any stakeholder process required prior to the exercise of these filing rights, and (iii)
apply to determine the share of the costs of an Interregional Transmission Project or such other
transmission project that is allocated to the NYISO region and the PJM region.73
Costs allocated to the NYISO and PJM’s regions under Section 35.10.2 are then further allocated by the NYISO and PJM under their applicable tariffs and agreements on file with the Commission.74 The NYISO proposes to allocate its regional share of the costs of an
Interregional Transmission Project in accordance with the provisions for reliability, economic or public policy transmission projects, as applicable and as provided under Attachment Y of the NYISO OATT. Section VII.C of this compliance filing further explains the intra-regional
allocation of Interregional Transmission Project costs.
D. The Cost Allocation Methodology Satisfies Order No. 1000’s Directives on
Cost Allocation for Interregional Transmission Projects, Including the Interregional Cost Allocation Principles
The NYISO’s and PJM’s cost allocation methodology satisfies the cost allocation
requirements set forth in Order No. 1000. The primary purpose of the agreed-upon interregional
cost allocation methodology is to provide a means for the NYISO and PJM to allocate an
Interregional Transmission Project's costs between the two regions where the project has been
approved by both regions. In general, the proposed methodology allocates the costs according to
the benefits for both regions. As described above, the proposal calculates the benefits of an
Interregional Transmission Project as the avoided costs due to the project replacing less efficient
or higher cost regionally-planned transmission projects with the more efficient or cost effective
proposed Interregional Transmission Project that addresses long-term needs that would have
72 Proposed JOA Section 35.10.3.
73 Proposed JOA Section 35.10.3.
74 Proposed JOA Section 35.10.2(i).
23
been addressed by the displaced projects. The proposed Interregional Transmission Project's
costs would be allocated between the regions on a pro rata basis based upon the ratio of each
region's avoided costs to the total avoided costs for both regions in which the facility would be located. Importantly, given the iterative nature of transmission plan and the significant lead time prior to the need for a party to commit to a significant regional project or an Interregional
Transmission Project, the proposal provides that the allocation will be based upon the present
values of the displaced projects as of a common base date keyed to the cost allocation analysis of the proposed Interregional Transmission Project.
Order No. 1000 requires that the cost allocation methodology satisfy six interregional cost allocation principles. As explained in the following subsections, the NYISO’s and PJM’s proposed cost allocation methodology set forth in Section 35.10 of the Joint Operating
Agreement complies with these principles.
1. Interregional Principle #1
Interregional Principle #1 provides that:
The costs of a new interregional transmission facility must be allocated to each
transmission planning region in which that transmission facility is located in a manner
that is at least roughly commensurate with the estimated benefits of that transmission
facility in each of the transmission planning regions. In determining the beneficiaries
of interregional transmission facilities, transmission planning regions may consider
benefits including, but not limited to, those associated with maintaining reliability and
sharing reserves, production cost savings and congestion relief, and meeting Public
Policy Requirements.75
The agreed-upon methodology would allocate the costs of Interregional Transmission
Projects in a manner that is roughly commensurate with the estimated benefits to each region,76
because the costs are allocated in proportion to the quantifiable benefits of avoided/displaced
transmission. In the context of cost allocation within a planning region, the Commission has
found that a cost allocation that includes avoided costs “could be a reasonable approach for
allocating costs in a manner that is roughly commensurate with benefits.”77 The Commission
specifically approved an avoided cost approach for allocating the cost of reliability projects
within a region, finding that it “reasonably captures the benefits of such projects.”78
An avoided cost approach to interregional cost allocation is particularly appropriate in
light of the purpose of interregional coordination under Order No. 1000. As the Commission
75 Order No. 1000 at P 622 (footnote omitted).
76 Order No. 1000 at P 622.
77Avista Corp., 143 FERC ¶ 61,255 at P 300 (2013), citing S.C. Elec. & Gas Co., 143 FERC ¶ 61,058 at P 232 (2013); Pub. Serv. Co. of Colorado, 142 FERC ¶ 61,206 at P 312 (2013).
78Pub. Serv. Co. of Colorado, 142 FERC ¶ 61,206 at P 312.
24
explained in Order No. 1000-A, its interregional coordination reforms do not require the
establishment of interregional planning processes to develop integrated interregional plans, but rather call upon public utility transmission providers to consider “whether the local and regional transmission planning processes result in transmission plans that meet local and regional
transmission needs more efficiently and cost-effectively, after considering opportunities for
collaborating with public utility transmission providers in neighboring transmission planning
regions.”79 Since the purpose of interregional coordination is thus to determine whether an
interregional project might beneficially displace one or more projects included in regional or
local plans, the cost of the displaced projects represents a reasonable measure of the benefits of the interregional project for cost allocation purposes.
The NYISO and PJM recognize that the Commission has held that the sole use of an
avoided cost methodology does not comply with the principles applicable to regional cost
allocation because it does not account for economic or public policy benefits.80 These findings,
however, are not determinative or relevant with respect to interregional cost allocation. Order
No. 1000 does not require the consideration of public policy or economic benefits at the
interregional level.81 Accordingly, the Commission’s concerns about the sole use of an avoided
cost methodology for regional cost allocation are inapplicable at the interregional level. The
regional planning process and regional cost allocation methodologies in NYISO and in PJM
address reliability and market efficiency needs and public policy considerations in a manner the
Commission has found to substantially comply with the requirements of Order No. 1000.82 Order
No. 1000 expressly holds that such considerations need not be repeated at the interregional level.
Measuring the benefits of Interregional Transmission Projects for cost allocation
purposes through the avoided cost approach is also appropriate in light of the ability of each
region to decline to select an Interregional Transmission Project in its regional plan for cost
allocation purposes if the project is not cost-effective for that region.83 The benefits of an
79 Order No. 1000-A at P 511. See also No. 1000 at P 368, where the Commission explained that it was requiring further reforms in interregional coordination because, in the absence of coordination between regions, transmission providers “may be unable to identify more efficient and cost-effective solutions to the individual needs identified in their respective regional and local planning processes,
potentially including interregional transmission facilities.”
80See S.C. Elec. & Gas Co., 143 FERC ¶ 61,058 at P 226.
81 Order No. 1000 at P 401 (footnotes omitted) (Order No. 1000 does not “require[] . . .
consideration of transmission needs driven by Public Policy Requirements, or the evaluation of economic considerations” in interregional coordination).
82 PJM Interconnection, L.L.C., 142 FERC ¶ 61,214 (2013); New York Independent System
Operator, Inc., 143 FERC ¶ 61,059 (2013). The NYISO will make its supplemental compliance filing in response to this order in Docket No. ER13-102-000 on August 16, 2013.
83 See Order No. 1000-A at P 512. This ability is a corollary of the requirement that an
interregional project be selected for interregional cost allocation in the regional plans of the affected regions. Id. at P 509.
25
Interregional Transmission Project are essentially ascertained in the underlying regional planning
process, because the regional project that is being displaced will already have been found
sufficiently beneficial to be included in the regional system plan. The default allocation
methodology properly calculates the benefits of an interregional project as the avoided costs
associated with the project, e.g., the cost savings achieved by replacing the regionally-planned
transmission projects with the more efficient or cost-effective proposed Interregional
Transmission Project that addresses long-term needs that would have been addressed by the
displaced projects - already found to be beneficial, efficient and cost-effective by the regions.
Allocating an Interregional Transmission Project’s cost in proportion to the costs of the regional
project or projects that it would displace takes into account the essentially voluntary nature of
interregional coordination and results in a close “alignment of transmission planning and cost
allocation,” which was a “central underpinning” of the Commission’s interregional coordination
reforms.84
In summary, for the most part, each region benefits from an Interregional Transmission
Project to the extent that it avoids the costs of regional transmission projects that would
otherwise be needed to meet a regional need. The NYISO and PJM both benefit by development
of an Interregional Transmission Project that each region determines is superior based on its cost
and/or efficiency in meeting a need compared to regional projects. By quantifying the benefit to
each region from avoiding regional projects, the ratio of the regional avoided costs allocates
costs between the regions in a manner that is roughly commensurate to the benefits to each
region. Regions may decide to build an Interregional Transmission Project that is more
expensive than regional transmission projects because they are more efficient in meeting the
identified need. Even if an Interregional Transmission Project costs more than the sum of the
regional projects it displaces, the ratio of regional avoided costs nevertheless provides an
accurate proportion of the benefits to each region based on the relative comparison of the
regional project costs in the avoided cost ratio. Moreover, in the event the default cost allocation
does not fully realize the benefits of a project, the regions may negotiate an alternative cost
allocation methodology consistent with Section 35.10.3 of the Joint Operating Agreement.
2. Interregional Principle #2
Interregional Principle #2 provides that:
A transmission planning region that receives no benefit from an interregional
transmission facility that is located in that region, either at present or in a likely future
scenario, must not be involuntarily allocated any of the costs of that transmission
facility.85
The NYISO’s and PJM’s cost allocation methodology satisfies this principle. As
described above, the NYISO’s and PJM’s cost allocation methodology does not allocate the costs
of an Interregional Transmission Project to a region if it has not been selected in the region’s
84Order No. 1000 at P 582.
85 Order No. 1000 at P 637.
26
transmission plan.86 In addition, even if a portion of the Interregional Transmission Project is included in the region’s transmission plan, the proposed methodology does not allocate costs to the region if that region does not have an identified regional need for the project or if there is no displaced regional transmission project.87
3. Interregional Principle #3
Interregional Principle #3 provides that:
If a benefit-cost threshold ratio is used to determine whether an interregional
transmission facility has sufficient net benefits to qualify for interregional cost
allocation, this ratio must not be so large as to exclude a transmission facility with
significant positive net benefits from cost allocation. The public utility transmission
providers located in the neighboring transmission planning regions may choose to use
such a threshold to account for uncertainty in the calculation of benefits and costs. If
adopted, such a threshold may not include a ratio of benefits to costs that exceeds
1.25 unless the pair of regions justifies and the Commission approves a higher ratio.88
The agreed-upon methodology also satisfies this principle because it does not establish a benefit/cost threshold for interregional cost allocation.
4. Interregional Principle #4
Interregional Principle #4 provides that:
Costs allocated for an interregional transmission facility must be assigned only to
transmission planning regions in which the transmission facility is located. Costs
cannot be assigned involuntarily under this rule to a transmission planning region in
which that transmission facility is not located. However, interregional coordination
must identify consequences for other transmission planning regions, such as upgrades
that may be required in a third transmission planning region and, if the transmission
providers in the regions in which the transmission facility is located agree to bear
costs associated with such upgrades, then the interregional cost allocation method
must include provisions for allocating the costs of such upgrades among the
beneficiaries in the transmission planning regions in which the transmission facility is
located.89
As described above, the NYISO’s and PJM’s cost allocation methodology does not
allocate the costs of an Interregional Transmission Project to a region if it has not been selected
86 Proposed JOA Section 35.10.2(g).
87 Proposed JOA Section 35.10.2(h).
88 Order No. 1000 at P 646 (footnote omitted).
89 Order No. 1000 at P 657 (footnotes omitted).
27
in the region’s transmission plan.90 In addition, as described in Section VII of this compliance
filing, the NYISO has revised Attachment Y of its OATT to provide for identifying the
consequences for transmission projects on neighboring regions. In addition, as described above,
the NYISO and PJM have specified that they would not agree to be responsible for sharing of
costs of upgrades that might be required in a region in which an Interregional Transmission
Project is not located. Accordingly, the NYISO’s and PJM’s cost allocation methodology
satisfies this principle.91
5. Interregional Principle #5
Interregional Principle #5 provides that:
The cost allocation method and data requirements for determining benefits and
identifying beneficiaries for an interregional transmission facility must be transparent with adequate documentation to allow a stakeholder to determine how they were applied to a proposed interregional transmission facility.92
The cost allocation methodology described above is set forth in detail in Section 35.10.2
of the Joint Operating Agreement. The entire interregional transmission planning process is
conducted under the Amended Protocol in concert with the stakeholders of the NYISO, PJM, and
ISO-NE. As described above in Section IV of this compliance filing, the Amended Protocol
provides for transparency, input, and review by stakeholders through the IPSAC. Relevant
information is also posted on the websites of the NYISO, PJM, and ISO-NE. In addition, as
described in Sections VI and VII of this compliance filing, the NYISO has included a clear
description of the interregional transmission planning process and interregional cost allocation
methodology in Attachment Y of its OATT. The NYISO has also clarified in Attachment Y that
any interested party can participate in the NYISO’s Interregional Planning Task Force (“IPTF”)
to participate in the interregional transmission planning process. Moreover, NYISO stakeholders
participate in the regional planning processes that underlie the selection of an Interregional
Transmission Project for cost allocation purposes. Accordingly, the NYISO’s and PJM’s cost
allocation methodology satisfies this principle.
6. Interregional Principle #6
Interregional Principle #6 provides that:
The public utility transmission providers located in neighboring transmission
planning regions may choose to use a different cost allocation method for different
types of interregional transmission facilities, such as transmission facilities needed for
reliability, congestion relief, or to achieve Public Policy Requirements. Each cost
90 Proposed JOA Section 35.10.2(g).
91 Proposed JOA Section 35.10.6.
92 Order No. 1000 at P 668 (footnote omitted).
28
allocation method must be set out clearly and explained in detail in the compliance filing for this rule.93
The NYISO’s and PJM’s cost allocation methodology described above and set forth in
Section 35.10.2 of the Joint Operating Agreement applies to all eligible Interregional
Transmission Projects involving the NYISO and PJM, regardless of the purpose that the
transmission facility will serve. In addition, as described in Section VII of this compliance
filing, the NYISO region’s share of the costs of an Interregional Transmission Project are further
allocated to its customers based on the need that the project resolves (reliability, economic,
public policy) in line with a regional cost allocation process set forth in Attachment Y of the
NYISO OATT.
E. Example of the Application of the Cost Allocation Methodology
The following example illustrates the cost allocation methodology for an Interregional Transmission Project as described in Section V.C of this compliance filing.94
A cost allocation analysis of the costs of Interregional Transmission Project Z is to be
performed during a given month establishing the beginning of that month as the Base Date.
• Region A has identified a reliability need in its region and has selected a transmission
project (Project X) as the preferred solution in its regional plan. The estimated cost of Project X is: Cost (X), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (X) is: N(X).
• Region B has identified a reliability need in its region and has selected a transmission
project (Project Y) as the preferred solution in its Regional Plan. The estimated cost of Project Y is: Cost (Y), provided in a given year’s dollars. The number of years from the Base Date to the year associated with the cost estimate of Project (Y) is: N(Y).
• Regions A and B, through the interregional planning process have determined that an
Interregional Transmission Project (Project Z) will address the reliability needs in both
regions more efficiently and cost-effectively than the separate regional projects. The
estimated cost of Project Z is: Cost (Z). Regions A and B have each determined that
Interregional Transmission Project Z is the preferred solution to their reliability needs and
have adopted that Interregional Transmission Project in their respective regional plans in
lieu of Projects X and Y, respectively. If Regions A and B have agreed to bear the costs
of upgrades in other affected transmission planning regions, these costs will be
considered part of Cost (Z).
• The discount rate used for all displaced regional transmission projects is: D
93 Order No. 1000 at P 685 (footnotes omitted).
94 The example has been included in Section 35.10.2(j) of the Joint Operating Agreement.
29
• Based on the foregoing assumptions, the following formulas will be used:
Present Value of Cost (X) = PV Cost (X) = Cost (X) / (1+D)N(X)
Present Value of Cost (Y) = PV Cost (Y) = Cost (Y) / (1+D)N(Y)
Cost Allocation to Region A = Cost (Z) x PV Cost (X)/[PV Cost (X) + PV Cost (Y)]
Cost Allocation to Region B = Cost (Z) x PV Cost (Y)/[PV Cost (X) + PV Cost (Y)] • Applying those formulas, if:
Cost (X) = $60 Million and N(X) = 8.25 years Cost (Y) = $40 Million and N(Y) = 4.50 years Cost (Z) = $80 Million
D = 7.5% per year
Then:
PV Cost (X) = 60/(1+0.075)8.25 = 33.039 Million
PV Cost (Y) = 40/(1+0.075)4.50 = 28.888 Million
Cost Allocation to Region A = $80 x 33.039/(33.039 + 28.888) = $42.681 Million
Cost Allocation to Region B = $80 x 28.888/(33.039 + 28.888) = $37.319 Million
F. Clarification of Filing Rights Regarding Cost Allocation for Interregional
Transmission Projects in the NYISO and PJM
The NYISO and PJM acknowledge in Section 9 of the Amended Protocol that the cost
allocation methodology set forth in the Joint Operating Agreement shall not be changed without
the mutual consent of the holders of the Section 205 rights in the PJM and NYISO regions,
including for the NYISO the Long Island Power Authority and the New York Power Authority.
The NYISO and PJM proposed to revise Section 35.10 to reserve their filing rights and those of the NYTOs and the PJM transmission owners with regard to the cost allocation
methodology for Interregional Transmission Projects. These provisions were written with the input of the transmission owners of both regions, and reasonably maintain their filing rights in accordance with existing agreements and tariff provisions. Specifically, the NYISO and PJM propose to indicate in Section 35.10.4 that:
• Nothing in Sections 35.10.2 through 35.10.6 of the Joint Operating Agreement or in the
Amended Protocol will convey, expand, limit or otherwise alter any rights of the NYISO or
PJM, transmission owners, transmission developers, other market participants, or other
30
entities in PJM or NYISO to submit filings under Section 205 of the Federal Power Act regarding cost allocation or any other matter.
• The NYISO and PJM have been authorized by entities that have cost allocation rights for
their respective regions, but are not parties to the Joint Operating Agreement, to enter into and file the cost allocation provisions set forth in Sections 35.10.2 through 35.10.6 of the Joint Operating Agreement.
• Such cost allocation provisions shall not be modified without the mutual consent of the
holders of Section 205 rights and the Long Island Power Authority and the New York Power
Authority with respect to interregional cost allocation in the PJM region and the NYISO
region.
• With respect to PJM, the provisions in Sections 35.10.2 through 35.10.6 have been approved
by the PJM Transmission Owners acting through the Consolidated Transmission Owners
Agreement (“CTOA”) pursuant to Section 9.1 of the PJM Open Access Transmission Tariff
(“PJM Tariff”) and Article 7 of the CTOA, and any amendment to the provisions of Sections
35.10.2 through 35.10.6 or any other provision of the Joint Operating Agreement allocating the costs of Interregional Transmission Projects, shall require approval by the PJM
Transmission Owners acting through the CTOA pursuant to Section 9.1 of the PJM Tariff and Article 7 of the CTOA and shall be filed pursuant Section 205 of the Federal Power Act in accordance with the PJM Tariff and Article 7 of the CTOA.
• Nothing in Sections 35.10.2 through 35.10.6 of the Joint Operating Agreement shall limit or
alter the rights of the PJM Transmission Owners set forth in the PJM Tariff and CTOA to submit filings under Section 205 of the Federal Power Act.
G.Coordination Between the NYISO and PJM Regarding the Impacts of
Projects Located Entirely in One Region
In addition to the interregional cost allocation methodology, the NYISO and PJM propose to insert a new Section 35.10.7 to the Joint Operating Agreement to provide for an enhanced coordination process between both regions with regard to the impact of projects located entirely in one of the regions.
Under the proposed revisions, the NYISO and PJM will share with each other their
baseline reliability analyses.95 Each region will identify any potential violations to its system
resulting from a proposed reliability transmission project located entirely in the other region.96
The NYISO and PJM will then discuss identified impacts and coordinate any studies required to
analyze such impacts.97 Based on the results of the studies, the NYISO and PJM will discuss
with each other potential alternative solutions and the mitigation of impacts on the potentially
95 Proposed JOA Section 35.10.7.1.
96 Proposed JOA Section 35.10.7.2.
97 Proposed JOA Section 35.10.7.3.
31
impacted region’s systems and will present agreed-upon mitigation to stakeholders in the region
with the proposed reliability transmission project as part of the solution to the identified
reliability need.98 Other than any agreed-upon mitigation or operational alternatives, the NYISO
and PJM are only responsible for the costs of addressing impacts to their own respective
systems.99
Any disputes arising under this Section 35.10.7 will be addressed under the existing
dispute resolution provisions in Section 35.15 of the Joint Operating Agreement. The NYISO
understands Section 35.15.2 to require that the parties first seek voluntary mediation, and, if a
party determines that mediation has failed, a party may initiate a formal proceeding at the
Commission under Section 206 of the Federal Power Act. The NYISO understands that the
language recognizing each party’s rights to seek formal resolution at the Commission does not
represent any party’s consent to participate in or to the outcome of such a proceeding.
VI. THE INTERREGIONAL COST ALLOCATION METHODOLOGY IN
ATTACHMENT Y OF THE NYISO OATT AND COMPLIANCE WITH THE
INTERREGIONAL COST ALLOCATION REQUIREMENTS OF ORDER NO.
1000
The new interregional cost allocation methodology in Section 31.5.7 of Attachment Y of
the NYISO OATT satisfies the interregional cost allocation requirements of Order Nos. 1000 and
1000-A with regard to the allocation of costs of Interregional Transmission Projects involving
the NYISO and ISO-NE.100 ISO-NE is filing the same cost allocation methodology in its tariffs.
The cost allocation methodology in Section 31.5.7 of Attachment Y, including the
alternate cost allocation methodology provision, is substantially identical in all material respects to the cost allocation methodology set forth in the Joint Operating Agreement, as described in Section V of this compliance filing.101 The methodology in Section 31.5.7 complies with Order No. 1000’s six interregional cost allocation principles for the same reasons as those set forth in Section V of this compliance filing.
98 Proposed JOA Section 35.10.7.4.
99 Proposed JOA Section 35.10.7.4.
100 Though Con Edison, O&R, NYPA, and LIPA support this compliance filing, they disagree
with the application of the avoided cost methodology to an interregional transmission project that costs
more than the cost of the displaced regional projects and reserve the right to file a protest to this aspect of
the filing.
101 Minor language differences between the provisions in Section 31.5.7 of Attachment Y and the parallel provisions in the NYISO-PJM Joint Operating Agreement are not intended to introduce
substantive differences. For example, Section 31.5.7.1(b)(iv) of Attachment Y expressly provides that for purposes of reviewing that reasonably comparable estimating procedures have been used for displaced regional transmission projects, the regions’ review process will occur in the IPSAC.
32
In addition, as between the NYISO and PJM, the NYISO and ISO-NE acknowledge, as
set forth in Section 9 of the Amended Protocol and Section 31.5.7. 1 of Attachment Y, that the
cost allocation methodology set forth in the NYISO’s and ISO-NE’s tariffs shall not be changed
without the mutual consent of the holders of Section 205 rights in the ISO-NE and NYISO
region.102
The NYISO similarly proposes, and understands that ISO-NE will propose, to clarify in
the cost allocation methodology the scope of their filing rights and those of the transmission
owners in their regions with regard to the cost allocation methodology. These provisions were
written with the input of the transmission owners of both regions, and reasonably maintain the
filing rights of the transmission owners in New York and ISO-NE in accordance with existing
agreements and tariff provisions. Specifically, Section 31.5.7.3 of Attachment Y of the NYISO
OATT provides that:
• Nothing in this Section 31.5.7 will convey, expand, limit or otherwise alter any rights of
ISO-NE, the ISO, PJM, each region’s transmission owners, market participants, or other
entities to submit filings under Section 205 of the Federal Power Act regarding
interregional cost allocation or any other matter; and
• Where applicable, the regions have been authorized by entities that have cost allocation
rights for their respective regions to implement the provisions of this Section 31.5.7.
VII. ADDITIONAL COMPLIANCE REVISIONS IN ATTACHMENT Y OF THE
NYISO OATT
The following revisions proposed to Attachment Y of the NYISO OATT, in conjunction with the Amended Protocol, Joint Operating Agreement, and other revisions to Attachment Y described above, complete the interregional coordination and interregional cost allocation
requirements of Order No. 1000 by providing for the coordination of regional and interregional transmission planning process and the inclusion of Interregional Transmission Projects in
regional transmission plans. The compliance revisions to Attachment Y are being submitted by the Joint Filing Parties, i.e., by the NYISO and the NYTOs.
A.Integration of Interregional Transmission Projects into the NYISO’s
Transmission Planning Processes
Order No. 1000 requires the development and implementation of procedures for the
identification and joint evaluation by neighboring regions of Interregional Transmission Projects to determine whether those facilities are more efficient or cost-effective than regional solutions. Order No. 1000 requires that these procedures include a process by which:
102 This includes the NYTOs, which include the Long Island Power Authority and the New York Power Authority.
33
•A developer of an Interregional Transmission Project must first propose its
project in the regional processes of each of the neighboring regions; 103 and
• The joint evaluation of the Interregional Transmission Project must occur in the
same general timeframe as, rather than subsequent to, each transmission planning
region’s individual consideration of the proposed project, with a meaningful
opportunity to review and evaluate through the interregional coordination
procedures information developed through the regional planning process and vice
versa;104 and
These requirements are satisfied by Section 7 of the Amended Protocol, as described in
Section IV in this compliance filing, along with the revisions to Attachment Y of the NYISO
OATT described below. Section 7 of the Amended Protocol establishes a process to identify and jointly evaluate Interregional Transmission Projects. Under these requirements, the developer of an Interregional Transmission Project must first propose the project in each of the neighboring
regions in which the project is physically located. In addition, the joint evaluation of the
Interregional Transmission Project must occur in the same general timeframe of each region’s
individual consideration of the project.
In line with these requirements, the Joint Filing Parties propose the revisions to
Attachment Y of the NYISO OATT to provide for an Interregional Transmission Project to be proposed and evaluated comparably with regional projects within the NYISO’s reliability,
economic, and Public Policy Requirements transmission planning processes. In addition, the Joint Filing Parties propose to specify that the interregional planning processes will be conducted in parallel with these intraregional processes.
1. Interregional Transmission Project
The Joint Filing Parties propose to define the term “Interregional Transmission Project” in Section 31.1.1 (“Definitions”) as follows:
Interregional Transmission Project: A transmission facility located in two or
more transmission planning regions that is evaluated under the Interregional
Planning Protocol and proposed to address an identified Reliability Need,
congestion identified in CARIS, or a transmission need driven by a Public Policy
Requirement pursuant to Order No. 1000 and the provisions of this Attachment Y.
2. Reliability Planning Process
The Joint Filing Parties propose a new Section 31.2.4.2 (“Interregional Transmission
Projects”) to establish that Interregional Transmission Projects may be proposed as solutions in the NYISO’s reliability planning process. Section 31.2.4.2 provides:
103 Id. at P 436.
104 Id. at PP 436, 439.
34
Interregional Transmission Projects may be proposed as regulated backstop
solutions, alternative regulated solutions, or market-based solutions. Interregional Transmission Projects proposed as regulated backstop solutions, alternative
regulated solutions or market-based solutions shall be subject to the applicable requirements of the reliability planning process of this Attachment Y.
Additionally, the Joint Filing Parties propose to revise Section 31.2.2.3.2 to incorporate
Interregional Transmission Projects into the base case for the Reliability Needs Assessment, which identifies Reliability Needs. Section 31.2.2.3.2 provides (in relevant part):
The Five Year Base Case shall also include Interregional Transmission Projects that have been approved by the NYPSC transmission siting process and meet the base case inclusion requirements in the ISO Procedures.
The Joint Filing Parties also propose to revise Section 31.2.6 to provide that the draft
Comprehensive Reliability Plan (“CRP”), which sets forth the NYISO’s findings and
recommendations for solving a Reliability Need, will include a comparison of any Interregional Transmission Project identified and evaluated pursuant to the Amended Protocol. Section 31.2.6 provides (in relevant part):
The draft CRP shall include a comparison of a proposed regional solution to an
identified Reliability Need to an Interregional Transmission Project identified and
evaluated under the “Analysis and Consideration of Interregional Transmission
Projects” section of the Interregional Planning Protocol, if any. An Interregional
Transmission Project proposed in the NYISO’s reliability planning process may
be selected as a market based response, regulated backstop solution or an
alternative regulated solution, under the provisions of the ISO’s reliability
planning process.
3. Economic Planning Process
The Joint Filing Parties propose revisions to Section 31.3.1.1 to provide that Interregional Transmission Projects may be proposed as solutions to congestion identified in the NYISO’s
Congestion Assessment and Resource Integration Study (“CARIS”). Section 31.3.1.1 provides
(in relevant part):
The CARIS process shall determine whether to approve an Interregional
Transmission Project, identified and evaluated under the “Analysis and
Consideration of Interregional Transmission Projects” section of the Interregional
Planning Protocol, if any, and proposed in the NYISO’s economic planning
process as an economic transmission project in lieu of a proposed regional
economic transmission project for regulated cost allocation and recovery under
the ISO Tariff.
35
Additionally, the Joint Filing Parties propose to make the following related revisions to Section
31.3.2.4 (“Actual Project Proposals”):
As discussed in Section 31.3.1 of this Attachment Y, the CARIS analyzes system congestion over the Study Period and, for informational purposes, provides
benefit/cost analysis and other analysis of potential generic solutions to the
congestion identified. If, in response to the CARIS, a Developer proposes an
actual project, including an Interregional Transmission Project that has been
identified and evaluated in accordance with the “Analysis and Consideration of
Interregional Transmission Projects” section of the Interregional Planning
Protocol, to address specific congestion identified in the CARIS, then the ISO will process that project proposal in accordance with the relevant provisions of
Sections 31.5.1, 31.5.4 and 31.5.5 of this Attachment Y.
4. Public Policy Requirements Planning Process
The Joint Filing Parties propose revisions to Section 31.4.3 (“Request for and Evaluation of Proposed Transmission Solutions”) to provide that Interregional Transmission Projects may be proposed to address identified Public Policy Requirements. Section 31.4.3 provides:
The ISO will request and evaluate specific proposed transmission solutions to a
transmission need identified by the NYDPS, including any proposed Interregional Transmission Project that has been identified and evaluated in accordance with the “Analysis and Consideration of Interregional Transmission Projects” section of the Interregional Planning Protocol.
5. Parallel Performance of Interregional and Regional Planning Processes
The Joint Filing Parties propose revisions to Section 31.1.8.2 to specify that the
interregional planning process will be conducted in parallel with the regional planning processes. Section 31.1.8.2 provides (in relevant part):
As further detailed in Sections 31.2, 31.3, 31.4, and 31.5, the interregional
planning process shall be conducted in parallel with the reliability planning
process, the economic planning process, and the Public Policy Requirements
planning process to identify and evaluate Interregional Transmission Projects that may more efficiently or cost-effectively meet the needs of the region than a
regional transmission project.
B. Eligibility for Interregional Cost Allocation
Order No. 1000 requires that an Interregional Transmission Project must be selected in
both regions’ regional transmission planning processes to be eligible for interregional cost
allocation.105 As described in Section V of this compliance filing, the cost allocation rules in
105 Id. at PP 400, 436, 581-582.
36
Section 35.10.2(a) of the JOA for Interregional Transmission Projects involving the NYISO and
PJM expressly require that an Interregional Transmission Project must be selected in both
regions’ regional transmission plans to be eligible for interregional cost allocation. In parallel, as
described in Section VI of this compliance filing, the cost allocation rules in Section 31.5.7.1(a)
of Attachment Y include the same requirement for Interregional Transmission Projects involving
the NYISO and ISO-NE.
The Joint Filing Parties propose to make the following revisions to Attachment Y that acknowledge this requirement:
• Section 31.5.1.7 (“Eligibility for Cost Allocation and Cost Recovery”) provides (in
relevant part): “Interregional Transmission Projects identified in accordance with the
Interregional Planning Protocol, and that have been accepted in each region’s planning
process, shall be eligible for interregional cost allocation and cost recovery, as set forth
in Section 31.5 of this Attachment Y and associated rate schedules.”
• New Section 31.1.6 (“Interregional Planning Process”) provides that the interregional
planning process provides for the “allocation of costs among the ISO/RTO Regions of
Interregional Transmission Projects, identified in accordance with the Interregional
Planning Protocol and approved by each region, pursuant to the cost allocation
methodology set forth in Section 31.5.7 herein.”
The Joint Filing Parties also propose to include Order No. 1000’s six interregional cost allocation principles in Section 31.5.2.2 of Attachment Y, and to specify that the NYISO will implement the interregional cost allocation methodology set forth in Section 31.5.7 in
accordance with these principles.
C. Allocation of Regional Share of Costs of Interregional Transmission Project
Order No. 1000 provides that: “Each transmission planning region would determine for itself how to allocate the costs of a new interregional transmission facility consistent with this Final Rule.”106 Order No. 1000 indicates that the public utility transmission providers may
allocate their share of the costs of an Interregional Transmission Project using their regional cost allocation method or methods.107
The Joint Filing Parties propose to revise Attachment Y to provide that the NYISO will
allocate its region’s share of the costs of an Interregional Transmission Project based on the type
of regional transmission project that is being displaced by the Interregional Transmission Project.
For example, if the Interregional Transmission Project displaces a regional transmission project
that is required to resolve a Reliability Need, the NYISO will allocate its region’s share of the
costs of the Interregional Transmission Project through the cost allocation methodology for its
reliability planning process in Attachment Y. The NYISO would similarly apply the cost
106 Order No. 1000 at P 735.
107 Order No. 1000 at P 733.
37
allocation methodology for its economic or Public Policy Requirement planning processes for
Interregional Transmission Projects that displace regional transmission projects and solve these needs. This approach ensures that the costs of Interregional Transmission Projects that satisfy
reliability, economic, or public policy needs are allocated to those that benefit from such projects on a comparable basis with how the costs of regional projects that satisfied those same needs
would be allocated to those that benefit. This approach uses regional cost allocation
methodologies accepted by the Commission as consistent with its Order No. 1000 requirements and regional cost allocation principles.
The Joint Filing Parties propose to revise Section 31.5.1.7 (“Eligibility for Cost
Allocation and Cost Recovery”) to establish this process for allocating the NYISO region’s share of the costs of an Interregional Transmission Project. Section 31.5.1.7 provides:
The ISO’s share of the cost of an Interregional Transmission Project selected
pursuant to this Attachment Y to meet a Reliability Need, congestion identified in CARIS, or a transmission need driven by a Public Policy Requirement shall be eligible for cost allocation consistent with the cost allocation methodology
applicable to the type of regional transmission project that would be replaced through the construction of such Interregional Transmission Project.
The Joint Filing Parties propose to revise the description of the cost allocation
methodology for the NYISO’s reliability planning process in Section 31.5.3.1 (“Cost Allocation Principles”) to provide for this allocation. Section 31.5.3.1 provides (in relevant part):
This methodology shall apply to cost allocation for a regulated transmission
solution to an identified Reliability Need, including the ISO’s share of the cost of
an Interregional Transmission Project proposed as a regulated transmission
solution to an identified Reliability Need allocated in accordance with Section
31.5.7 of this Attachment Y.
Similarly, the Joint Filing Parties propose to revise the description of the cost allocation
methodology for the NYISO’s economic planning process in Section 31.5.4.4 (“Cost Allocation for Eligible Projects”) to provide (in relevant part):
This methodology shall apply to cost allocation for a [regulated economic
transmission project (“RETP”)], including the ISO’s share of the cost of an
Interregional Transmission Project proposed as a RETP allocated in accordance with Section 31.5.7 of this Attachment Y.
In addition, the Joint Filing Parties propose to revise the description of the cost allocation
methodology for the NYISO’s Public Policy Requirements planning process in Section 31.5.5.4 (“Cost Allocation for Eligible Projects”) to provide (in relevant part):
This methodology shall apply to cost allocation for a proposed solution to a
transmission need driven by a Public Policy Requirements, including the ISO’s
share of the costs of an Interregional Transmission Project proposed as a solution
38
to a transmission need driven by a Public Policy Requirement allocated in accordance with Section 31.5.7 of this Attachment Y.
D.Additional Compliance Revisions
The Joint Filing Parties propose the following additional modifications to Attachment Y.
1. Overview of Interregional Planning Process
Order No. 1000 requires a public utility transmission provider that includes its
interregional transmission coordination procedures in an interregional transmission coordinating
agreement to include in its OATT a sufficiently detailed description for stakeholders to follow
how interregional transmission coordination will be conducted.108 The Joint Filing Parties
propose to replace the overview of the existing “Interregional Planning Coordination” process in
Section 31.6.6 with the following revised overview of the “Interregional Planning Process” in
Section 31.1.6:
The ISO, the Transmission Owners, and Market Participants and other interested
parties shall coordinate system planning activities with neighboring planning
regions (i.e., the ISO/RTO Regions and adjacent portions of Canada). The
Interregional Planning Protocol includes a description of the committee structure,
processes, and procedures through which system planning activities are openly
and transparently coordinated by the ISO/RTO Regions. The objective of the
interregional planning process is to contribute to the on-going reliability and the
enhanced operational and economic performance of the ISO/RTO Regions
through: (1) exchange of relevant data and information; (2) coordination of
procedures to evaluate certain interconnection and transmission service requests;
(3) periodic comprehensive interregional assessments; (4) identification and evaluation of potential Interregional Transmission Projects that can address
regional needs in a manner that may be more efficient or cost-effective than separate regional solutions, in accordance with the requirements of Order No. 1000; (5) allocation of costs among the ISO/RTO Regions of Interregional
Transmission Projects, identified in accordance with the Interregional Planning Protocol and approved by each region, pursuant to the cost allocation
methodology set forth in Section 31.5.7 herein.
The planning activities of the ISO/RTO Regions shall be conducted consistent with the planning criteria of each ISO/RTO Region’s regional reliability
organization(s) as well as the relevant local reliability entities. The ISO/RTO Regions shall periodically produce a Northeastern Coordinated System Plan that integrates the system plans of all of the ISO/RTO Regions.
108 Order No. 1000 at P 475 n 372.
39
2. Consequences for Other Regions
The Joint Filing Parties propose to revise Sections 31.2.2.7, 31.3.1.6, and 31.4.4.1 of
Attachment Y to provide that the NYISO will coordinate with the neighboring ISO/RTO
Regions (i.e., PJM and ISO-NE) to identify the consequences of reliability transmission projects, economic transmission projects, and transmission solutions driven by Public Policy
Requirements on such ISO/RTO Regions “using the respective planning criteria of such
ISO/RTO Regions.” The proposed revisions enable the NYISO to identify consequence of its regional planning process for neighboring ISO/RTO systems to inform the interregional planning process. In addition, consistent with Order No. 1000’s interregional cost allocation principle 4, the revisions enable the NYISO to coordinate with neighboring ISOs/RTOs to identify the
consequences on their systems of an Interregional Transmission Project.
3. Stakeholder Participation
The Joint Filing Parties propose to revise Section 31.1.7 to provide that, for purposes of any matter addressed in the NYISO’s Attachment Y, any interested entity is eligible to
participate in the NYISO’s Interregional Planning Task Force (“IPTF”), irrespective of whether the entity has become a Party to the NYISO’s Independent System Operator Agreement. The IPTF was formed to enable NYISO stakeholders to provide input and guidance to the NYISO regarding technical and economic aspects of interregional planning.
4. Adoption of Procedures
Section 31.1.8.1 of Attachment Y provides that the NYISO will adopt procedures to
implement and administer the CSPP set forth in Attachment Y. The Joint Filing Parties proposed
to revise this section to provide that the NYISO will also adopt procedures, with input from all
interested parties, to implement and administer the CSPP requirements set forth in the Amended
Protocol.
5. Definitions
The Joint Filing Parties also propose to revise or insert the following definitions for Attachment Y:
CSPP: The Comprehensive System Planning Process set forth in this Attachment Y, and in the Interregional Planning Protocol, which covers reliability planning, economic planning, Public Policy Requirements planning, cost allocation and cost recovery, and the interregional planning process coordination.
Interregional Planning Protocol: The Amended and Restated Northeastern
ISO/RTO Planning Coordination Protocol, or any successor to that protocol.
IPTF: The Interregional Planning Task Force, or any successor ISO stakeholder working group or committee designated to fulfill the functions assigned to the IPTF in this tariff.
40
ISO/RTO Region: One or more of the three ISO or RTO regions known as PJM, ISO-New England, and NYISO, which are the “Parties” to the Interregional
Planning Protocol.
Order No. 1000: The Final Rule entitled Transmission Planning and Cost Allocation by Transmission Owning and Operating Public Utilities, issued by the Commission on July 21, 2011, in Docket RM10-23-001, as modified on rehearing, or upon appeal. (See
FERC Stats & Regs. ¶ 31,323 (2011) (“Order No. 1000”), on reh’g and clarification, 139 FERC ¶ 61,132 (“Order No. 1000-A”), on reh’g and clarification, 141 FERC ¶ 61,044
(2012) (“Order No. 1000-B”).
6. Ministerial Modifications
Additionally, the Joint Filing Parties propose to make certain ministerial modifications to Attachment Y that will not alter the substance of the NYISO’s transmission planning process as set forth in Attachment Y.109 These changes include correcting internal cross-references and applying defined terms consistently throughout Attachment Y.
VIII. EFFECTIVE DATE
The NYISO, and with respect to Section VII, the Joint Filing Parties, respectfully request
that the compliance tariff modifications proposed herein become effective January 1, 2014. The
NYISO understands that PJM and ISO-NE are proposing the same effective date for their Order
No. 1000 interregional compliance revisions to the extent that they are interrelated with the
NYISO’s revisions.
IX.SERVICE
The NYISO will send an electronic copy of this filing to the official representative of
each party to this proceeding, to the official representative of each of its customers, to each
participant on its stakeholder committees, to the New York Public Service Commission and the
New Jersey Board of Public Utilities. In addition, the complete public version of this filing will
be posted on the NYISO’s website at www.nyiso.com.
X.CONCLUSION
WHEREFORE, the New York Independent System Operator, Inc. and, for purposes of
Section VII, the New York Transmission Owners respectfully request that the Commission
accept this compliance filing, without requiring any modifications, and make it effective on
January 1, 2014.
109 The Commission has previously authorized the NYISO to include these kinds of limited, but necessary, clarifications in compliance filings and should follow that precedent here. See New York
Independent System Operator, Inc., 125 FERC ¶ 61,206 (2008), reh’g, 127 FERC ¶ 61,042 (2009)
(accepting proposed tariff revisions necessary to correct drafting errors, clarify ambiguities, or flesh out necessary implementation details).
41
NEW YORK INDEPENDENT SYSTEM OPERATOR, INC.
By: /s/ Carl F. Patka
Robert E. Fernandez, General Counsel
Ray Stalter, Director of Regulatory Affairs
Carl F. Patka, Assistant General Counsel
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Email: rfernandez@nyiso.com Email: rstalter@nyiso.com
Email: cpatka@nyiso.com
Ted J. Murphy
Hunton & Williams LLP
2200 Pennsylvania Ave, NW
Washington, DC 20037
Email: tmurphy@hunton.com
Michael Messonnier
Hunton & Williams LLP
951 East Byrd Street
Richmond, VA 23219
Email: mmessonnier@hunton.com
/s/ John Borchert
John Borchert
Senior Director of Energy Policy and Transmission Development
Central Hudson Gas & Electric Corporation 284 South Avenue
Poughkeepsie, NY 12601
Email: jborchert@cenhud.com
NEW YORK TRANSMISSION OWNERS
By: /s/ Elias G. Farrah
Elias G. Farrah
Winston & Strawn, LLP 1700 K Street, NW
Washington, DC 2006-3817
Email: efarrah@winston.com
*Paul L. Gioia
Whiteman Osterman & Hanna LLP 111 Washington Avenue
Suite 401
Albany, NY 12210
Email: pgioia@woh.com
/s/ Richard B. Miller
Consolidated Edison Company of New York, Inc. Orange and Rockland Utilities, Inc.
Richard B. Miller
Director of Energy Markets Policy Group Consolidated Edison Co.
of New York, Inc.
4 Irving Place
Room 1815-s
New York, NY 10003
Email: millerrich@coned.com
/s/Kristina Nifora
Consolidated Edison Company of New York, Inc. Orange and Rockland Utilities, Inc.
Kristina Nifora, Esq. Senior Attorney
Consolidated Edison Co. of New York, Inc.
42
/s/ Jacqueline Hardy
Jacqueline Hardy
Assistant General Counsel
Long Island Power Authority
333 Earle Ovington Boulevard Suite 403
Uniondale, NY 11553
Email: jhardy@lipower.org
David Clarke
Director of Power Markets Policy Long Island Power Authority
99 Washington Avenue 10th Floor
Albany, NY 12210-2822
Email: dclarke@lipower.org
/s/ R. Scott Mahoney
R. Scott Mahoney, Esq.
New York State Electric & Gas Corporation Rochester Gas and Electric Corporation
Durham Hall, 52 Farm View Drive New Gloucester, ME 04260
Email: scott.mahoney@iberdrolausa.com
/s/ Andrew Neuman
New York Power Authority Andrew Neuman, Esq.
New York Power Authority 123 Main Street
White Plains, NY 10601-3170
Email: andrew.neuman@nypa.gov
Andrew Antinori, Director Market Issues New York Power Authority
123 Main Street
White Plains, NY 10601-3170
Email: andrew.antinori@nypa.gov
/s/ Daniel Galaburda
Niagara Mohawk Power Corporation d/b/a/ National Grid
National Grid USA Service Company, Inc. Assistant General Counsel and Director
40 Sylvan Road
Waltham, MA 02451-1120
Email: daniel.galaburda@us.nrid.com
David Lodemore
Senior Counsel
Niagara Mohawk Power Corporation d/b/a National Grid
40 Sylvan Road
Waltham, MA 02451-1120
david.lodemore@nationalgrid.com
Bart Franey
Director of Federal Regulation
Niagara Mohawk Power Corporation d/b/a National Grid
300 Erie Boulevard West Syracuse, NY 13202
43