HUNTON & WILLIAMS LLP

BANK OF AMERICAN CENTER
700 LOUISIANA STREET
SUITE 4200

HOUSTON, TX  77002-2742

 

TEL713 • 229…5700

FAX713 • 229 • 5750

 

VANESSA A. COLÓN

DIRECT DIAL: 713 • 229 • 5724
EMAIL:  vcolon@hunton.com

April 2, 2012

 

 

 

Kimberly D. Bose, Secretary

Federal Energy Regulatory Commission 888 First Street, N.E.

Washington, D.C. 20426

 

Re:    Annual Compliance Report of the New York Independent System Operator, Inc.
Regarding Unreserved Use and Late Study Penalties

Docket No. OA12-_______

 

Dear Ms. Bose:

Paragraph 472 of Order No. 890-A1 requires that “each transmission provider …
report on its [unreserved use and late study] penalty assessments and distributions in an
annual compliance report to be submitted on or before the deadline for submitting FERC
Form-1, as established by the Federal Energy Regulatory Commission’s (“Commission’s”)
Office of Enforcement each year.”  Pursuant to that directive, the New York Independent
System Operator, Inc. (“NYISO”) respectfully submits its annual compliance report.2

 

I.Unreserved Use Penalties

Unreserved use penalties are designed to address an issue that arises only under a
physical reservation regime.  The NYISO does not offer physical reservation based
transmission service and the NYISO tariffs do not provide for the imposition of unreserved use penalties.  Therefore, the NYISO neither imposed nor collected such penalties during the period since April 18, 2011.

 

1 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890-A, FERC Stats & Regs. ¶ 31,261 (2007).

2 Order No. 890-A provides that the “annual compliance report should be filed under the same docket as
the docket in which the proposed one-time compliance filing [establishing the transmission provider’s
methodology for distributing penalty revenues] is submitted.”  Order No. 890-A at P 472.  Because that “one-
time compliance filing can be submitted at any time prior to the first distribution of operational penalties,” and
because the NYISO has neither imposed unreserved use penalties, or been subject to late study penalties, it has
not yet made such a filing. Id.  Accordingly this compliance filing is being made in a new docket.

 

 

ATLANTA   AUSTIN   BANGKOK   BEIJING   BRUSSELS   CHARLOTTE   DALLAS   HOUSTON   LONDON   LOS ANGELES
McLEAN   MIAMI   NEW YORK   NORFOLK   RALEIGH   RICHMOND   SAN FRANCISCO   WASHINGTON

www.hunton.com


 

 

 

 

 

 

 

Kimberly D. Bose, Secretary April 2, 2012

Page 2

 

 

II.Late Study Penalties

In Order No. 890, the Commission adopted a rule requiring that “transmission

providers … submit a notification filing with the Commission in the event the transmission
provider processes more than 20 percent of non-affiliates’ [system impact and facilities]
studies outside of the 60-day due diligence deadlines in the pro forma OATT for two
consecutive quarters.”3  The Commission determined further that a “transmission provider …
will be subject to an operational penalty if the transmission provider continues to be out of
compliance with the deadlines prescribed in the pro forma OATT for each of the two quarters
following its notification filing and the Commission determines that no extenuating
circumstances exist to excuse the transmission provider’s non-compliance.”4

As explained in prior reports, the Commission has accepted modifications to the

NYISO OATT transmission study deadlines.5  In the year since the NYISO’s last compliance report, the NYISO’s administration of transmission studies has not triggered the penalty or notification filing requirements under the NYISO OATT.  Therefore, the NYISO has not been assessed any transmission study penalties in the past year.

If you have any questions regarding this submission, please do not hesitate to contact the undersigned.

 

Respectfully submitted,

/s/ Vanessa A. Colón

Vanessa A. Colón
Counsel to the

New York Independent System Operator, Inc.

 

 

 

 

 

 

 

3 Order No. 890 at P 1319.

4 Id.

5 See New York Independent System Operator, Inc., Letter Order, Docket No. ER08-1527-000

(November 4, 2008) (accepting the NYISO’s proposed modifications to its Open Access Transmission Tariff (“OATT”), effective September 13, 2008, which modified and extended the transmission study deadlines under the pro forma OATT).