HUNTON & WILLIAMS LLP
BANK OF AMERICA CENTER
700 LOUISIANA STREET
SUITE 4200
HOUSTON, TEXAS 77002-2742
TEL713 • 229 • 5700
FAX713 • 229 • 5750
VANESSA A. COLÓN
DIRECT DIAL: 713 • 229 • 5724
EMAIL: vcolon@hunton.com
June 29, 2012FILE NO: 55430.000093
Ms. Kimberly D. Bose Secretary
Federal Energy Regulatory Commission 888 First St, NE
Washington, DC 20426
Re: New York Independent System Operator, Inc., Further Compliance Filing
Docket Nos. ER04-449-__, ER12-360-___
Dear Ms. Bose:
The New York Independent System Operator, Inc. (“NYISO”) submits this further
compliance filing proposing market mitigation measures for New Capacity Zones (“NCZs”),
pursuant to the Commission’s September 8, 2011 Order on Compliance Filing (“September
Order”)1 and to the NYISO’s November 7, 2011 compliance filing (“November 2011 Filing”)
in this proceeding. This filing proposes tariff revisions to the NYISO’s Market
Administration and Control Area Services Tariff (“Services Tariff”) to implement both buyer-
side and supplier-side mitigation measures for NCZs using the same conceptual framework of
the existing market mitigation measures currently applicable to the New York City Locality.2
The NYISO requests an effective date of September 1, 2012, or the effective date the Commission accepts for the tariff revisions submitted in the November 2011 Filing.
1New York Independent System Operator, Inc., 136 FERC ¶ 61,165 (2011) (“September
Order”).
2 The NYISO will be making additional revisions to the currently existing market mitigation
measures applicable to Installed Capacity Suppliers in New York City, in compliance with to the
Commission’s June 21, 2012 order in Docket No. EL11-42-000. See New York Independent System
Operator, Inc., 139 FERC ¶ 61,244 (2012) (“EL11-42 Order”). The revisions proposed in that
compliance filing will be made to then-filed version of the tariff, which will include the modifications
proposed herein. Therefore, the compliance filing in response to the EL11-42 Order will also include
additional modifications to the changes proposed in this filing so they are consistent with the
directives in the EL11-42 Order.
ATLANTA AUSTIN BANGKOK BEIJING BRUSSELS CHARLOTTE DALLAS HOUSTON LONDON LOS ANGELES
McLEAN MIAMI NEW YORK NORFOLK RALEIGH RICHMOND SAN FRANCISCO TOKYO WASHINGTON
Ms. Kimberly D. Bose, Secretary
Page 2
I.LIST OF DOCUMENTS SUBMITTED
The NYISO respectfully submits the following documents:
1. This filing letter;
2. A blacklined version of the modifications to the Services Tariff (“Attachment I”);
3. A clean version of the modifications to Services Tariff (“Attachment II”);
4. The Affidavit of David B. Patton, Ph.D (“Attachment III”); and
5. The Affidavit of Randall Wyatt (“Attachment IV”).
II.BACKGROUND
In the September Order, the Commission accepted in part and rejected in part a
NYISO compliance filing proposing criteria for the implementation of NCZs. Among other things, the September Order confirmed that “additional market power mitigation measures may be needed for an established new capacity zone.”3
On November 7, 2011, the NYISO submitted its compliance filing in response to the September Order.4 The November 2011 Filing, however, did not propose market mitigation measures for NCZs, instead noting that discussions between the Market Monitoring Unit (“MMU”) and the NYISO had occurred and a set of such measures were being developed.5 The filing stated that the development of the mitigation measures would be complex and that the NYISO would make a further compliance filing by June 30, 2012.6
III. DESCRIPTION OF PROPOSED COMPLIANCE TARIFF REVISIONS
In compliance with P 64 of the September Order, the NYISO submits this filing
proposing compliance tariff revisions to implement supplier-side and buyer-side market
mitigation measures for NCZs (“NCZ Market Mitigation Measures”). As explained in the
Patton Affidavit, these measures are necessary because as the NYCA market is further
divided to add NCZs, potential market power increases, because the size of the effective
3 September Order at P 64.
4 The November 2011 Filing is still pending before the Commission.
5 November 2011 Filing at 7.
6 The NYISO also requested, to the extent necessary, that the Commission grant an extension
of time to make this filing by June 30, 2012, rather than concurrent with the November 2011 Filing.
Ms. Kimberly D. Bose, Secretary
Page 3
market area becomes narrower.7 Because NCZs are not expected to have significant amounts of surplus capacity in equilibrium, they raise local market power concerns and thus warrant mitigation.8 Further, over mitigation in NCZs is not an issue, because as proposed by the
NYISO, the NCZ Market Mitigation Measures are not punitive nor do they create substantial risk for suppliers without market power.9 The NCZ Market Mitigation Measures are designed to “preclude conduct that would not be rational for a competitive supplier.”10 Consistent
application of supplier-side and buyer-side mitigation measures to all NCZs will reduce future uncertainty regarding the formation of NCZs over time, for buyers and sellers in the ICAP11 Market.12 Reducing uncertainty will facilitate long-term investment and contracting
decisions, which is the primary purpose of the ICAP Market.13
The NCZ Market Mitigation Measures utilize the conceptual framework of the
currently effective ICAP market mitigation measures applicable to the New York City
Locality.14 As explained in the Wyatt Affidavit, using the framework of the existing ICAP
mitigation measures provides consistent rules across all Mitigated Capacity Zones and allows sufficient flexibility to modify specific Pivotal Supplier thresholds to accommodate
differences among NCZs. As explained in more detail below, the NCZ Market Mitigation Measures utilize the current In-City mitigation rules with modifications as necessary to
accommodate the differences between NCZs and the New York City Locality.
A.General Revisions
The NYISO proposes these general revisions for ease of implementation of the NCZ
Market Mitigation Measures and consistency with other tariff provisions. First, the NYISO
proposes the new term “Mitigated Capacity Zone” in Services Tariff Section 2.13. The term
“Mitigated Capacity Zone” is defined as “New York City and any Locality added to the
definition of “Locality” accepted by the Commission on or after March 31, 2012.” This term
7 Patton Affidavit at P 8.
8 Id. at P 9.
9 Id. at P 12.
10 Id.
11 Terms with initial capitalization not defined herein shall have the meaning set forth in the Services Tariff, and if not defined therein, then in the November 2011 Filing.
12 Patton Affidavit at P 14.
13 Id.
14 The NYISO will thus be making revisions in compliance with the EL11-42 Order. See supra n. 3.
Ms. Kimberly D. Bose, Secretary
Page 4
excludes Long Island, which is an existing Locality and it is presently not subject to the current buyer-side and supplier-side mitigation measures.
The NYISO also proposes to revise references15 to the “New York City Locality” or
“In-City” to “Mitigated Capacity Zone” in order to make the Pivotal Supplier provisions,
which currently only apply in the New York City Locality, applicable to Pivotal Suppliers in
any Mitigated Capacity Zone. Additionally, the NYISO proposes to revise references,16 in
the provisions in Section 23.4.5.7, et. seq., to the “New York City Locality” or “In-City” to
“Mitigated Capacity Zone” in order to make those sections applicable to Installed Capacity
Suppliers in any Mitigated Capacity Zone. Sections have also been renumbered, as
appropriate.
B.NCZ Supplier-Side Mitigation Measures
The NYISO proposes compliance revisions to Attachment H Section 23.4.5 to
implement supplier-side mitigation measures for NCZs. As explained by the Patton Affidavit,
the proposed tariff revisions include provisions to ensure that the application of the supplier-
side mitigation measures in any Mitigated Capacity Zone is restricted to Pivotal Suppliers.
This restriction is necessary to ensure that there are no adverse impacts on suppliers without
market power.
First, the NYISO is proposing to revise the definition of Pivotal Supplier to make it
applicable to Market Parties that Control a specified MW of Unforced Capacity in a Mitigated Capacity Zone, as follows:
For purposes of Section 23.4.5 of this Attachment H, “Pivotal Supplier” shall mean (i) for the New York City Locality, a Market Party that, together with
any of its Affiliated Entities, (a) Controls 500 MW or more of Unforced
Capacity, and (b) Controls Unforced Capacity some portion of which is
necessary to meet the New York City Locational Minimum Installed Capacity Requirement in an ICAP Spot Market Auction; and (ii) for each Mitigated
Capacity Zone except New York City, a Market Party that Controls at least the quantity of MW of Unforced Capacity specified for the Mitigated Capacity
Zone and accepted by the Commission.
15 See Attachment H Sections 23.4.5.3, 23.4.5.4, 23.4.5.4.1, 23.4.5.4.2, 23.4.5.4.3, 23.4.5.6, as well as the definitions of “Affiliated Entity,” “Control,” “Going-Forward Costs,” “Net CONE,”
“UCAP Offer Reference Level,” “Surplus Capacity,” and “Unit Net CONE” and Attachment O
Sections 30.4.6.2.8 and 30.4.6.2.10.
16 See Attachment H Sections 23.4.5.7, 23.4.5.7.1, 23.4.5.7.223.5.7.5, as well as the definitions of “Net CONE,” and “Unit Net CONE” and Attachment O Section 30.4.6.2.11
Ms. Kimberly D. Bose, Secretary
Page 5
Because the configuration of NCZs that may be proposed is currently unknown, the NYISO
proposes to indicate the MW level of Unforced Capacity at which a supplier will be deemed
to have Control, and is thus a Pivotal Supplier, at the time the NYISO submits a filing
proposing a Mitigated Capacity Zone; i.e., the March 31 Filing in a Demand Curve Reset
Filing Year.17
Additionally, the NYISO is proposing to modify Section 23.4.5.2 to establish the
UCAP Offer Reference Level for Resources in a Mitigated Capacity Zone in which an
Installed Capacity Supplier is a Pivotal Supplier. Because an Installed Capacity Supplier
could be a Pivotal Supplier in some, but not all, of the Mitigated Capacity Zones in which it has Resources, the NYISO is proposing to modify Section 23.4.5.2 to establish the UCAP
Offer Reference Level to be set at either “the lowest of the UCAP Offer Reference Levels for each Mitigated Capacity Zone in which such Installed Capacity Supplier has Resources” or
the applicable Going-Forward Costs.
C.NCZ Buyer-Side Mitigation Measures
The NYISO proposes compliance revisions to Section 23.4.5 of Attachment H to
implement buyer-side mitigation measures for NCZs. The modifications include provisions to: (1) exempt projects that have made significant investments prior to the filing of a proposal to create a Mitigated Capacity Zone (i.e., “grandfathering” the projects from the rule), (2)
exempt certain Special Case Resources in Mitigated Capacity Zones under a grandfathering
provision; and (3) conduct an Offer Floor mitigation exemption/Offer Floor determination for non-grandfathered projects.
1.Grandfathering Generators and UDR Projects
As explained by the Patton Affidavit, the proposed tariff revisions include provisions
grandfathering certain projects that, as of the date the NYISO’s filing proposing a Mitigated
Capacity Zone, have Commenced Construction and received Capacity Resource
Interconnection Service (“CRIS”) or, met specific requirements regarding a CRIS transfer at
the same location. In order to ensure that the proposed mitigation measures do not act as a
barrier to new investment, the NYISO is proposing changes in Section 23.4.5.7.7 that apply
tests to determine whether projects have advanced enough prior to a filing to create an NCZ to
warrant being grandfathered from buyer-side mitigation. The new Section 23.4.5.7.7 states:
For any Mitigated Capacity Zone except New York City:
17 See November 2011 Filing at Attachment I at Services Tariff § 5.16.4.
Ms. Kimberly D. Bose, Secretary
Page 6
(I) Any existing or proposed Generator or UDR project that has the
characteristics specified in this Section 23.4.5.7.7(I) shall be exempt from an
Offer Floor with respect to the MW of CRIS that it received at the time, or for
which it satisfied the specific CRIS transfer requirements stated in this Section.
To be eligible for an exemption under this Section: (a) the existing or proposed
Generator or UDR project’s location must be included in the ISO’s March 31
Filing in the ICAP Demand Curve Reset Filing Year in which a Mitigated
Capacity Zone is first applied to such location; (b) prior to that March 31
Filing the existing or proposed Generator or UDR project must have both: (i)
Commenced Construction and (ii) either (1) received the MW of CRIS in a
Class Year that was completed or (2) submitted to the ISO a request for an
Interconnection Agreement that specifically states that the Generator or UDR
project will be requesting or has requested a transfer of a specific MW quantity
of CRIS at the same location in accordance with Section 25.9.4 of OATT
Attachment S (provided that the transfer is ultimately approved by the ISO and
consummated); and (c) the existing or proposed Generator or UDR project
must demonstrate to the ISO no later than the deadline established by the ISO
that it satisfies the requirements of (b) (i) and (ii) above; and
(II) An existing or proposed Generator or UDR project that is not
subject to a deliverability requirement (and therefore, is not in a Class Year
and does not receive CRIS MW) shall be exempt from an Offer Floor if it
meets the following requirements prior to the ISO’s March 31 Filing in an
ICAP Demand Curve Reset Filing Year in which a Mitigated Capacity Zone is
first applied to such location: (a) has Commenced Construction, (b) has an
effective Small Generator Interconnection Agreement pursuant to OATT
Attachment Z, and (c) provides specific written notification to the ISO that it
meets requirements (a) and (b) of this subsection 23.4.5.7.7(II) no later than
the deadline established by the ISO.
The ISO shall consult with the Market Monitoring Unit prior to
determining whether an existing or proposed Generator or UDR project has
Commenced Construction. Prior to the ISO making its determination, the
Market Monitoring Unit shall provide the ISO a written opinion and
recommendation regarding whether an existing or proposed Generator or UDR
project Commenced Construction. The responsibilities of the Market
Monitoring Unit that are addressed in this section of the Mitigation Measures
are also addressed in Section 30.4.6.2.11 of Attachment O. The ISO shall only
make a determination pursuant to this Section for an existing or proposed
Generator or UDR project for the Mitigated Capacity Zone’s first application
to the location of the project. The Market Monitoring Unit shall also provide a
Ms. Kimberly D. Bose, Secretary
Page 7
public report on its assessment of an ISO determination that an existing or
proposed Generator or UDR project is exempt from an Offer Floor pursuant to this Section 23.4.5.7.7.
As explained in the Patton Affidavit, the tests proposed by the NYISO are appropriate because they reasonably balance the concerns of exposing investors to the risk that a project could be denied capacity revenues when it was initiated long prior to the creation of an NCZ and not allowing strategic uneconomic investments.18 The Patton Affidavit further explains that the two proposed “Commenced Construction” tests are appropriate because they will determine whether a project has advanced enough prior to the announcement and filing of the new capacity zone to warrant an exemption from buyer-side mitigation.19
The NYISO has also proposed to add “Commenced Construction” as a defined term in Section 23.2.1, as follows:
“Commenced Construction” shall mean (a) all of the following site
preparation work is completed: ingress and egress routes exist; the site on
which the project will be located is cleared and graded; there is power service
to the site; footings are prepared; and foundations have been poured consistent
with purchased equipment specifications and project design; or (b) as approved
by the ISO in accordance with ISO Procedures, a financial commitment
comparable to (a) has been made, which includes costs incurred, and costs of
cancelling, discontinuing, or suspending the project; and may consist of a
combination of actions or commitments. Such actions or commitments may
include: major equipment has been purchased; an engineering, procurement,
and construction contract for the project has been executed by all parties and is
effective; or financing has been completed.
As explained in the Patton Affidavit, the criteria specified in subsection (a) of the definition of
Commenced Construction provides milestones that will likely only be satisfied if the project
has been under development for a number of years, long before the NCZ was announced by
the NYISO, and the project has incurred significant costs.20 The part (b) criterion provides an
opportunity for a project that may have a level of commitment by the developer that is
comparable to what is required under the part (a) criterion, even though the project does not
satisfy all of the elements of part (a).21 The second test, therefore, allows the NYISO to
18 Patton Affidavit at P 16.
19 Id. at 17.
20 Id. at 17.
21 Id. at 19.
Ms. Kimberly D. Bose, Secretary
Page 8
exempt a project if that project can demonstrate other actions or commitments that are
comparable to those in the first test.22 As explained in the Patton Affidavit, this test “is
beneficial because not all projects follow the same developmental milestones.”23
In order to be considered for this exemption and a Commenced Construction
determination, a project has to have received CRIS or met certain criteria regarding a request
for a transfer of CRIS at the same location. Pursuant to this requirement, a project must have
either received CRIS MW in a completed Class Year, or received it after having submitted a
request for an Interconnection Agreement that states it has requested or will request a transfer
of CRIS. Further, any such transfer must be approved by the NYISO and ultimately
consummated.24
Section 23.4.5.7.7 requires that a Commenced Construction test and the requirement
related to CRIS are met for a project to be exempt from buyer-side mitigation under the
grandfathering provision. Further, pursuant to Section 23.4.5.7.7 (and proposed
corresponding revisions to Attachment O Section 30.4.6.2.11) the NYISO must consult with
the MMU before a project will be determined to be exempt under this two prong test, and the
MMU will provide a public report on any such determination by the NYISO.25 As explained
in the Patton Affidavit, these requirements provide a reasonable level of oversight.26
Finally, the NYISO is proposing revisions to Section 23.4.5.7.6 that exempt from the
Offer Floor existing Generators or UDR projects, in Mitigated Capacity Zones outside of New
York City, that have been grandfathered from the deliverability requirements pursuant to
OATT Attachment S.27 The proposed exemption is consistent with those described above
because Generators and UDR projects that are “existing” now would generally have taken
actions that satisfy the “Commenced Construction” test long before the NYISO’s March 31
22 Id.
23 Id. at P 19.
24 Since projects 2 MW and under are not subject to the Class Year deliverability rules in OATT Attachment S, the buyer-side mitigation rules for such projects provide for exemption if a project satisfies the “Commenced Construction” criteria and has an effective Small Generator Interconnection Agreement.
25 As explained in n.3 above, the NYISO will be proposing compliance tariff revisions in
response to the directives in EL11-42-000 Order. The modifications will include changes providing that the NYISO will announce such determinations and that the MMU’s report will be published concurrently with that announcement.
26 Patton Affidavit at P 19.
27 The NYISO developed this exemption in consultation with Dr. Patton and is authorized to state that he supports it.
Ms. Kimberly D. Bose, Secretary
Page 9
Filing proposing any New Capacity Zone. To be eligible for this exemption, an entity must
have been an “existing facility” as of the date of this filing, i.e., June 29, 2012. Such entities
will be exempt at the level of CRIS MW at which they were grandfathered from
deliverability. Any subsequent increase in CRIS MW for such a facility that is greater than 2
MW will not be covered by the Section 23.4.5.7.6(b) exemption but would have an
opportunity to be considered for an exemption pursuant to the Section 23.4.5.7.7 test. If
ineligible for either the 23.4.5.7.6(b) or 23.4.5.7.7 exemptions a subsequent increase in CRIS
MW beyond 2 MW would be subject to the NYISO’s examination for an Offer Floor or
exemption. However, such an increase in the project’s MW of CRIS can be reviewed for an
exemption under the proposed grandfathering rule set forth in the revisions to Section
23.4.5.7.7.
2.Grandfathering Special Case Resources
The NYISO proposes to grandfather from the buyer-side mitigation measures any
Special Case Resources enrolled with the NYISO prior to the filing of a proposed Mitigated
Capacity Zone. Specifically, the NYISO proposes to modify Section 23.4.5.7.5 as follows:
An Mitigated Capacity ZoneIn-City Installed Capacity Supplier that is a
Special Case Resource shall be subject to an Offer Floor beginning with the
month of its initial offer to supply Installed Capacity, and until its offers of
Installed Capacity have been accepted in the ICAP Spot Market Auction at a
price at or above its Offer Floor for a total of twelve, not necessarily
consecutive months. A Special Case Resources shall be exempt from the Offer
Floor if (a) it is located in a Mitigated Capacity Zone except New York City
and is enrolled as a Special Case Resource with the ISO for any month within
the Capability Year that includes March 31 in an ICAP Demand Curve Reset
Filing Year in which the ISO proposes a New Capacity Zone that includes the
location of the Special Case Resource, or (b) the ISO projects that the ICAP
Spot Market Auction price will exceed the Special Case Resource’s Offer
Floor for the first twelve months that the Special Case Resource reasonably
anticipated to offer to supply UCAP…”
As explained in the Wyatt Affidavit, grandfathering of such Special Case Resources is
appropriate because Special Case Resources are existing “facilities that offer capacity in the
form of their ability to curtail their system load during specific periods when called upon” and
whose “primary business … is not the provision of capacity.” This makes the “Commenced
Construction” criteria unsuitable for SCRs.28 The revisions providing for the period for
grandfathering Special Case Resources were proposed because they account for the fact that
28 Wyatt Affidavit at P 5.
Ms. Kimberly D. Bose, Secretary
Page 10
Special Case Resources’ willingness or ability to curtail can vary from month-to-month and
can vary “significantly from one Capability Period to the next.”29 Thus, it is appropriate for
the rule to account for variations in Special Case Resource enrollment as an Installed Capacity
Supplier in the ICAP Market throughout a Capability Year.30 As the Wyatt Affidavit
explains, because Special Case Resources can readily enter and exit the ICAP market, it is
appropriate to limit the exemption to those SCRs that were enrolled in the Capability Year
that includes the March 31 Filing proposing an NCZ that includes the location of the Special
Case Resource.31
3. Offer Floor and Mitigation Exemption Determinations
The NYISO proposes to make Offer Floor and mitigation exemption determinations
for projects located in a Mitigated Capacity Zone that are not eligible to be grandfathered.
The NYISO proposes to apply the tests in Section 23.4.5.7.2 to make the Offer Floor and
exemption determinations and proposes the tariff modifications further explained below to
establish the procedures and rules necessary to issue those Offer Floor and exemption
determinations.
First, the NYISO proposes revisions that identify the projects that will be subject to an Offer Floor or exemption determination, by adding a new defined term “NCZ Examined
Project” to Section 23.2.1. An NCZ Examined Project is defined as:
“NCZ Examined Project” shall mean any Generator or UDR project that is
not exempt pursuant to 23.4.5.7.7 and either (i) is in a Class Year on the date
the Commission accepts the first ICAP Demand Curve to apply to a Mitigated
Capacity Zone, (ii) meets the criteria specified in 23.4.5.7.3(II), or (iii) meets
the criteria specified in 23.4.5.7.3(III) but the time period therein has passed on
the date the Commission accepts the first ICAP Demand Curve. An NCZ
Examined Project may be at any phase of development or in operation or an Installed Capacity Supplier.
The NYISO also proposes to revise the previously submitted definition of “Mitigation Net CONE”32 so that it will be applicable to NCZ Examined Projects in a Mitigated Capacity Zone. Specifically, the NYISO proposes to modify the definition as follows:
29 Id.
30 Id.
31 Id.
32 See EL11-42 Order at P 7, n. 11 (explaining that “Mitigation Net CONE” is a new term that NYISO proposed which is still pending Commission review in Docket No. ER10-2371-000 and
Ms. Kimberly D. Bose, Secretary
Page 11
For purposes of Section 23.4.5 of this Attachment H, “Mitigation Net
CONE” shall mean the capacity price on the currently effective In-CityICAP
Demand Curve for the Mitigated Capacity Zone corresponding to the average
amount of excess capacity above the In-CityMitigated Capacity Zone Installed
Capacity requirement, expressed as a percentage of that requirement, that
formed the basis for the ICAP Demand Curve approved by the Commission;
provided however that if there is not an effective ICAP Demand Curve and the
Commission has (i) accepted an ICAP Demand Curve for the Mitigated
Capacity Zone that will become effective when the Mitigated Capacity Zone is
first effective, then Mitigation Net CONE shall mean the capacity price on
such ICAP Demand Curve for the Mitigated Capacity Zone corresponding to
the average amount of excess capacity above the Indicative NCZ Locational
Minimum Installed Capacity Requirement, as applicable, expressed as a
percentage of that requirement that formed the basis for the ICAP Demand
Curve accepted by the Commission, or (ii) not accepted an ICAP Demand
Curve for the Mitigated Capacity Zone, but the ISO has filed an ICAP Demand
Curve for the Mitigated Capacity Zone pursuant to Services Tariff Section
5.14.1.2.11, the Mitigation Net CONE shall mean the capacity price on such ICAP Demand Curve corresponding to the average amount of excess capacity above the Indicative NCZ Locational Minimum Installed Capacity
Requirement, expressed as a percentage of that requirement, that formed the basis for such ICAP Demand Curve.
The NYISO also proposes several new subsections to Section 23.4.5.7 which provide
the processes and procedures used to evaluate NCZ Examined Projects for Offer Floor and
exemption determinations. New Section 23.4.5.7.2.1 provides that such determinations will
be made promptly after Commission acceptance of the first ICAP Demand Curve for the
NCZ, for projects which are in a completed Class Year. This timing is appropriate because it
ensures that the final determinations provided by the NYISO are consistent with the
Commission approved ICAP Demand Curves for the applicable Mitigated Capacity Zone.
For NCZ Examined Projects that are not in a completed Class Year, the NYISO
proposes revisions in Section 23.4.5.7.2 which provide for an Indicative BSM Determination.
As described in the Wyatt Affidavit, the Indicative BSM Determination provisions will allow
the NYISO to provide information to a project in a Class Year that is not yet completed and
before the Commission accepts the NCZ ICAP Demand Curve that would apply to the
stating that it represents “the price equal to what the Commission defined as the ‘net CONE’ used to design the NYC demand curves”).
Ms. Kimberly D. Bose, Secretary
Page 12
location of the project.33 An Indicative BSM Determination will provide a project with an
indication of whether it might be exempt, or an estimate of the Offer Floor that might apply to
the project.34 The proposed tariff revisions make clear that the Indicative BSM Determination
is not the determination that will apply to the project. The determination will be made using
the filed ICAP Demand Curve because it will provide the most accurate determination.35
The Indicative BSM Determination will be for informational purposes only, and the
Offer Floor or exemption determination that applies to the project will be made after
Commission acceptance of the first ICAP Demand Curve for the new Locality, based on the
Commission-accepted Locality ICAP Demand Curve. Once the Commission accepts an
ICAP Demand Curve for the new Locality, the NYISO will cease providing an Indicative
BSM Determination. The NYISO will then utilize the accepted ICAP Demand Curve to
examine and make examinations or Offer Floor determinations for projects that have received
CRIS where the relevant Class Year has been completed, and to examine and issue decisional
round determinations for projects that have not been removed from the Class Year
Deliverability Study, if the Class Year has not been completed. Such Indicative BSM
Determinations will be issued only if the NYISO has filed an ICAP Demand Curve for the
applicable NCZ.
New Section 23.4.5.7.2.3 requires NCZ Examined Projects to submit data and
information requested by the NYISO, in order to allow the NYISO to make the required
determinations. Related Section 23.4.5.7.2.6 provides that where a project fails to provide the
required information by the deadline provided by the NYISO, such project will be subject to
an Offer Floor, in accordance with Section 23.4.5.7. Additionally, Section 23.4.5.7.2.3
provides how the NYISO will compute the reasonably anticipated ICAP Spot Market Auction
forecast price to be used in making the determination. It will be based on Expected
Retirements and each NCZ Examined Project. Section 23.4.5.7.2.3.1 explains how Expected
Retirements will be determined and Section 23.4.5.7.2.3.2 explains what the load forecast will
be based on.
Section 23.4.5.7.2.4 requires the NYISO to post on its web site prior to making Offer
Floor or exemption determinations the inputs and ICAP Spot Market Auction forecast prices
in accordance with any confidentiality requirements, as well as Expected Retirements and
33 Wyatt Affidavit at P 11. See also, November 2011 Filing at 4 and Attachment I, Services Tariff § 5.14.1.2. ( providing that by November 30 in a Demand Curve Reset Year, the NYISO will file concurrent with ICAP Demand Curves for then-existing Localities and the NYCA, a proposed ICAP Demand Curves for any NCZ).
34 Id.
35 Id.
Ms. Kimberly D. Bose, Secretary
Page 13
NCZ Examined Projects. Section 23.4.5.7.2.4 sets forth revisions which establish that the
NYISO’s computation of the anticipated ICAP Spot Market Auction forecast price will, when
concurrently evaluating projects, assume that projects will clear from lowest to highest. For
each NCZ Examined Project the NYISO will use the lower of the project Unit Net CONE or
75 percent of Mitigation Net CONE. As with the other provisions, the buyer-side mitigation examination provisions use the same framework that presently exists for Examined Facilities. These new provisions accommodate the establishment of NCZs.36
Section 23.4.5.7.2.5 provides that the NYISO will seek comment from the MMU on
its calculations, and will inform NCZ Examined Projects of the relevant determinations in a
prompt manner. Section 23.4.5.7.2.7 provides that where an NCZ Examined Facility is
located in more than one NCZ, it will be evaluated based on where the project is electrically
located.
Finally, Section 23.4.5.7.3 has been modified to note that the term “Examined
Facility” does not include any facility found to be exempt from the Offer Floor pursuant to Section 23.4.5.7.7.
D.Other Revisions
The NYISO also proposes modifications to the term “Locality” which will allow the accommodation of “nested zones” as explained in the November 2011 Filing. The NYISO proposes to modify the definition of “Locality” as follows:
Locality: A single LBMP Load Zone or set of adjacent LBMP Load Zones
within one Transmission District or a set of adjacent Transmission Districts (or a portion of a Transmission District(s)) within which a minimum level of
Installed Capacity must be maintained, and as specifically identified in this subsection to mean (1) Load Zone J and (2) Load Zone K.
This modification is necessary to ensure that any future configuration of an NCZ, including
where an NCZ encompasses more than one Load Zone, is correctly accounted for in Load
Forecasts performed pursuant to Services Tariff Article 5.37 The NYISO’s November 2011
36 The rules apply only to projects in a Class Year coinciding with the NYISO’s filing of a Mitigated Capacity Zone. After the establishment of an NCZ, ICAP Demand Curves will be
applicable to such NCZ. Thus, any project in a Class Year will be considered an Examined Facility. As Examined Facilities, projects located in Mitigated Capacity Zones will be subject to examination under the Offer Floor and exemption determination in the current rules.
37 To the extent necessary, the NYISO requests leave to submit this modification, which was
inadvertently not included in the pending November 2011 Filing. The Commission has previously
Ms. Kimberly D. Bose, Secretary
Page 14
Filing makes clear in the definition of the proposed term “New Capacity Zone or NCZ” that a Locality cannot be smaller than a Load Zone.38
Additionally, minor corrections were made to (1) the previously submitted definition of “Mitigation Net CONE” to insert “ICAP” before the term “Demand Curve; and (2) remove extraneous internal numbering in 23.4.5.7.3.
IV. STAKEHOLDER AND MARKET MONITORING UNIT REVIEW
The NYISO made presentations at three meetings of its Installed Capacity Working
Group (i.e., April 16, May 22, and June 19, 2012) in which it described the proposed
mitigation measures and reviewed proposed tariff revisions that comprised the expected
content of this compliance filing. The NYISO circulated the draft tariff revisions to
stakeholders for their review prior to each meeting. There were extensive discussions at each of the meetings, and an opportunity to provide any additional comments in writing. The
NYISO considered stakeholders’ comments and made modifications based on those
comments in order to enhance the filing.
In addition, the MMU was given an opportunity to review and comment on the
proposed compliance tariff revisions. The NYISO carefully considered and incorporated the MMU’s recommendations in this compliance filing.
V.REQUESTED EFFECTIVE DATE
The NYISO requests that the Commission accept these proposed modifications
effective September 1, 2012 or the effective date the Commission accepts for the tariff
revisions proposed in the November 2011 Filing. Since the effective date requested in the November 2011 Filing has passed and the filing is still pending, an effective date of
September 1, 2012, or the date accepted for the November 2011 Filing revisions will ensure that these proposed NCZ Market Mitigation Measures are in place by the time the NYISO begins the triennial NCZ Study process.39
VI.SERVICE
authorized the NYISO to include these kinds of limited, but necessary, clarifications in compliance filings and should follow that precedent here. See New York Independent System Operator, Inc., 125 FERC ¶ 61,206 (2008), reh’g, 127 FERC ¶ 61,042 (2009) (accepting proposed tariff revisions
necessary to correct drafting errors or ambiguities).
38 See November 2011 Filing at 3 and Attachment I at Services Tariff § 2.14.
39 See id. at 4.
Ms. Kimberly D. Bose, Secretary
Page 15
This filing will be posted on the NYISO’s website at www.nyiso.com. In addition, the
NYISO will e-mail an electronic link to this filing to the official representative of each party
to this proceeding, to each of its customers, to each participant on its stakeholder committees,
to the New York Public Service Commission, and to the New Jersey Board of Public Utilities.
VII. CONCLUSION
Wherefore, for the foregoing reasons, the New York Independent System Operator, Inc. respectfully requests that the Commission accept this compliance filing to become effective as specified herein.
Respectfully submitted,
/s/ Vanessa A. Colón___________________
Vanessa A. Colón
Counsel for the
New York Independent System Operator, Inc.
cc:Michael A. Bardee
Gregory Berson
Connie Caldwell
Anna Cochrane
Jignasa Gadani
Lance Hinrichs
Jeffrey Honeycutt
Michael Mc Laughlin
Kathleen E. Nieman
Daniel Nowak
Rachael Spiker
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person
designated on the official service list compiled by the Secretary in this proceeding in accordance with the requirements of Rule 2010 of the Rules of Practice and Procedure, 18 C.F.R. §385.2010.
Dated at Rensselaer, NY this 29th day of July, 2012.
/s/ Joy A. Zimberlin
Joy A. Zimberlin
New York Independent System Operator, Inc
10 Krey Blvd.
Rensselaer, NY 12144 (518) 356-6207