10 Krey Boulevard Rensselaer, NY 12144
June 30, 2015
By Electronic Delivery
Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE
Washington, DC 20426
Re: Filing of an Executed Engineering, Procurement, and Construction Agreement
Among the New York Independent System Operator, Inc., Central Hudson Gas &
Electric Corp., and CPV Valley, LLC; and Request for Waiver of the 60-Day
Notice Period; Docket No. ER15-___000
Dear Ms. Bose:
Pursuant to Section 205 of the Federal Power Act1 and Section 35.12 of the
Commission’s regulations,2 the New York Independent System Operator, Inc. (“NYISO”)
hereby tenders for filing an executed engineering, procurement, and construction agreement (“EPC Agreement”) among the NYISO, Central Hudson Gas & Electric Corp. (“Central
Hudson”), and CPV Valley, LLC (“CPV”). The EPC Agreement is labeled as Service
Agreement No. 2218.
CPV is developing a nominal 680 MW combined-cycle generating facility (“Facility”)
that will interconnect with the transmission facilities of the New York Power Authority
(“NYPA”). The NYISO’s Class Year 2011 Interconnection Facilities Study (“Facilities Study”)
determined that this interconnection will also have impacts on Central Hudson’s transmission
system, which is part of the New York State Transmission System.3 The Facilities Study
identified certain System Upgrade Facilities that are required on Central Hudson’s system for the
Facility to interconnect reliably to the New York State Transmission System. The EPC
Agreement governs the rates, terms, and conditions regarding the engineering, procurement, and
construction of the System Upgrade Facilities on Central Hudson’s transmission system. The
EPC Agreement is based on and generally conforms with the pro forma Large Generator
Interconnection Agreement (“Pro Forma LGIA”) contained in Attachment X to the NYISO Open
Access Transmission Tariff (“OATT”).
The NYISO respectfully requests that the Commission accept the EPC Agreement for
filing. Further, as described in Part III of this letter, the NYISO respectfully requests a waiver of
1 16 U.S.C. § 824d (2014).
2 18 C.F.R. § 35.12 (2014).
3 Capitalized terms that are not otherwise defined in this filing shall have the meaning specified in
Attachments X and S of the NYISO OATT, and if not defined therein, in Section 1 of the NYISO OATT.
Honorable Kimberly D. Bose June 30, 2015
Page 2
the Commission’s prior notice requirements4 to make the EPC Agreement effective as of June 3, 2015, which is the date of its execution.
I.BACKGROUND
CPV is developing a nominal 680 MW combined-cycle generating facility that will be
located in Orange County, New York. The Facility will interconnect to certain transmission
facilities of NYPA that are part of the New York State Transmission System. CPV’s Facility
was included in and studied as part of the Class Year 2011 Facilities Study. The Facilities Study determined that the interconnection of the Facility will have certain impacts on the transmission system of Central Hudson and identified Central Hudson as an Affected Transmission Owner.5 The Facilities Study identified certain System Upgrade Facilities that must be constructed on
Central Hudson’s system to provide for the reliable interconnection of the Facility to the New
York State Transmission System (“Affected System Upgrade Facilities”). CPV accepted, and
provided security to Central Hudson to cover, the costs identified in the Facilities Study for the construction of the Affected System Upgrade Facilities.
The NYISO and NYPA, as the Connecting Transmission Owner, have jointly filed an
executed Large Generator Interconnection Agreement among the NYISO, NYPA, and CPV for the interconnection of the Facility to the transmission facilities of NYPA (“CPV LGIA”).6 In the CPV LGIA, the parties indicated that the construction of the Affected System Upgrade Facilities on Central Hudson’s system would be addressed through a separate EPC Agreement among the NYISO, Central Hudson, and CPV. Consistent with Commission precedent and NYISO
practice, the EPC Agreement for the construction of the Affected System Upgrade Facilities was developed using the Pro Forma LGIA as a template.7
4 See Prior Notice and Filing Requirements Under Part II of the Federal Power Act, 64 FERC ¶ 61,139, clarified, 65 FERC ¶ 61,081 (1993).
5 The Facilities Study also identified that the interconnection of the Facility will have certain
impacts on the transmission system of the New York State Electric & Gas Corp. (“NYSEG”) and
identified NYSEG as an Affected Transmission Owner as well. The NYISO is separately filing an EPC Agreement among the NYISO, NYSEG, and CPV for the engineering, procurement, and construction of the System Upgrade Facilities that are required on NYSEG’s system for the Facility to interconnect reliably to the New York State Transmission System.
6 New York Independent System Operator, Inc. and New York Power Authority, Filing of
Executed Large Generator Interconnection Agreement Among the New York Independent System
Operator, Inc., the New York Power Authority, and CPV Valley, LLC; Request for Waiver of 60-Day
Notice Period; and Request for Critical Energy Infrastructure Information Designation, Docket No. ER15-
1895-000 (June 10, 2015).
7 There is no pro forma EPC Agreement in the NYISO OATT. The EPC Agreement is based on
the Pro Forma LGIA, consistent with Commission precedent. See New York Independent System
Operator, Inc., and Niagara Mohawk Power Corporation, Letter Order, Docket No. ER08-230-000
(December 18, 2007); see also Midwest Independent Transmission System Operator, Inc., 113 FERC ¶
61,048 (2005); Duke Electric Transmission, a Division of Duke Energy Corp., 113 FERC ¶ 61,139
(2005).
Honorable Kimberly D. Bose June 30, 2015
Page 3
II. DESCRIPTION OF THE EPC AGREEMENT
Central Hudson, as the Affected Transmission Owner, will engineer, procure, and
construct the Affected System Upgrade Facilities in accordance with the terms of the EPC
Agreement (“EPC Services”). CPV has posted security to Central Hudson to cover the costs of
constructing these facilities identified in the Facilities Study in accordance with the requirements
in Attachment S of the NYISO OATT. Any differences in cost between the posted security and
the final cost of constructing the facilities will be allocated in accordance with the tariff
requirements for addressing such differences in Section 25.8.6 of Attachment S of the NYISO
OATT. The NYISO’s role in the EPC Agreement will be limited to certain oversight rights and
responsibilities.
The EPC Agreement is based on the Pro Forma LGIA, as modified: (i) to reflect the
different purpose of the agreement, (ii) to allocate the parties’ responsibilities for the
performance of the EPC Services and the payment for such performance, and (iii) to set forth the scope of work, cost estimate, and milestone schedule for the construction of the Affected System Upgrade Facilities.
The EPC Agreement varies from the Pro Forma LGIA primarily as follows, consistent
with the approach the Commission approved with regard to a similar EPC agreement in 2007:8
• The EPC Agreement governs only the performance of the EPC Services and
terminates upon the completion of the Affected System Upgrade Facilities and the payment of related invoices. For this reason, the EPC Agreement does not include the provisions of the Pro Forma LGIA that govern the ongoing operation or
maintenance of the constructed facilities.9
• The EPC Agreement is limited to the activities required to construct and place in
service the Affected System Upgrade Facilities. For this reason, the EPC Agreement does not include the provisions of the Pro Forma LGIA that govern the activities
required to construct and place in-service the Large Generating Facility, the
Attachment Facilities, other System Upgrade Facilities, or System Deliverability
Upgrades. These requirements are addressed under the CPV LGIA among the
NYISO, NYPA, and CPV.
• The EPC Agreement does not include the provisions of the Pro Forma LGIA that
govern the NYISO’s provision of interconnection service to CPV, which is addressed under the CPV LGIA among the NYISO, NYPA, and CPV.
8 See New York Independent System Operator, Inc., and Niagara Mohawk Power Corporation, Letter Order, Docket No. ER08-230-000 (December 18, 2007).
9 Once completed, Central Hudson will own the Affected System Upgrade Facilities and be
responsible for their operation and maintenance. The requirements for the ongoing operation and
maintenance of the Facility are set forth in the CPV LGIA among the NYISO, NYPA, and CPV.
Honorable Kimberly D. Bose June 30, 2015
Page 4
• As Central Hudson will perform the EPC Services, the EPC Agreement does not
include the provisions of the Pro Forma LGIA that address the developer’s options
and responsibilities for performing such work.
• As the parties have already completed the interconnection studies necessary to
determine the impact of the interconnection, the EPC Agreement does not include the provisions of the Pro Forma LGIA that address such studies.
• The EPC Agreement replaces the use of the term “Connecting Transmission Owner”
(i.e., NYPA”) with “Affected Transmission Owner” (i.e., Central Hudson), except
where the language is referring to the interconnection of CPV’s Facility with NYPA’s
transmission facilities.
• The EPC Agreement also includes minor clean-ups and revisions that are consistent
with the terms of the EPC Agreement.
The NYISO provides in Attachment I of this filing letter a matrix that describes in greater detail the differences between the EPC Agreement and the Pro Forma LGIA.10
III. EFFECTIVE DATE AND REQUEST FOR WAIVER
The NYISO requests an effective date of June 3, 2015, for the EPC Agreement, which is the date of its execution. The NYISO respectfully requests that the Commission waive its prior notice requirement to permit the requested effective date. The Commission has previously
permitted similar agreements to become effective upon the date of execution.11
10 As described in this filing letter, “Connecting Transmission Owner” has been replaced with
“Affected Transmission Owner” throughout the EPC Agreement with limited exceptions. The NYISO
has not highlighted this change, which applies in most provisions of the EPC Agreement, in the matrix in
Attachment I.
11 See, e.g., New York Independent System Operator, Inc. and New York State Electric & Gas
Corporation, Docket No. ER11-2953-000 (April 7, 2011) (accepting interconnection agreement effective as of date of execution); see also New York Independent System Operator, Inc. and Niagara Mohawk Power Corp., Letter Order, Docket No. ER08-985-000 (June 26, 2008) (same); New York Independent System Operator, Inc. and New York Power Authority, Letter Order, Docket No. ER08-861-000 (May 27, 2008) (same); New York Independent System Operator, Inc. and New York Power Authority, Letter
Order, Docket No. ER08-699-000 (May 16, 2008) (same).
Honorable Kimberly D. Bose June 30, 2015
Page 5
IV. COMMUNICATIONS AND CORRESPONDENCE12
Communications regarding this filing should be directed to:
Robert E. Fernandez, General Counsel
Karen Georgenson Gach, Deputy General Counsel
*Sara B. Keegan, Senior Attorney
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
Tel: (518) 356-6000
Fax: (518) 356-4702
skeegan@nyiso.com
*Designated to receive service.
V.DOCUMENTS SUBMITTED
*Ted J. Murphy
Hunton & Williams LLP
2200 Pennsylvania Avenue, NW Washington, D.C. 20037
Tel: (202) 955-1500
Fax: (202) 778-2201
tmurphy@hunton.com
*Michael J. Messonnier Jr. Hunton & Williams LLP 951 East Byrd Street
Richmond, VA 23219
Tel: (804) 788-8200
Fax: (804) 344-7999
mmessonnier@hunton.com
The NYISO submits the following documents:
• this filing letter;
• the matrix describing the differences between the EPC Agreement and the Pro Forma
LGIA (Attachment I);
• a clean version of the EPC Agreement (Attachment II);
• a blacklined version of the EPC Agreement showing the changes from the body of the
Pro Forma LGIA (Attachment III); and
• the signature pages for the EPC Agreement (Attachment IV). VI. SERVICE
The NYISO will send an electronic link to this filing to the official representative of each of its customers, to each participant on its stakeholder committees, to the New York Public
12 The NYISO respectfully requests waiver of 18 C.F.R. § 385.203(b)(3) (2014) to permit service on counsel in both Washington, D.C. and Richmond, VA.
Honorable Kimberly D. Bose June 30, 2015
Page 6
Service Commission, and to the New Jersey Board of Public Utilities. In addition, a complete
copy of the documents included with this filing will be posted on the NYISO’s website at
www.nyiso.com.
VII. CONCLUSION
Wherefore, the NYISO respectfully requests that the Commission accept the EPC Agreement for filing with an effective date of June 3, 2015.
Respectfully submitted,
/s/ Sara B. Keegan
Sara B. Keegan
Counsel for the
New York Independent System Operator, Inc.
cc:Michael Bardee
Gregory Berson
Anna Cochrane
Morris Margolis
David Morenoff
Daniel Nowak
Kathleen Schnorf
Jamie Simler
Kevin Siqveland