FEDERAL ENERGY REGULATORY COMMISSION
WASHINGTON, D.C. 20426
OFFICE OF ENERGY MARKET REGULATION
New York Independent System
Operator, Inc.
Docket No. ER17-830-000
Issued: 2/21/17
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, New York 12144
Attention:Sara B. Keegan
Senior Attorney
Reference: Interconnection Tariff Revisions Dear Ms. Keegan:
On January 23, 2017, New York Independent System Operator, Inc. (NYISO)
filed proposed revisions to the interconnection procedures set forth in Attachments S
(section 25) and X (section 30) of its Open Access Transmission Tariff (OATT).1
NYISO states that the proposed revisions improve upon the interconnection study process by providing developers with additional flexibility in addressing the regulatory milestone requirement that must be met for a project to enter into a Class Year Interconnection
Facilities Study.
Pursuant to the authority delegated to the Director, Division of Electric Power Regulation - East, under 18 C.F.R. § 375.307, your submittal is accepted for filing, effective February 22, 2017, as requested.
The filing was noticed on January 25, 2017, with comments, interventions, and
protests due on or before February 2, 2017. Pursuant to Rule 214 (18 C.F.R. § 385.214
1 New York Independent System Operator, Inc., NYISO Tariffs, NYISO OATT, Open Access Transmission Tariff (OATT), 0.0.0, NYISO OATT, 25 OATT Attachment S - Rules To Allocate Responsibility For, 0.0.0, and NYISO OATT, 25.6 OATT Att S Cost Allocation Methodology For ERIS, 4.0.0
Docket Nos. ER17-830-0002
(2016)), to the extent that any timely filed motions to intervene and any motion to
intervene out-of-time were filed before the issuance date of this order, such interventions are granted. Granting late interventions at this stage of the proceeding will not disrupt the proceeding or place additional burdens on existing parties.
This acceptance for filing shall not be construed as constituting approval of the referenced filing or of any rate, charge, classification, or any rule, regulation, or practice affecting such rate or service contained in your filing; nor shall such acceptance be
deemed as recognition of any claimed contractual right or obligation associated
therewith; and such acceptance is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against NYISO.
This order constitutes final agency action. Requests for rehearing by the
Commission may be filed within 30 days of the date of issuance of this order, pursuant to
18 C.F.R. § 385.713.
Sincerely,
Kurt M. Longo, Director Division of Electric Power Regulation - East