FEDERAL ENERGY REGULATORY COMMISSION
WASHINGTON, D.C. 20426

 

 

OFFICE OF ENERGY MARKET REGULATION

 

New York Independent System Operator, Inc. Docket No. ER11-2547-007

 

Issued:  11/14/12

 

 

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144

 

Attention: James H. Sweeny, Esquire

Council to the New York Independent System Operator, Inc.

Reference:   Compliance Filing on Scheduling at Keystone Proxy Buses Dear Mr. Sweeny:

On October 12, 2012, the New York Independent System Operator, Inc. (NYISO) filed tariff revisions in compliance with the Commission’s March 14, 2011 order.1  The revisions reflect an updated timetable for the phased implementation of intra-hour (i.e., 15-minute) transaction scheduling at the PJM Neptune proxy generation bus.  This filing is in satisfactory compliance with the March 14 order.

Pursuant to the authority delegated to the Director, Division of Electric Power Regulation - East, under 18 C.F.R. §375.307, your submittal is accepted for filing, effective October 30, 2012 as requested.

 

The filing was noticed on October 12, 2012, with comments, protests, or

interventions due on or before November 2, 2012.  Pursuant to Rule 214 (18 C.F.R. §

385.214 (2011)), to the extent that any timely filed motions to intervene and any motion to intervene out-of-time were filed before the issuance date of this order, such
interventions are granted.  Granting late interventions at this stage of the proceeding will not disrupt the proceeding or place additional burdens on existing parties.

This acceptance for filing shall not be construed as constituting approval of the

 

1 New York Independent System Operator, Inc., 134 FERC ¶ 61,186 (2011)


 

 

Docket No. ER11-2547-0072

 

referenced filing or of any rate, charge, classification, or any rule, regulation, or practice affecting such rate or service contained in your filing; nor shall such acceptance be
deemed as recognition of any claimed contractual right or obligation associated
therewith; and such acceptance is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against NYISO.

 

This order constitutes final agency action.  Requests for rehearing by the

Commission may be filed within 30 days of the date of issuance of this order, pursuant to

18 C.F.R. § 385.713.

 

Sincerely,

 

 

 

Jignasa Gadani, Director Division of Electric Power Regulation - East


 

 

 

 

 

FEDERAL ENERGY REGULATORY COMMISSION
WASHINGTON, D.C.  20426

 

OFFICE OF ENERGY MARKET REGULATION

 

New York Independent System Operator, Inc. Docket No. ER11-2547-007

 

Issued:  11/19/12

 

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144

 

Attention: James H. Sweeny, Esquire

Council to the New York Independent System Operator, Inc.

Reference:   Errata to Letter Order Issued November 14, 2012 Dear Mr. Sweeny:

On November 14, 2012, the Commission issued a letter order in the above proceeding to the New York Independent System Operator, Inc.

 

The proxy bus for intra-hour (i.e., 15-minute) transaction scheduling was

incorrectly identified as the Keystone bus in the Reference line of the letter.  The

Reference line should have indicated the Neptune proxy bus as indicated in the body of the letter.

 

Sincerely,

 

 

 

Jignasa Gadani, Director Division of Electric Power Regulation - East