Docket ER25-1352-000 1

FEDERAL ENERGY REGULATORY COMMISSION

WASHINGTON, DC  20426

 

OFFICE OF ENERGY MARKET REGULATION

 

 

 New York Independent System Operator, Inc.

Docket No. ER25-1352-000

       

Issued:  April 15, 2025

 

On February 20, 2025, New York Independent System Operator, Inc. (NYISO) submitted an amended Large Generator Interconnection Agreement among NYISO as Transmission Provider, Long Island Lighting Company as Transmission Owner, and Riverhead Solar 2, LLC as Developer.[1]  NYISO requested that the filing be accepted effective February 12, 2025.  Pursuant to authority delegated to the Director, Division of Electric Power Regulation – East, under 18 C.F.R. § 375.307, the submittal is accepted for filing, effective February 12, 2025, as requested.[2]

 

The filing was publicly noticed.  No protests or adverse comments were filed.  Pursuant to Rule 214 of the Commission’s regulations (18 C.F.R. § 385.214), notices of intervention, timely-filed motions to intervene, and any unopposed motions to intervene out-of-time filed before the issuance date of this order are granted.
 

This action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed document(s); nor shall such action be deemed as recognition of any claimed contractual right or obligation affecting or relating to such service or rate; and such action is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against the applicant(s).

 

This order constitutes final agency action.  Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F.R. § 385.713.

Issued by:  Kurt M. Longo, Director, Division of Electric Power Regulation – East


[1] New York Independent System Operator, Inc., NYISO Agreements, Agreement No. 2740, LGIA among NYISO, LIPA, and Riverhead Solar 2 (1.0.0).

[2] See 18 C.F.R. § 35.3(a)(2).