Docket No. RM21-17-000  1

UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION

 

 

Building for the Future Through Electric Regional Transmission Planning and Cost Allocation

Docket No.

RM21-17-000

 

 

NOTICE OF EXTENSION OF TIME

 

(March 24, 2025)

 

 On February 21, 2025, New York Independent System Operator, Inc. (NYISO) filed a motion in the above-captioned proceeding requesting that the Commission grant an extension of time, until April 30, 2026, to make a compliance filing to meet all requirements of Order No. 1920,[1] except those related to interregional transmission coordination.  NYISO also requests an extension of time, until June 14, 2027, to make a compliance filing to meet all the interregional transmission coordination requirements of Order No. 1920.  NYISO states that good cause exists to grant its requested extensions because they will enable NYISO to:  (1) continue its coordination with the New York State Department of Public Service to address the alignment of the new Long-Term Regional Transmission Planning process with the state’s transmission planning efforts; (2) provide sufficient time to develop and review the transmission planning reforms with Relevant State Entities, transmission owners, and other NYISO stakeholders; and (3) coordinate with its neighboring transmission planning regions to reflect the long-term transmission planning reforms in the interregional transmission coordination processes.

New York Transmission Owners filed an answer in support of NYISO’s motion. 

Upon consideration, NYISO’s request for extension of time is hereby granted and the deadline for NYISO to submit its compliance filing to meet all requirements of Order No. 1920, except those related to interregional transmission coordination, is extended to and including April 30, 2026. 

Upon consideration, NYISO’s request for extension of time is hereby granted and the deadline for NYISO to submit its compliance filing to meet the interregional

transmission coordination requirements of Order No. 1920 is extended to and including June 14, 2027.

 

 

Carlos D. Clay,

 Deputy Secretary.

 

 

 

 

 

 


[1] Bldg. for the Future Through Elec. Reg’l Transmission Planning & Cost Allocation, Order No. 1920, 187 FERC ¶ 61,068, order on reh’g, Order No. 1920-A, 189 FERC ¶ 61,126 (2024).