Docket No. ER24-2096-001 1

FEDERAL ENERGY REGULATORY COMMISSION

WASHINGTON, DC  20426

 

OFFICE OF ENERGY MARKET REGULATION

 

New York Independent System Operator, Inc.  

Docket No. ER24-2096-001

       

Issued:  October 24, 2024

 

On August 22, 2024, New York Independent System Operator, Inc. (NYISO) submitted revisions to sections 5.12 and 5.14 of its Market Administration and Control Area Services Tariff to modify the implementation timeline for tariff revisions regarding fuel characteristic elections and related market rules from the 2025-2026 Capability Year to the 2026-2027 Capability Year,[1] in compliance with the directives in a July 23, 2024 Commission order.[2]  NYISO requested that the filing be accepted effective July 24, 2024.  Pursuant to authority delegated to the Director, Division of Electric Power Regulation – East under 18 C.F.R. § 375.307, the submittal is accepted for filing, effective July 24, 2024, as requested.

 

The filing was publicly noticed.  No protests or adverse comments were filed.  Pursuant to Rule 214 of the Commission’s regulations (18 C.F.R. § 385.214), notices of intervention, timely-filed motions to intervene, and any unopposed motions to intervene out-of-time filed before the issuance date of this order are granted. 
 

This action does not constitute approval of any service, rate, charge, classification, or any rule, regulation, contract, or practice affecting such rate or service provided for in the filed document(s); nor shall such action be deemed as recognition of any claimed contractual right or obligation affecting or relating to such service or rate; and such action is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against the applicant(s).

 

This order constitutes final agency action.  Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F.R. § 385.713.

Issued by:  Kurt M. Longo, Director, Division of Electric Power Regulation – East


[1] New York Independent System Operator, Inc., NYISO Tariffs, NYISO MST, 5.12 MST Requirements Applicable to Installed Capacity Suppl (50.0.0); NYISO MST, 5.14 MST Installed Capacity Spot Market Auction and Installe (42.0.0)

[2] N.Y. Indep. Sys. Operator, Inc., 188 FERC ¶ 61,051 (2024).