On May 22, 2023, the Commission issued a delegated letter order in the above-referenced docket. The delegated letter order incorrectly characterized the service agreement submitted as a Large Generator Interconnection Agreement. The agreement submitted is a Small Generator Interconnection Agreement. This errata notice hereby corrects the description of the service agreement in the first sentence to “an executed Amended and Restated Small Generator Interconnection Agreement among NYISO, Niagara Mohawk as the connecting transmission owner, and Regan Solar, LLC as the interconnection customer.”