Docket No. ER22-1201-000 1
FEDERAL ENERGY REGULATORY COMMISSION
WASHINGTON, DC 20426
OFFICE OF ENERGY MARKET REGULATION
In Reply Refer To:
New York Independent System Operator, Inc.,
Niagara Mohawk Power Corporation
Issued: April 28, 2022
National Grid USA
40 Sylvan Road
Waltham, MA 02451
Attention:David Lodemore, Esq.
Reference:Smart Path Connect Project Cost Recovery and Incentive Rate Treatment
On March 4, 2022, New York Independent System Operator, Inc. (NYISO) filed, on behalf of Niagara Mohawk Power Corporation (Niagara Mohawk), pursuant to section 205 and 219 of the Federal Power Act (FPA),[1] 18 C.F.R. Part 35, and Order No. 679,[2] proposed amendments to NYISO’s Open Access Transmission Tariff (OATT) to allocate and recover the costs of Niagara Mohawk’s investment in the Smart Path Connect Project (Project), along with a request for authorization of certain transmission rate incentives associated with the Project.[3]
Please be advised that your filing is deficient, and that additional information is required in order to process the filing. Please provide the information requested below.
This letter is issued pursuant to 18 C.F.R. § 375.307 and is interlocutory. This letter is not subject to rehearing under 18 C.F.R. § 385.713. A response to this letter must be filed with the Secretary of the Commission within 30 days of the date of this letter by making a deficiency filing in accordance with the Commission’s electronic tariff requirements. For your response, use Type of Filing Code 170 if your company is registered under program code “M” (Electric Market Based Rate Public Utilities) or Type of Filing Code 180 if your company is registered under program code “E” (Electric Traditional Cost of Service and Market Based Rates Public Utilities).[6] In addition, submit an electronic version of your response to Stephanie Eyocko at JackyNicole.Eyocko@ferc.gov. The information requested in this letter order will constitute an amendment to your filing and a new filing date will be established.[7] A notice will be issued upon receipt of your filing.
Pending receipt of the above information, a filing date will not be assigned to your filing. Failure to respond to this letter order within the time period specified may result in a further order rejecting your filing.
Issued by: Kurt M. Longo, Director, Division of Electric Power Regulation – East
[1] 16 U.S.C. § 824d.
[2] Promoting Transmission Investment through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057, order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006), order on reh’g, 119 FERC ¶ 61,062 (2007).
[3] New York Independent System Operator, Inc., NYISO Tariffs, NYISO OATT, 6.18 OATT Schedule 18 Rate Mechanism for the Recovery of the (0.0.0), and NYISO OATT, 14.2-14.2.1 OATT Att H Attachment 1 to Attachment H (21.0.0).
[4] We note that Mr. Adrien M. McKenzie’s testimony in Exhibit Nos. NMPC-300 – NMPC-311 is based on Niagara Mohawk’s financial situation, rather than on the Project.
[5] See New York Power Assn. v. Niagara Mohawk Power Corp., 151 FERC ¶ 61,121 (2015) (order approving Niagara Mohawk's filing of an Offer of Settlement and Settlement Agreement and approving, inter alia, section 2.1 of the Settlement Agreement, an ROE of “10.3 percent, inclusive of any incentive adders”).
[6] The filing must include at least one tariff record to restart the statutory timeframe for Commission action even though a tariff revision might not otherwise be needed. See generally Elec. Tariff Filings, 130 FERC ¶ 61,047, at PP 3-8 (2010) (explaining that the Commission uses the data elements resulting from the tariff filing process to establish statutory filing and other procedural dates).
[7] See Duke Power Co., 57 FERC ¶ 61,215, at 61,713 (1991) (“the Commission will consider any amendment or supplemental filing filed after a utility’s initial filing . . . to establish a new filing date for the filing in question”).