-2-

176 FERC ¶ 62,124

UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION

 

 

Hecate Energy Green County 3 LLC

                v.

Central Hudson Gas & Electric Corporation

New York Independent System Operator, Inc.

   Docket No.

EL21-49-001

 

 

NOTICE OF DENIAL OF REHEARING BY OPERATION OF LAW AND PROVIDING FOR FURTHER CONSIDERATION

 

(September 13, 2021)

 

Rehearing has been timely requested of the Commissions order issued on
July 15, 2021, in this proceedingHecate Energy Green County 3 LLC v. Central Hudson Gas & Electric Corporation, 176 FERC ¶ 61,023 (2021)In the absence of Commission action on the request for rehearing within 30 days from the date the request was filed, the request for rehearing (and any timely requests for rehearing filed subsequently)[1] may be deemed denied. 16 U.S.C. § 825l(a); 18 C.F.R. § 385.713 (2020); Allegheny Def. Project v. FERC, 964 F.3d 1 (D.C. Cir. 2020) (en banc).

 

As provided in 16 U.S.C. § 825l(a), the rehearing request of the above-cited order filed in this proceeding will be addressed in a future order to be issued consistent with the requirements of such sectionAs also provided in 16 U.S.C. § 825l(a), the Commission may modify or set aside its above-cited order, in whole or in part, in such manner as it shall deem properAs provided in 18 C.F.R. § 385.713(d), no answers to the rehearing request will be entertained. 

 

 

 

 

 

Debbie-Anne A. Reese,

Deputy Secretary.

 

 


[1] See San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs. Into Mkts. Operated by Cal. Indep. Sys. Operator & Cal. Power Exch., 95 FERC ¶ 61,173 (2001).